Home / Browse projects / Raigarh, Maharashtra / Plot No. 19 Sector-14 Kharghar Bus Terminus
Plot No. 19 Sector-14 Kharghar Bus Terminus
By CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED
RG-MH-29175 · RERA P52000028204 · Last updated on MahaRERA portal: 24 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 25 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Plot No. 19 Sector-14 Kharghar Bus Terminus is a Others project by CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000028204 on 10 Feb 2021. Possession is promised by 31 Jul 2027. The completion date has moved by 25 months from the original filing. 229 of the 350 units on this registration are recorded sold or booked, and 18 of 33 construction stages are filed complete.
At a glance
Project
- NamePlot No. 19 Sector-14 Kharghar Bus Terminus
- TypeOthers
- Location
- Sector-14
- Kharghar
- Panvel
- Raigarh
- 410210
- Pincode410210
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000028204
- ReraGenie IDRG-MH-29175
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Feb 2021
- Promised completion31 Jul 2027
- Revised completionRevised to 31 Jul 2027 (originally 30 Jun 2025)
- Buildings3 building records
- Documents filed94 files
Current status
Figures as on 24 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E-B-01 | NA | 27 | 22 | 170 | 0 | 170 |
| E-B-02 | NA | 27 | 22 | 170 | 0 | 170 |
| Commercial | NA | 1 | 1 | 0 | 10 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 97%.
E-B-0190%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 43% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
E-B-0290%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 97% |
| Sanitary Fittings within the flats / premises | 43% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 85% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Commercial82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 94% |
| Sanitary Fittings within the flats / premises | 3% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Progress on shared amenities15
As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 75% |
| Water Supply | Yes | 65% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 10% |
| Street Lighting | Yes | 5% |
| Community Buildings | Yes | 80% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 5% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 65% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed93
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| E-B-01 | 43 | 43 |
| E-B-02 | 43 | 43 |
| Commercial | 7 | 7 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| E-B-01 | NA | Rs 28.14 cr | Rs 28.14 cr |
| E-B-02 | NA | Rs 28.14 cr | Rs 28.14 cr |
| - | NA | Rs 18.72 cr | Rs 6.24 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Architect Hafeez Contractor |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | Rutuja Narsingh & Associates |
| Chartered Accountant | N B Sayed& Associates |
| Partner | Role in project |
|---|---|
| CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions and coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31/12/2030 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval of this reques
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Feb 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Feb 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Jul 2027
Documents filed94
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 94 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Kharghar Bus Terminus as on March 2026.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Kharghar Bus Terminus as on March 2026.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - Kharghar Bus Terminus as on Dec 2025.pdf | 24 Jun 2026 |
| Form 5 (FY 2024-2025)File: Final Form 5 of Kharghar Bus Terminus as on 31-03-2025.pdf | 8 Jun 2026 |
| Building plan approvalFile: 1-2.pdf | 23 Feb 2026 |
| Building plan approvalFile: 3-6.pdf | 23 Feb 2026 |
| Building plan approvalFile: 7-11.pdf | 23 Feb 2026 |
| Building plan approvalFile: 12-14.pdf | 23 Feb 2026 |
| Layout approvalFile: Layout.pdf | 23 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Kharghar Bus Terminus as on June 2025.PDF | 23 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Kharghar Bus Terminus as on Sept 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Kharghar Bus Terminus as on Dec 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Kharghar Bus Terminus as on June 2025.PDF | 23 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Kharghar Bus Terminus as on Sept 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Kharghar Bus Terminus as on Dec 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Kharghar Bus Terminus as on June 2025.PDF | 23 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Kharghar Bus Terminus as on Sept 2025.pdf | 23 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Kharghar Bus Terminus as on Dec 2025.pdf | 23 Feb 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus as on 31-03-2025.pdf | 20 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 of Kharghar Bus Terminus as on FY 2023-24.pdf | 19 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Terminus as on March 2025.pdf | 14 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Kharghar Bus Terminus as on March 2025.pdf | 16 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus as on 31-12-2024.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus as on 30-09-2024.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus as on 30-06-2024.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus as on 31-03-2024.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Terminus as on March 2024.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Terminus as on June 2024.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Terminus as on Sep 2024.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Kharghar Bus Terminus as on Dec 2024.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus - Sep 23.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus - Dec 23 (Change As on Date year).pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus - Mar 24.