Home / Browse projects / Palghar, Maharashtra / PHILIPS VILLA

Registered No litigation declared Residential / Group Housing project

PHILIPS VILLA

By SHREE BALAJI DEVELOPERS

RG-MH-90115 · RERA P99000022803 · Last updated on MahaRERA portal: 21 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 76 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Apr 2029Possession promisedmoved 76 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 65%
22 of 31Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

PHILIPS VILLA is a Residential / Group Housing project by SHREE BALAJI DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000022803 on 30 Oct 2019. Possession is promised by 30 Apr 2029. The completion date has moved by 76 months from the original filing. 9 of the 31 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NamePHILIPS VILLA
  • TypeResidential / Group Housing
  • Location
    • RAM LAXMAN MARG
    • PANCHAL NAGAR
    • NALLASOPARA (WEST)
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • RERA no.P99000022803
  • ReraGenie IDRG-MH-90115

Builder

  • NameSHREE BALAJI DEVELOPERS
  • Entity typePartnership
  • PartnerASHWIN ARVIND PORWAL
  • Other registrations21 more →
  • Completed6 of 22
  • No longer live12 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2019First promiseDec 2022Revised toApr 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Oct 2019
  • Promised completion30 Apr 2029
  • Revised completionRevised to 30 Apr 2029 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed103 files

Current status

29%9 of 31 units booked
47.6%Work done, per cost certificate

Figures as on 21 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PHILIPS VILLANA5031031

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 65%.

PHILIPS VILLA: 48% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 21 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Open Space44

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area958 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Apr 2026

Approvals and building plan

Sanctioning authorityVasai Virar city Municipal Corporation
Permissible FSI1820.04
Proposed, not sanctioned958 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHREE APARTMENT, NALLASOPARA WEST DISTRICT THANE
Estimated costRs 4.70 cr
Cost incurredRs 2.24 cr
Work done47.65%
BuildingWingEstimatedIncurred
PHILIPS VILLANARs 3.84 crRs 2.24 cr
-NARs 86.01 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASSOCIATE PLANNERS AND APPRAISERS
EngineerMubeen Ghori
Chartered AccountantRAKESH AGARWAL
PartnerRole in project
SHREE BALAJI DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000013223Dec 2022 → Dec 2025

Reason as filed by the promoterCHANGE OF DEVELOPMENT CONTROL RULES AND REVISED STATUARY PERMISSIONS

EA16062621385Dec 2022 → Dec 2028

Reason as filed by the promoterRespected Sir/Madam, We, the promoters of the project Philips Villa (Reg. No. P99000022803), humbly submit this application seeking revocation of the “Lapsed” status and extension of registration. The project registration expired on 31/12/2025, and the portal presently reflects the status as “Lapsed.” We respectfully request the Authority to revoke the lapsed status and extend validity till 31/12/2028 to enable completion of balance work and procurement of the Occupation Certificate. Grounds for Request: The project suffered delays due to severe financial constraints and bankruptcy issues face

P99000022803/WarDec 2022 → Apr 2029

Reason as filed by the promoterNA

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000192781SHAMBHU KUMAR GOENKASHREE BALAJI DEVELOPERS29/02/2020
CC006000000171641Vinay patelABHISHEK RAMSINGH HANDA23/11/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2029

