Home / Browse projects / Pune, Maharashtra / Phase VI - Buildings O1 and P1

Registration lapsed No litigation declared Residential / Group Housing project

Phase VI - Buildings O1 and P1

By Shree Sai Associates

RG-MH-21129 · RERA P52100012061 · Last updated on MahaRERA portal: 9 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 78 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 10%
0 of 80Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

Phase VI - Buildings O1 and P1 is a Residential / Group Housing project by Shree Sai Associates in Pune, Maharashtra, registered with MahaRERA as P52100012061 on 1 Sep 2017. Possession was promised by 29 Jun 2026 and is now 4 months past that date. The completion date has moved by 78 months from the original filing. 80 of the 80 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NamePhase VI - Buildings O1 and P1
  • TypeResidential / Group Housing
  • Location
    • Pune Nashik Highway
    • Chakan
    • Chakan (CT)
    • Khed
    • Pune
    • 410501
  • Pincode410501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100012061
  • ReraGenie IDRG-MH-21129

Builder

  • NameShree Sai Associates
  • Entity typePartnership
  • PartnersGanesh Laxman Zagade, Hrishikesh Chandrankant Zagade
  • Other registrations11 more →
  • Completed3 of 12
  • No longer live5 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

4 months past promisethis monthRegisteredSep 2017First promiseDec 2019Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion29 Jun 2026
  • Revised completionRevised to 29 Jun 2026 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed53 files

Current status

100%80 of 80 units booked
76.9%Work done, per cost certificate

Figures as on 9 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
O1NA5440040
P1NA5440040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 10%.

O128%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
P127%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed158

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots158
Closed/Covered158
BuildingClosed/CoveredTotal
O18080
P17878

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jun 2026
LandownerVillageDistrict
Ananda Bala DhadgeChakan (CT)Pune
Sushila Maruti SayakarChakan (CT)Pune

Approvals and building plan

Sanctioning authorityChakan Nagar Parishad
Permissible FSI3059.74
Proposed, not sanctioned3,060 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRenuka Icon At Shrishetra Mahalunge Ingale Chakan 410501
Estimated costRs 6.64 cr
Cost incurredRs 5.10 cr
Work done76.87%
BuildingWingEstimatedIncurred
O1NARs 3.32 crRs 2.55 cr
P1NARs 3.32 crRs 2.55 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDeepak Honkan
EngineerShirke Consulting Engineers
Chartered AccountantPravin Pise and Associates
PartnerRole in project
Shree Sai Associates-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018075Dec 2019 → Jun 2026

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project.

