Home / Browse projects / Thane, Maharashtra / PENTAGON ENCLAVE

Registration lapsed No litigation declared Residential / Group Housing project

PENTAGON ENCLAVE

By DAMJI HARI INFRASTRUCTURE PVT LTD

RG-MH-09044 · RERA P51700010181 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 10 complaints at MahaRERA
  • Completion date moved by 72 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
16 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 91%
56 of 246Units unsoldnot recorded sold or booked
10Complaints at MahaRERAon this registration
Jump to the 196 documents Report an error

PENTAGON ENCLAVE is a Residential / Group Housing project by DAMJI HARI INFRASTRUCTURE PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700010181 on 24 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 190 of the 246 units on this registration are recorded sold or booked, and 16 of 33 construction stages are filed complete. 10 complaints are on record with the regulator.

At a glance

Project

  • NamePENTAGON ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • ASANGAON
    • SHAHAPUR
    • Asangaon (CT)
    • Thane
    • 421601
  • Pincode421601
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700010181
  • ReraGenie IDRG-MH-09044

Builder

  • NameDAMJI HARI INFRASTRUCTURE PVT LTD
  • Entity typeCompany
  • GSTIN27AAFCD4481J1ZE
  • Managing DirectorsPARESH DHANJI BHANUSHALI, MAHADEV DAMJI PATEL

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
  • Buildings3 building records
  • Documents filed196 files

Current status

77%190 of 246 units booked

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PENTA 1 - TYPE 2NA971190119
PENTA 2 - TYPE 3NA971190119
COMMERCIAL COMPLEX - TYPE 1NA32088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 91%.

PENTA 1 - TYPE 281%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.91%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
PENTA 2 - TYPE 367%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
COMMERCIAL COMPLEX - TYPE 135%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,816 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
HARESH RAMCHAND SOBHANIAsangaon (CT)Thane

Approvals and building plan

Sanctioning authorityMAHADEV DAMJI PATEL
Permissible FSI8268.4
Proposed, not sanctioned8,268 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJ B NAGAR ANDHERI EAST

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR. ALIM A.K. FOUZI
EngineerMR. MAJID DHOKLE
Chartered AccountantM O NEHTA & ASSOCIATES
Chartered AccountantVIVEK KHANDOR
Chartered AccountantBhavik deepakbhai shah
PartnerRole in project
DAMJI HARI INFRASTRUCTURE PVT LTD-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018081Dec 2019 → Dec 2024

Reason as filed by the promoterProject completion delayed due to certain mitigating circumstances beyond the control of the promoter

EXT51700005382Dec 2019 → Dec 2020

Reason as filed by the promoter1) There was a delay in supply of river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2) The unexpected rains and prolonged monsoons further has caused a further delay. 3) Due to bankruptcy proceedings against non- banking finance companies like DHFL and Indiabulls,amounts have not been disbursed since the past year. Almost 50% of allotted flats are mortgagedwith these banksfor a home loan.

EXT51700010735Dec 2019 → Dec 2022

Reason as filed by the promoter1. Unavailability of raw materials due to covid 19 pandemic lockdown: Despite placing purchase orders for the raw materials on time, the same have not been supplied on time by the suppliers due to covid 19 pandemic lockdown. There was a delay in supply of cement,flooring tiles,electrical and plumbing materials,river sand, metal no.2, crush sand and wash sand by the suppliers though the order for the same had been placed in a timely manner by the promoter. 2. Labour/Manpower issue due to covid 19 pandemic lockdown : Due to Covid 19 Pandemic, nationwide complete lockdown was declared which has s

EXT51700013203Dec 2019 → Nov 2023

Reason as filed by the promoterDue to certain mitigating circumstances the project is still incomplete

EXT51700027987Dec 2019 → Dec 2025

Reason as filed by the promoterWe just want to inform you that we have obtained part OC for our project but still we want extension for second building and our commercial sector , the reason behind the extension is There are financial difficulties that make it hard for developers to continue construction. Issues like non-payment by buyers, difficulty in securing funding, or lack of working capital which affects delay in construction. The cost of construction materials can fluctuate significantly, which may lead to budget overruns. That’s also delay the project timelines. Sometimes, delays in specific work packages, caused b

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000023922DAMJI HARI INFRASTRUCTURE PVT LTDANIL LAKHANI27/03/2018
CC006000000044278DAMJI HARI INFRASTRUCTURE PVT LTDCoatwala Maimoona Yakub/ Coatwala Iqubal Yakub25/04/2018
CC006000000078378DAMJI HARI INFRASTRUCTURE PVT LTDAslam Shaikh07/03/2019
CC006000000078416DAMJI HARI INFRASTRUCTURE PVT LTDRAJENDRA GAIKWAD09/03/2019
CC006000000196689MAIMOONA YAKUB COATWALAM/S DAMJI HARI INFRASTRUCTURE PRIVATE LIMITED31/05/2021
CC006000000251738Taher Saifuddin SehorewalaDamji Hari Infrastructure Pvt Ltd07/07/2022
CC006000000303010ALKA RAJENDRA GAIKWADM/s Damji Hari Infrastructure Private Limited18/10/2022
CC006000000303011VISHNU PRABHU HANDEM/s Damji Hari Infrastructure Private Limited18/10/2022
CC006000000303014SHRIKANT SHIVAJI BAGADM/s Damji Hari Infrastructure Private Limited19/10/2022
CC006000000303015RAM LAXMINARAYAN BHATM/s Damji Hari Infrastructure Private Limited19/10/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Feb 2025

