ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / PLATINUM HOMES

Registered No litigation declared Plotted project

PLATINUM HOMES

By ARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN

RG-MH-37819 · RERA P50500053097 · Last updated on MahaRERA portal: 9 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
25 of 81Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

PLATINUM HOMES is a Plotted project by ARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN in Nagpur, Maharashtra, registered with MahaRERA as P50500053097 on 16 Oct 2023. Possession is promised by 31 Dec 2027. 56 of the 81 units on this registration are recorded sold or booked.

At a glance

Project

  • NamePLATINUM HOMES
  • TypePlotted
  • Location
    • MIHAN ROAD
    • HINGNA
    • Wagdara (536054)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500053097
  • ReraGenie IDRG-MH-37819

Builder

  • NameARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN
  • Entity typeOthers
  • Named personsPRITI KHETAN, MANISHA DEEPAK AGRAWAL, ARETI AMIT RAJA

Key dates

this monthRegisteredOct 2023PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Oct 2023
  • Promised completion31 Dec 2027
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed110 files

Current status

69%56 of 81 units booked
26.7%Work done, per cost certificate

Figures as on 9 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area10,552 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Sep 2024

Approvals and building plan

Sanctioning authorityNagpur Metropolitan Region Development Authority

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHARDA COMPLEX NEAR TELEPHON EXCHANGE SQUARE CENTRAL AVENUE NAGPUR
Estimated costRs 1.50 cr
Cost incurredRs 40.00 lakh
Work done26.67%
BuildingWingEstimatedIncurred
NA Plot Without StructureNARs 1.50 crRs 40.00 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIL BHAVE
ArchitectTEJASHREE GADODIA
EngineerANIL BHAVE
EngineerShrawan Kumar Sharma
Chartered AccountantCA ANKIT TALREJA
Chartered AccountantDeepak Satyanarayan Agrawal & Co
Chartered AccountantKhetan Raja & Co
PartnerRole in project
ARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES JUNE 2026.pdf9 Jul 2026
Withdrawal Update Form 2File: FORM-2 (1).pdf9 Jul 2026
Withdrawal Update Form 3File: form 3 .pdf9 Jul 2026
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES JUNE 2026.pdf8 Jul 2026
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES JUNE 2026.pdf8 Jul 2026
Withdrawal Update Form 2File: FORM-2 PLATINUM HOMES JUNE 2026.pdf8 Jul 2026
Withdrawal Update Form 2File: FORM-2.pdf8 Jul 2026
Withdrawal Update Form 3File: FORM 3 PLATINUM HOMES.pdf8 Jul 2026
Withdrawal Update Form 3File: FORM 3 PLATINUM HOMES.pdf8 Jul 2026
Form 1File: FORM-1 PLATINUM HOMES DEC-2023.pdf6 Jul 2026
Form 2File: FORM-2 PLATINUM HOMES DEC-2023.pdf6 Jul 2026
Form 3File: FORM-3 PLATINUM HOMES DEC-2023.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf6 Jul 2026
Form 1File: FORM-1 PLATINUM HOMES MAR-2024.pdf6 Jul 2026
Form 2File: FORM-2 PLATINUM HOMES MAR-2024.pdf6 Jul 2026
Form 3File: FORM-3 PLATINUM HOMES MAR-2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf6 Jul 2026
Form 1File: FORM-1 PLATINUM HOMES JUN-2024.pdf6 Jul 2026
Form 2File: FORM-2 PLATINUM HOMES JUN-2024.pdf6 Jul 2026
Form 3File: FORM-3 PLATINUM HOMES JUN-2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold unsold.pdf6 Jul 2026
Form 1File: FORM-1 PLATINUM HOMES SEP-2024.pdf6 Jul 2026
Form 2File: FORM-2 PLATINUM HOMES SEP-2024.pdf6 Jul 2026
Form 3File: FORM-3 PLATINUM HOMES SEP-2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SEP-24.pdf6 Jul 2026
Form 1File: FORM-1 PLATINUM HOMES DEC-2024.pdf6 Jul 2026
Form 2File: FORM-2 PLATINUM HOMES DEC-2024.pdf6 Jul 2026
Form 3File: FORM-3 PLATINUM HOMES DEC-2024.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf6 Jul 2026
Form 1File: Form 1 - PLATINUM HOME.pdf6 Jul 2026
Form 2File: Form 2 -PLATINUM HOME.pdf6 Jul 2026
Form 3File: form 3 -PLATINUM HOME_compressed.pdf6 Jul 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf6 Jul 2026
Withdrawal Update Form 1File: Form 1 JUN-25.pdf6 Jul 2026
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES MAR-2026.pdf6 Jul 2026
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES JUNE 2026.pdf6 Jul 2026
Withdrawal Update Form 2File: Form 2 JUN-25.pdf6 Jul 2026