EXT52100010539Dec 2019 → Dec 2022

Reason as filed by the promoterThe project is almost 90% complete, as indicated in the architect's certificate. However, the promoter requests for additional time to complete the balance 10% work, due to the following reasons: 1) Cash flows stopped during covid. Contractor payments was delayed, 2) Banks not giving any grace period, and all collections were given to Banks for repayment of loans , 3) Due to GST tax rate changes, customers not paying GST at higher rates. 4) Project Extention required up to 31 December 2022.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 31-12-2025 From 1 phase vi.pdf9 Jun 2026
Withdrawal Update Form 1File: 31-3-2026 From 1 Phase vi.pdf9 Jun 2026
Withdrawal Update Form 2File: F2 - Engineer Certificate Dec 25.pdf9 Jun 2026
Withdrawal Update Form 2File: F2 - Engineer Certificate Dec 25.pdf9 Jun 2026
Withdrawal Update Form 3File: 31-12-2025 form 3 phase VI.pdf9 Jun 2026
Withdrawal Update Form 3File: 31-03-2026 form 3 phase VI.pdf9 Jun 2026
Withdrawal Update Form 1File: 30-6-2025 From 1 Phase Vi.pdf8 Jun 2026
Withdrawal Update Form 1File: 30-9-2025 From1 phase vi.pdf8 Jun 2026
Withdrawal Update Form 1File: 30-9-2025 From1 phase vi.pdf8 Jun 2026
Withdrawal Update Form 2File: F2 - Engineer Certificate Jun 25.pdf8 Jun 2026
Withdrawal Update Form 2File: F2 - Engineer Certificate Sept 25.pdf8 Jun 2026
Withdrawal Update Form 2File: F2 - Engineer Certificate Sept 25.pdf8 Jun 2026
Withdrawal Update Form 3File: 30-06-2025 form 3 phase VI.pdf8 Jun 2026
Withdrawal Update Form 3File: 30-09-2025 form 3 phase VI.pdf8 Jun 2026
Withdrawal Update Form 3File: 30-09-2025 form 3 phase VI.pdf8 Jun 2026
Disclosure of sold/ booked inventoryFile: Sold Unsold inventory.pdf23 Jan 2024
CERSAI detailsFile: SOLD UNSOLD INVENTORY O1 AND P1.pdf20 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 O1 ANDP1.pdf17 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 -O1-P1 22-23.pdf17 Jan 2024
Certificates of CA (Form 3)File: FORM -3 O1-P1 SEPT 2023.pdf11 Jan 2024
Declaration in FORM BFile: Affidavit Cum Declaration.pdf25 Dec 2023
Certificates of CA (Form 3)File: FORM -3 O1-P1 2020 -2021.pdf6 Dec 2023
Certificates of CA (Form 3)File: FORM -3 O1-P1 2021-2022.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM - 5 O1-P1 2020-2021.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM - 5 O1-P1 2021-2022.pdf6 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: o1 and p1 20-21.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: o1 and p1 21-22.pdf26 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: o1 and p1 22-23.pdf26 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Annual Audit Report of Statutory CA (Form 5) (FY 2017-18).pdf27 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Audit Report of Statutory CA (Form 5) (FY 2018-19.pdf27 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Audit Report of Statutory CA (Form 5) (FY 2019-20.pdf27 Sep 2021
Declaration about Commencement CertificateFile: declaration about commencement.pdf14 Sep 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold inventory.pdf14 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: PhaseVI_Form 5 FY2017-18.pdf14 Sep 2021
Declaration about Commencement CertificateFile: declaration about commencement.pdf13 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 Till FY2018-19.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY2019-20.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY2019-20.pdf13 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Phase VI_ Commencement certificate.pdf30 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: Phase VI _ NOC .pdf30 Apr 2018
Building plan approvalFile: O1 and P1 HPSCANNER0129 (1).pdf3 Aug 2017
Layout approvalFile: Layout HPSCANNER0130 (1).pdf3 Aug 2017
Copy of the legal title reportFile: Phase VI.pdf3 Aug 2017
Details of encumbrancesFile: Phase 6.pdf3 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout HPSCANNER0130 (1).pdf3 Aug 2017
Building Plan Approval (IOD)File: O1 and P1 HPSCANNER0129 (1).pdf3 Aug 2017
Declaration in FORM BFile: Promoters.pdf3 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect _Certificate_Phase VI.pdf3 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase VI.pdf3 Aug 2017
Certificates of CA (Form 3)File: Phase VI.pdf3 Aug 2017
Proforma of Allotment letterFile: PHASE VI RERA Draft 4000SqMtr.pdf3 Aug 2017

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 78 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Phase VI - Buildings O1 and P1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chakan13,700+ in Pune

2 kmPhase VI - Buildings O1 Completed 11Lapsed / revoked 9Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: Shree Sai Associates

SHREE SAI ASSOCIATES has 12 registrations on MahaRERA, including SHREE SAI ENCLAVE and SHREE SAI PARK. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Phase VI - Buildings O1 and P1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Phase VI - Buildings O1 and P1 is delayed beyond 29 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Phase VI - Buildings O1 and P1?

The registered promoter entity is Shree Sai Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Phase VI - Buildings O1 and P1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Phase VI - Buildings O1 and P1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Phase VI - Buildings O1 and P1?

The professionals named in the filing: Architect: Deepak Honkan; Engineer: Shirke Consulting Engineers; Chartered Accountant: Pravin Pise and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Phase VI - Buildings O1 and P1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Phase VI - Buildings O1 and P1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Phase VI - Buildings O1 and P1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.