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf21 Jul 2026
Withdrawal Update Form 1File: Sept form 1.pdf14 Jul 2026
Withdrawal Update Form 2File: Sept form 2.pdf14 Jul 2026
Withdrawal Update Form 3File: Sept form 3.pdf14 Jul 2026
Withdrawal Update Form 1File: March form 1.pdf13 Jul 2026
Withdrawal Update Form 1File: June form 1.pdf13 Jul 2026
Withdrawal Update Form 1File: June form 1.pdf13 Jul 2026
Withdrawal Update Form 1File: Sept form 1.pdf13 Jul 2026
Withdrawal Update Form 2File: March form 2.pdf13 Jul 2026
Withdrawal Update Form 2File: June form 2.pdf13 Jul 2026
Withdrawal Update Form 2File: June form 2.pdf13 Jul 2026
Withdrawal Update Form 2File: Sept form 2.pdf13 Jul 2026
Withdrawal Update Form 3File: March form 3.pdf13 Jul 2026
Withdrawal Update Form 3File: June form 3.pdf13 Jul 2026
Withdrawal Update Form 3File: June form 3.pdf13 Jul 2026
Withdrawal Update Form 3File: Sept form 3.pdf13 Jul 2026
Withdrawal Update Form 1File: form 1_Philips June 2025 QPR.pdf3 Jul 2026
Withdrawal Update Form 1File: form 1_Philips September 2025 QPR.pdf3 Jul 2026
Withdrawal Update Form 1File: form 1_Philips Dec 2025 QPR.pdf3 Jul 2026
Withdrawal Update Form 2File: Form 2 Philips June 2025 QPR.pdf3 Jul 2026
Withdrawal Update Form 2File: Form 2 Philips Sept 2025 QPR.pdf3 Jul 2026
Withdrawal Update Form 2File: form 2 Philips Dec 2025 QPR.pdf3 Jul 2026
Withdrawal Update Form 3File: Form 3_Philips June 2025 QPR (1).pdf3 Jul 2026
Withdrawal Update Form 3File: Form 3_Philips Sept 2025 QPR (1).pdf3 Jul 2026
Withdrawal Update Form 3File: Form 3_Philips Dec 2025 QPR.pdf3 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A (1).pdf22 Jun 2026
Withdrawal Update Form 1File: form 1.pdf16 Jun 2026
Withdrawal Update Form 2File: form 2.pdf16 Jun 2026
Withdrawal Update Form 3File: form 3.pdf16 Jun 2026
Form 5 (FY 2024-2025)File: form 5.pdf16 Jun 2026
Withdrawal Update Form 1File: form 1.pdf14 May 2026
Withdrawal Update Form 2File: form 2.pdf14 May 2026
Withdrawal Update Form 3File: Form 3.pdf14 May 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Form 3File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Withdrawal Update Form 1File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Withdrawal Update Form 2File: Philips Villa _Nil QPR _ 2025.pdf16 Apr 2026
Withdrawal Update Form 3File: Blank Page.pdf16 Apr 2026
Form 1File: QPR LETTER_0001.pdf13 Apr 2026
Form 2File: QPR LETTER_0001.pdf13 Apr 2026
Form 3File: QPR LETTER_0001.pdf13 Apr 2026
Disclosure of Sold and Booked InventoryFile: QPR LETTER_0001.pdf13 Apr 2026
Form 1File: QPR LETTER_0001.pdf30 Mar 2026
Form 2File: QPR LETTER_0001.pdf30 Mar 2026
Form 3File: QPR LETTER_0001.pdf30 Mar 2026
Disclosure of Sold and Booked InventoryFile: QPR LETTER_0001.pdf30 Mar 2026

How this compares with Palghar

29%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 76 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PHILIPS VILLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NALLASOPARA (WEST)3,200+ in Palghar

Builder: SHREE BALAJI DEVELOPERS

SHREE BALAJI DEVELOPERS has 22 registrations on MahaRERA, including SHREE RESIDENCY and PNT SQUARE. Its filings disclose 4 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if PHILIPS VILLA is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PHILIPS VILLA?

The registered promoter entity is SHREE BALAJI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PHILIPS VILLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PHILIPS VILLA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PHILIPS VILLA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PHILIPS VILLA?

The professionals named in the filing: Architect: ASSOCIATE PLANNERS AND APPRAISERS; Engineer: Mubeen Ghori; Chartered Accountant: RAKESH AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PHILIPS VILLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PHILIPS VILLA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PHILIPS VILLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.