ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / PARK VIEW CO OP HOUSING SOCIETY LIMITED

Registered No litigation declared Others project

PARK VIEW CO OP HOUSING SOCIETY LIMITED

By PARKVIEW CO OP HOUSING SOCIETY LIMITED

RG-MH-31292 · RERA P99000079626 · Last updated on MahaRERA portal: 1 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 75%
68 of 68Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

PARK VIEW CO OP HOUSING SOCIETY LIMITED is a Others project by PARKVIEW CO OP HOUSING SOCIETY LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000079626 on 17 Mar 2025. Possession is promised by 31 Dec 2027. 0 of the 68 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NamePARK VIEW CO OP HOUSING SOCIETY LIMITED
  • TypeOthers
  • Location
    • S T DEPOT ROAD
    • NALLASOPARA WEST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • RERA no.P99000079626
  • ReraGenie IDRG-MH-31292

Builder

  • NamePARKVIEW CO OP HOUSING SOCIETY LIMITED
  • Entity typeSociety

Key dates

this monthRegisteredMar 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Mar 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed90 files

Current status

0%0 of 68 units booked
16.0%Work done, per cost certificate

Figures as on 1 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARK VIEW CO OP HOUSING SOCIETY LIMITEDNA108402868

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 75%.

PARK VIEW CO OP HOUSING SOCIETY LIMITED: 20% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered1
Open Space2

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,011 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jul 2025

