ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / PARIVAR CO-OP HOUSING SOCIETY

Registration lapsed No litigation declared Residential / Group Housing project

PARIVAR CO-OP HOUSING SOCIETY

By VIJAY MALLYA

RG-MH-25020 · RERA P51800009500 · Last updated on MahaRERA portal: 27 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 87 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
9 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 95%
21 of 36Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 24 documents Report an error

PARIVAR CO-OP HOUSING SOCIETY is a Residential / Group Housing project by VIJAY MALLYA in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009500 on 22 Aug 2017. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 87 months from the original filing. 15 of the 36 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePARIVAR CO-OP HOUSING SOCIETY
  • TypeResidential / Group Housing
  • Location
    • JP ROAD
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009500
  • ReraGenie IDRG-MH-25020

Builder

  • NameVIJAY MALLYA
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed24 files

Current status

42%15 of 36 units booked

Figures as on 27 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARIVAR WING ANA111018018
PARIVAR WING BNA111018018

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 95%.

PARIVAR WING A81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
PARIVAR WING B63%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises69%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%

Progress on shared amenities15

As on 27 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes5%
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered34
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
PARIVAR WING A16521
PARIVAR WING B18523

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,790 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Jul 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3528.68
Proposed, not sanctioned3,251 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLA SERENA JP ROAD ANDHERI WEST MUMBAI-400058

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA R MEHTA & ASSOCIATES
EngineerCONSULTING CIVIL AND STRUCTURAL ENGINEER
Chartered Accountantvishal shah
Chartered AccountantRP MEHTA AND ASSOCIATES
PartnerRole in project
VIJAY MALLYA-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008923Dec 2018 → Oct 2021

Reason as filed by the promoterBy our application dated 17-03-2020, we had sought to extend the project completion date to 31st December 2020 under Rule 7(3) of The Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of Real Estate Agents, Rates of Interest and Disclosures on Website) Rules 2017. But due to the lockdown and subsequent slowdown in construction activities, we have been able to restart activity only in the month of Nov-Dec. Hence, we request an extension for the lost 10 months and allow us to adhere to the law.

EXT51800006232Dec 2018 → Dec 2020

Reason as filed by the promoterA.Continuous litigation with members of the Society which led to the expiry of the original Development Agreement and then again the Supplemental Development Agreement. As a result of which, the project’s ability to raise funds from even existing buyers was impaired and the introduction of funds into the Project was slowed to a crawl. Further, on account of the delay, the investors in the said Project decided to withdraw from the Project and led to further litigations on the financial front which were finally resolved in January 2020; B.Hospitalisation of the Proprietor of the Promoter, Mr. Vi

EA22072502123Dec 2018 → Mar 2026

Reason as filed by the promoterWe refer to the subject matter and hereunder submit our application for seeking extension of time for completion of the Project as required under Section 6 of The Real Estate (Regulation and Development) Act, 2016, read with Rule 7(3) of The Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of Real Estate Agents, Rates of Interest and Disclosures on Website) Rules 2017. Bawdhan Khurd, Tal. Mulshi, Dist. Pune 41 1 021 Tel: (020) 2295 3548 2295 3549 We place on record for your attention, the main reasons for which extension of Registration i

Litigation declared3

CaseCourtStatus
RAE SUIT NO 60/145 OF 2008/2008SMALL CAUSES COURTPENDING FOR WITHDRAWAL
RAE AND R SUIT NO 231/421 OF 2012/2012SMALL CAUSES COURTPENDING
474 OF 2007/2007CITY CIVIL COURTPENDING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000057318Sudhir Kumar Sharma & Karuna SharmaAmeya Developers through Mr. Vijay Mallya14/12/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed24

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: FOROM 5 PARIVAAR 25.pdf27 Sep 2025
Details of Restarting of Construction work post lockdownFile: PROJECT PARIVAR - Covid.pdf16 Jun 2020
Certificates of CA (Form 5)File: FORM_ 5-31032018 (AD-P).pdf2 Jan 2019
Proforma of Allotment letterFile: Proforma of Alotment Letter and Agreement for Sale.pdf28 Jul 2017
Building plan approvalFile: IOD(1)(1)(1).pdf27 Jul 2017
Layout approvalFile: 1.pdf27 Jul 2017
Layout approvalFile: 2.pdf27 Jul 2017
Layout approvalFile: 3.pdf27 Jul 2017
Layout approvalFile: 4.pdf27 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE (2).pdf27 Jul 2017
Details of encumbrancesFile: INDEX II - for SMDPL AND AD.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: 1.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: 2.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: 3.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: 4.pdf27 Jul 2017
Building Plan Approval (IOD)File: IOD(1)(1)(1).pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC_1.pdf27 Jul 2017
Declaration in FORM BFile: Affidavit-Parivar.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Mehta 1.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Mehta 2.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Mehta 3.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR Mehta 4.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Arif Bhakri Engineer Cert 2.pdf27 Jul 2017
Certificates of CA (Form 3)File: Vishal CA Cert.pdf27 Jul 2017

How this compares with Mumbai Suburban

42%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 87 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARIVAR CO-OP HOUSING SOCIETY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmPARIVAR CO-OP HOUSING SOCompleted 93Lapsed / revoked 58Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 271 registered projects within 2 km.

Builder: VIJAY MALLYA

VIJAY MALLYA has 2 registrations on MahaRERA, including SAFALYA and PARIVAR CO-OP HOUSING SOCIETY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that PARIVAR CO-OP HOUSING SOCIETY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARIVAR CO-OP HOUSING SOCIETY is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARIVAR CO-OP HOUSING SOCIETY?

The registered promoter entity is VIJAY MALLYA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARIVAR CO-OP HOUSING SOCIETY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARIVAR CO-OP HOUSING SOCIETY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARIVAR CO-OP HOUSING SOCIETY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARIVAR CO-OP HOUSING SOCIETY?

The professionals named in the filing: Architect: A R MEHTA & ASSOCIATES; Engineer: CONSULTING CIVIL AND STRUCTURAL ENGINEER; Chartered Accountant: vishal shah; Chartered Accountant: RP MEHTA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARIVAR CO-OP HOUSING SOCIETY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARIVAR CO-OP HOUSING SOCIETY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARIVAR CO-OP HOUSING SOCIETY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.