Documents filed196

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 196 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 3File: Form 3 Revised Jun-25.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: disclosure FY 25-26.pdf24 Apr 2026
Form 2File: form 2 june 2025.pdf24 Apr 2026
Form 1File: form 1 june 2025.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: disclosure FY 25-26.pdf24 Apr 2026
Form 1File: form 1 sep 2025.pdf24 Apr 2026
Form 2File: form 2 sept 2025.pdf24 Apr 2026
Form 3File: Form 3 Revised Sep-25.pdf24 Apr 2026
Form 1File: form 1 dec 2025.pdf24 Apr 2026
Disclosure of Sold and Booked InventoryFile: disclosure FY 25-26.pdf24 Apr 2026
Form 3File: Form 3 Dec-25.pdf24 Apr 2026
Form 2File: form 2 dec 2025.pdf24 Apr 2026
Form 5 (FY 2025-2026)File: Form 5 -24-25.pdf17 Apr 2026
Form 5 (FY 2023-2024)File: 60 - DHI - Form 5 march 24.pdf17 Apr 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Penta 2 Architect certificate.pdf1 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate commerical_.pdf1 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Penta 1 Architect certificate.pdf1 Jul 2025
Certificates of CA (Form 3)File: DHI - Form 3 - March 2025 with annexures.pdf1 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- P2_.pdf1 Jul 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- P1_.pdf1 Jul 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf7 Jun 2025
Declaration in FORM BFile: Form B.pdf16 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- Penta 2 Final.pdf15 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- Penta 1 Final.pdf15 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- COMMERCIAL Final_.pdf15 Apr 2025
Certificates of CA (Form 3)File: DHI - Form 3 with Ann - December 2024.pdf4 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PE_PART OC_CERTIFICATE_SIGNED.pdf20 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PE_AS BUILT PLAN_PART OC_SIGNED_compressed.pdf20 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC.pdf14 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enggi Certificate Penta- 1 March 2024.pdf31 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- Penta 2 March 2024.pdf31 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate- COMMERCIAL March 2024.pdf31 Dec 2024
Certificates of CA (Form 3)File: 55 - DHI - Form 3 with Annexure - March 2024.pdf19 Dec 2024
Certificates of CA (Form 3)File: 56 - DHI - Form 3 with ann A - Sept 2024_.pdf19 Dec 2024
Details of encumbrances concerned to FinanceFile: SOLD UNSOLD INVENTORY_.pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate - TYPE-1 - (MARCH - 2024).pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate - TYPE-2 - (MARCH - 2024).pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate - TYPE-3 - (MARCH - 2024).pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate - TYPE-1 - (JUNE - 2024).pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate - TYPE-2 - (JUNE - 2024).pdf3 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate - TYPE-3 - (JUNE - 2024).pdf3 Dec 2024
Details of encumbrances concerned to LegalFile: SOLD UNSOLD INVENTORY_.pdf3 Dec 2024
Declaration in FORM BFile: DH FORMB.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 (1) (1)_compressed.pdf12 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASSURANCE-2020-2021 new (1).pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QUALITY ASSURANCE-2021-2022 new.pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE-2022-2023 new1 (2).pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 1.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 2.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 3.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 3.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 4.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 5.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 6.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 7.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 8.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: 9.pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QA 1.pdf28 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QA 2.pdf28 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QA 3.pdf28 Dec 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD -final.pdf15 Dec 2023
Certificates of CA (Form 3)File: FORM 3 DEC.pdf28 Nov 2023
Certificates of CA (Form 3)File: FORM 3 SEPT.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: COMMERCIAL.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Penta 1.pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Penta 2.pdf24 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022 23.pdf22 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 - Engineer's certificate- COMMERCIAL - (31-03-2023).pdf17 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 - Engineer's certificate- Penta 1 - (31-03-2023).pdf17 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 - Engineer's certificate- Penta 2 - (31-03-2023).pdf17 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate TYPE-1 31-03-2023.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate TYPE-2 31-03-2023.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate TYPE-3 31-03-2023.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE TYPE 3.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE TYPE 1.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE TYPE 2.pdf2 Nov 2023
Certificates of CA (Form 3)File: from 3_.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate --TYPE-1 - (31-12-2022).pdf14 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate --TYPE-2 - (31-12-2022)-signed.pdf14 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 - Architect certificate --TYPE-3 - (31-12-2022)-signed.pdf14 Sep 2023

How this compares with Thane

77%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 72 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PENTAGON ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHAHAPUR7,600+ in Thane

2 kmPENTAGON ENCLAVECompleted 9Lapsed / revoked 7Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: DAMJI HARI INFRASTRUCTURE PVT LTD

DAMJI HARI INFRASTRUCTURE PVT LTD has 1 registration on MahaRERA, including PENTAGON ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that PENTAGON ENCLAVE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PENTAGON ENCLAVE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PENTAGON ENCLAVE?

The registered promoter entity is DAMJI HARI INFRASTRUCTURE PVT LTD, a company as per the filing. Its GSTIN 27AAFCD4481J1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PENTAGON ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PENTAGON ENCLAVE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PENTAGON ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PENTAGON ENCLAVE?

The professionals named in the filing: Architect: MR. ALIM A.K. FOUZI; Engineer: MR. MAJID DHOKLE; Chartered Accountant: M O NEHTA & ASSOCIATES; Chartered Accountant: VIVEK KHANDOR; Chartered Accountant: Bhavik deepakbhai shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PENTAGON ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PENTAGON ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PENTAGON ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.