Withdrawal Update Form 2File: FORM-2 PLATINUM HOMES MAR-2026.pdf6 Jul 2026
Withdrawal Update Form 2File: FORM-2 PLATINUM HOMES JUNE 2026.pdf6 Jul 2026
Withdrawal Update Form 3File: Form 3 JUN-25.pdf6 Jul 2026
Withdrawal Update Form 3File: FORM-3 PLATINUM HOMES MAR-2026_compressed.pdf6 Jul 2026
Withdrawal Update Form 3File: FORM-3 PLATINUM HOMES JUNE 2026.pdf6 Jul 2026
Withdrawal Update Form 1File: Q3-2023-24 FORM 1.pdf4 Jul 2026
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES DEC-2023.pdf4 Jul 2026
Withdrawal Update Form 1File: FORM-1 PLATINUM HOMES DEC-2023.pdf4 Jul 2026
Withdrawal Update Form 2File: Q3-2023-24 FORM 2.pdf4 Jul 2026
Withdrawal Update Form 2File: FORM-2 PLATINUM HOMES DEC-2023.pdf4 Jul 2026
Withdrawal Update Form 2File: FORM-2 PLATINUM HOMES DEC-2023.pdf4 Jul 2026
Withdrawal Update Form 3File: fORM 3.pdf4 Jul 2026
Withdrawal Update Form 3File: FORM-3 PLATINUM HOMES DEC-2023.pdf4 Jul 2026
Withdrawal Update Form 3File: FORM-3 PLATINUM HOMES DEC-2023.pdf4 Jul 2026
Form 2A (FY 2025-2026)File: FORM-2 (1).pdf4 Jul 2026
Form 5 (FY 2025-2026)File: FORM-5 (1).pdf4 Jul 2026
Withdrawal Update Form 1File: Q3-2023-24 FORM 1.pdf19 Apr 2026
Withdrawal Update Form 2File: Q3-2023-24 FORM 2.pdf19 Apr 2026
Withdrawal Update Form 3File: fORM 3.pdf19 Apr 2026
Withdrawal Update Form 1File: Q3-2023-24 FORM 1.pdf20 Jan 2026
Withdrawal Update Form 1File: Q3-2023-24 FORM 1.pdf20 Jan 2026
Withdrawal Update Form 1File: Q3-2023-24 FORM 1.pdf20 Jan 2026
Withdrawal Update Form 1File: Q3-2023-24 FORM 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Q3-2023-24 FORM 2.pdf20 Jan 2026
Withdrawal Update Form 2File: Q3-2023-24 FORM 2.pdf20 Jan 2026
Withdrawal Update Form 2File: Q3-2023-24 FORM 2.pdf20 Jan 2026
Withdrawal Update Form 2File: Q3-2023-24 FORM 2.pdf20 Jan 2026
Withdrawal Update Form 3File: fORM 3.pdf20 Jan 2026
Withdrawal Update Form 3File: fORM 3.pdf20 Jan 2026
Withdrawal Update Form 3File: fORM 3.pdf20 Jan 2026
Withdrawal Update Form 3File: fORM 3.pdf20 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3-2023-24 FORM 1-ARCHITECT CERTIFICATE.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q4-2023-24-FORM1-ARCHITECT CERTIFICATE.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architecht's Certificate-Q1 24-25.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architecht's Certificate-Q2 24-25.pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architecht's Certificate- Q3 24-25.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q3-2023-24 FORM 3-CA CERTIFICATE.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q-4-2023-24 FORM 3-CA CERTIFICATE.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate Q1 24-25.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate Q2 -24-25.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate Q3 24-25.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q3-2023-24 FORM 2.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q-4-2023-24 FORM 2.pdf13 Feb 2025

How this compares with Nagpur

69%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PLATINUM HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HINGNA2,800+ in Nagpur

2 kmPLATINUM HOMESCompleted 10Lapsed / revoked 5Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: ARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN

ARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN has 1 registration on MahaRERA, including PLATINUM HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if PLATINUM HOMES is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PLATINUM HOMES?

The registered promoter entity is ARTI AMIT RAJA, MANISHA DEEPAK AGRAWAL AND PRITI KHETAN, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PLATINUM HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PLATINUM HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PLATINUM HOMES?

The professionals named in the filing: Architect: ANIL BHAVE; Architect: TEJASHREE GADODIA; Engineer: ANIL BHAVE; Engineer: Shrawan Kumar Sharma; Chartered Accountant: CA ANKIT TALREJA; Chartered Accountant: Deepak Satyanarayan Agrawal & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PLATINUM HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PLATINUM HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PLATINUM HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.