Home / