Home / Browse projects / Raigarh, Maharashtra / PD ONE

Completed No litigation declared Others project

PD ONE

By PRAGATI DEVELOPERS

RG-MH-07140 · RERA P52000055286 · Last updated on MahaRERA portal: 17 Nov 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
9 of 39Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

PD ONE is a Others project by PRAGATI DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000055286 on 14 Mar 2024. The registration is recorded completed; possession was promised by 31 Dec 2026. 30 of the 39 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete.

At a glance

Project

  • NamePD ONE
  • TypeOthers
  • Location
    • SECTOR 15C
    • ULWE
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000055286
  • ReraGenie IDRG-MH-07140

Builder

  • NamePRAGATI DEVELOPERS
  • Entity typeOthers
  • Named personPARESH SHANTILAL SATRA
  • Other registrations8 more →
  • Completed6 of 9
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredMar 2024PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Mar 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed53 files

Current status

77%30 of 39 units booked
99.7%Work done, per cost certificate

Figures as on 17 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PD ONENA8834539

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

PD ONE: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered9

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area499 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI1686.1
Proposed, not sanctioned1,686 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPERSEPOLIS PREMISES COHS PLOT NO 74 SECTOR 17 VASHI NAVI MUMBAI PIN 400705
Estimated costRs 8.50 cr
Cost incurredRs 8.48 cr
Work done99.71%
BuildingWingEstimatedIncurred
PD ONENARs 7.82 crRs 7.82 cr
-NARs 68.00 lakhRs 65.55 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDISHA ARCHITECTS
EngineerS R CONSULTANT
Chartered AccountantR B SINGH AND ASSOCIATES
PartnerRole in project
PRAGATI DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Prgati Dev OC.pdf17 Nov 2025
Withdrawal Update Form 1File: Pragati developer Form 1 - converted.pdf23 Oct 2025
Withdrawal Update Form 2File: Pragati developer Form 2 - converted.pdf23 Oct 2025
Withdrawal Update Form 3File: Pragati developers Form 3 - converted.pdf23 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf30 Sep 2025
Withdrawal Update Form 2File: Form 2 Signed.pdf30 Sep 2025
Withdrawal Update Form 3File: Form 3.pdf30 Sep 2025
Form 1File: Form 1.pdf17 Jul 2025
Form 2File: Form 2.pdf17 Jul 2025
Form 3File: Form 3.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf17 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 signing - converted.pdf19 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Signed.pdf18 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Signed.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed.pdf18 Jul 2024
Layout approvalFile: Scan-0156.pdf7 Mar 2024
Building plan approvalFile: Scan-0156.pdf7 Mar 2024
Copy of Layout Approval (in case of layout)File: Scan-0156.pdf7 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Scan-0156.pdf7 Mar 2024
Proforma of Agreement for saleFile: AFS PARESH.pdf7 Mar 2024
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale3.pdf7 Mar 2024
Other - TechnicalFile: Annexure A.pdf4 Feb 2024
Other - TechnicalFile: cc mail.pdf4 Feb 2024
Layout approvalFile: Plan 1.pdf1 Feb 2024
Building plan approvalFile: Plan 1.pdf1 Feb 2024
Copy of the legal title reportFile: Title Report New (2).pdf1 Feb 2024
Details of encumbrances concerned to FinanceFile: No encumbrances Certificate FINANCE and LEGAL.pdf1 Feb 2024
Details of encumbrances concerned to LegalFile: No encumbrances Certificate FINANCE and LEGAL.pdf1 Feb 2024
Copy of Layout Approval (in case of layout)File: Plan 1.pdf1 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Plan 1.pdf1 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CORRIGENDUM and CC.pdf1 Feb 2024
Declaration about Commencement CertificateFile: declaration about comm cert.pdf1 Feb 2024
Proforma of Allotment letterFile: ALLOTMENT DRAFT NEW_1 (6 files merged).pdf1 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A bank account decla (14).pdf1 Feb 2024
Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf1 Feb 2024
Other - LegalFile: Lease Agg - converted.pdf1 Feb 2024
Other - LegalFile: Triparty - converted.pdf1 Feb 2024
Other - LegalFile: Supplementary Deed - converted.pdf1 Feb 2024
PAN CardFile: pan card.pdf20 Dec 2023
Declaration in FORM BFile: form b.pdf20 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed.pdf20 Dec 2023
CERSAI detailsFile: CERSAI_Search_Report_200287401155_For_Asset_Based_Search_20_11_2023_18_53_05_074.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf20 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other organisations.pdf20 Dec 2023

How this compares with Raigarh

77%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PD ONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ULWE5,900+ in Raigarh

2 kmPD ONECompleted 109Lapsed / revoked 34Other 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 249 registered projects within 2 km.

Builder: PRAGATI DEVELOPERS

PRAGATI DEVELOPERS has 9 registrations on MahaRERA, including PRAGATI NIVAS and Aishwarya Residency. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if PD ONE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PD ONE?

The registered promoter entity is PRAGATI DEVELOPERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PD ONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PD ONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PD ONE?

The professionals named in the filing: Architect: DISHA ARCHITECTS; Engineer: S R CONSULTANT; Chartered Accountant: R B SINGH AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PD ONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PD ONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PD ONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.