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNICIPAL CORPORATION
Permissible FSI7651.7
Proposed, not sanctioned3,826 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGALA NO. 1, GROUND FLOOR, LOTUS APARTMENT, SRI PRASTHA COMPLEX, NALLASOPARA WEST, TAL. VASAI, DIST. PALGHAR 401 203
Estimated costRs 13.00 cr
Cost incurredRs 2.08 cr
Work done16.0%
BuildingWingEstimatedIncurred
PARK VIEW CO OP HOUSING SOCIETY LIMITEDNARs 10.00 crRs 2.08 cr
-NARs 3.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYASH RAJEN DOSHI
ArchitectSANAT MEHTA AND ASSOCIATES
EngineerBhavin C Shah
Chartered AccountantSTR & ASSOCIATES
PartnerRole in project
PARKVIEW CO OP HOUSING SOCIETY LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1-Oct-Dec-2025.pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-Jan-March 2026.pdf1 Jun 2026
Withdrawal Update Form 1File: FORM-1 Park View Co.op.Hsg.Soc.Ltd (April-June 2025)_...pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-July-September-Park view.pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-Oct-Dec-2025.pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-Jan-March 2026.pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-Oct-Dec-2025.pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-Jan-March 2026.pdf1 Jun 2026
Withdrawal Update Form 2File: FORM-2 Park View Co.op.Hsg.Soc.Ltd (April-June 2025)-3...pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-July-September -Park view.pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-Oct-Dec-2025.pdf1 Jun 2026
Withdrawal Update Form 2File: Form-2-Jan-March 2026.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3-Oct-Dec-2025 compressed.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3-Jan-March 2026-compressed.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3-Park view_compressed.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3-Oct-Dec-2025 compressed.pdf1 Jun 2026
Withdrawal Update Form 3File: Form-3-Jan-March 2026-compressed.pdf1 Jun 2026
Withdrawal Update Form 1File: Form-1-July-September-Park view.pdf6 Nov 2025
Withdrawal Update Form 1File: Form-1-July-September-Park view.pdf6 Nov 2025
Withdrawal Update Form 2File: Form-2-July-September -Park view.pdf6 Nov 2025
Withdrawal Update Form 2File: Form-2-July-September -Park view.pdf6 Nov 2025
Withdrawal Update Form 3File: Form-3-Park view_compressed.pdf6 Nov 2025
Withdrawal Update Form 3File: Form-3-Park view_compressed.pdf6 Nov 2025
Withdrawal Update Form 1File: FORM-1 Park View Co.op.Hsg.Soc.Ltd (April-June 2025)_...pdf29 Jul 2025
Withdrawal Update Form 2File: FORM-2 Park View Co.op.Hsg.Soc.Ltd (April-June 2025)-3...pdf29 Jul 2025
Withdrawal Update Form 3File: Compressed Form 3_Q1(April-June 25)-Park View CHSL_compressed (1).pdf29 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cft form 1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA cft form 3.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RCC FORM 2.pdf19 Apr 2025
Copy of the legal title reportFile: 03-03-2025Legal title report.pdf8 Mar 2025
CERSAI detailsFile: 06-03-2025 Cersai letter.pdf8 Mar 2025
Copy of the legal title reportFile: Park View Title search Report Adv Tiwari compressed.pdf26 Feb 2025
Other - LegalFile: Revalidation Cert_RP_465333_PARKVIEW.pdf26 Feb 2025
CERSAI detailsFile: Cersai Undertaking.pdf26 Feb 2025
Copy of the legal title reportFile: Park View Title search Report Adv Tiwari compressed.pdf7 Feb 2025
CERSAI detailsFile: Undertaking Cersai report_compressed.pdf7 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf7 Feb 2025
Other - TechnicalFile: Annexure A-Declaration cum undertaking_compressed.pdf7 Feb 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf7 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured unsecured finance.pdf7 Feb 2025
Copy of the legal title reportFile: 7-12 extract.pdf17 Dec 2024
Copy of the legal title reportFile: Conveyance Deed.pdf17 Dec 2024
Details of encumbrances concerned to FinanceFile: Finance encumbrance.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Revised Form-3-CA.pdf17 Dec 2024
Other - LegalFile: 7-12 extract.pdf17 Dec 2024
Other - LegalFile: Conveyance Deed.pdf17 Dec 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION.pdf17 Dec 2024
Status of ConveyanceFile: Conveyance Deed.pdf17 Dec 2024
Status of ConveyanceFile: 7-12 extract.pdf17 Dec 2024
CERSAI detailsFile: CERSAI_Search_Report_200331743116_For_Asset_Based_Search_17_12_2024_12_07_47_222.pdf17 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf17 Dec 2024
Details of encumbrances concerned to LegalFile: Finance encumbrance.pdf17 Dec 2024
Other - FinanceFile: Finance encumbrance.pdf17 Dec 2024
Other - TechnicalFile: Flat details rev.pdf17 Dec 2024
Proforma of Agreement for saleFile: Agreement for sale.pdf17 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of interest in other real estate.pdf17 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf17 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: No Unsecured loans.pdf17 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Finance encumbrance.pdf17 Dec 2024
Declaration in FORM BFile: Form B -15-11-2024.pdf15 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 -15-11-2024.pdf15 Nov 2024
Other - LegalFile: Declaration cum undertaking - 15-11-2024.pdf15 Nov 2024
CERSAI detailsFile: CERSAI_Search_Report_200327693684_For_Asset_Based_Search_15_11_2024_16_58_24_765.pdf15 Nov 2024
Layout approvalFile: 01 Layout approval.pdf9 Oct 2024
Building plan approvalFile: 02 BUILDING APPROVAL.pdf9 Oct 2024
PAN CardFile: pan card.pdf9 Oct 2024
Copy of the legal title reportFile: Title search report.pdf9 Oct 2024
Details of encumbrances concerned to FinanceFile: for legal encumbrances.pdf9 Oct 2024
Details of encumbrances concerned to FinanceFile: FINANCIAL ENCUMBERANCES.pdf9 Oct 2024
Copy of Layout Approval (in case of layout)File: 01 Layout approval.pdf9 Oct 2024
Proforma of Allotment letterFile: Allotment letter.pdf9 Oct 2024
Declaration in FORM BFile: Form B.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM 1 09-10-24.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 09-10-2024.pdf9 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC LOW SIZE.pdf9 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 02 BUILDING APPROVAL.pdf9 Oct 2024
Disclosure of sold/ booked inventoryFile: NO INVENTORY.pdf9 Oct 2024
Declaration about Commencement CertificateFile: FORMAT D DECLARATION OF CC.pdf9 Oct 2024
CERSAI detailsFile: CERSAI_Search_Report_200316152170_For_Asset_Based_Search_06_08_2024_13_30_40_524.pdf9 Oct 2024

How this compares with Palghar

0%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARK VIEW CO OP HOUSING SOCIETY LIMITED on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NALLASOPARA WEST3,200+ in Palghar

Builder: PARKVIEW CO OP HOUSING SOCIETY LIMITED

PARKVIEW CO OP HOUSING SOCIETY LIMITED has 1 registration on MahaRERA, including PARK VIEW CO OP HOUSING SOCIETY LIMITED. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if PARK VIEW CO OP HOUSING SOCIETY LIMITED is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARK VIEW CO OP HOUSING SOCIETY LIMITED?

The registered promoter entity is PARKVIEW CO OP HOUSING SOCIETY LIMITED, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARK VIEW CO OP HOUSING SOCIETY LIMITED?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARK VIEW CO OP HOUSING SOCIETY LIMITED?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARK VIEW CO OP HOUSING SOCIETY LIMITED?

The professionals named in the filing: Architect: YASH RAJEN DOSHI; Architect: SANAT MEHTA AND ASSOCIATES; Engineer: Bhavin C Shah; Chartered Accountant: STR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARK VIEW CO OP HOUSING SOCIETY LIMITED?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARK VIEW CO OP HOUSING SOCIETY LIMITED. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARK VIEW CO OP HOUSING SOCIETY LIMITED to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.