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus - June 24.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus - Sep 24.pdf | 15 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus - Dec 24 (Change As on Date year).pdf | 15 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBT DEC2023_compressed.pdf | 13 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBT SEPT2023_compressed.pdf | 13 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBT JUN2023_compressed.pdf | 13 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KHBT MAR2023_compressed.pdf | 13 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vashi Truck Terminal Sec-19 30623.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vashi Truck Terminal Sec-19 30923.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vashi Truck Terminal Sec-19 301223.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Vashi Truck Terminal Sec-19 30323.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 2023 KHBD.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jun 2023 Form-II KHBD.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 2023 Form-II KHBD.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sept 2023 KHBD.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus June 23.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus Sept 23.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kharghar Bus Terminus Dec 23.pdf | 3 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Kharghar Bus Terminal FY 20-21.pdf | 19 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kalamboli Bus Depot FY 22-23.pdf | 19 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Kharghar Bus Terminal FY 21-22.pdf | 19 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Kharghar Bus Terminal FY 22-23.pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form- 2A -Plot 19 Kharghar.pdf | 13 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf | 24 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf | 7 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s Certificate on Cost Incurred on Project.pdf | 7 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 2 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate on Quality Assurance .pdf | 2 Jun 2023 |
| Declaration about Commencement CertificateFile: Format D- Kharghar Bus Terminus.pdf | 1 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Circular 29- Kharghar Bus Terminus.pdf | 1 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Kharghar Bus Terminus- Dec 21.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Kharghar Bus Terminus- Mar 22.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Kharghar Bus Terminus - Jun 22.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Kharghar Bus Terminus- Sept 22.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Kharghar Bus Terminus- Dec 22.pdf | 3 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2021 Kharghar Bus Terminus_11zon.pdf | 29 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mar 2022 Kharghar Bus Terminus_11zon.pdf | 29 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Jun 2022 Kharghar Bus Terminus_11zon.pdf | 29 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2022 Kharghar Bus Terminus_11zon.pdf | 29 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Kharghar Bus Terminus FY 2020-21.pdf | 25 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kharghar Bus Terminus.pdf | 24 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec 21 - Form 2.pdf | 23 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mar 22 - Form 2.pdf | 23 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Jun 22 - Form 2.pdf | 23 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sept 22 - Form 2.pdf | 23 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus Dec 21 - UP_11zon.pdf | 25 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Kharghar Bus Terminus Mar 22_11zon.pdf | 25 Jan 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SWAPNAPOORTI HOUSING SCHEME | Plot No -2 Sector -36 Kharghar Navi Mumbai | 3,590 | Completed | May 2015 | Late, Jun 2016 |
| VALLEY SHILP HOUSING SCHEME | Plot No -3 Sector 36 Kharghar Navi Mumbai | 1,224 | Completed | May 2014 | Late, May 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 21 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 94 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Plot No. 19 Sector-14 Kharghar Bus Terminus on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kharghar5,900+ in Raigarh
Filed coordinates, straight-line distance. 64 registered projects within 2 km.
KHARGHAR HILLS
TODAY PRACHAR DEVELOPERS LLP, BHADRESH RAJ
Gami Bhagwati Orelia
GAMI VISION PRIVATE LIMITED
ANANDAM - II
TODAY GLOBAL HOMES
Godrej Varanya Phase 1
Godrej Properties Limited
Sai World Empire Phase III
paradisesuperstructures
SATYAM TRINITY TOWERS
SATYAM INFRA REALTY LLP
See every Raigarh project, with the district possession charts
Builder: CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED
CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED has 22 registrations on MahaRERA, including SECTOR 21 TALOJA and SECTOR 22, TALOJA. Its filings disclose 7 earlier MahaRERA projects: declares 0 of 7 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Plot No. 19 Sector-14 Kharghar Bus Terminus is delayed beyond 31 Jul 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Plot No. 19 Sector-14 Kharghar Bus Terminus?
The registered promoter entity is CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Plot No. 19 Sector-14 Kharghar Bus Terminus?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Plot No. 19 Sector-14 Kharghar Bus Terminus?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Plot No. 19 Sector-14 Kharghar Bus Terminus?
The professionals named in the filing: Architect: Architect Hafeez Contractor; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: N B Sayed& Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Plot No. 19 Sector-14 Kharghar Bus Terminus?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback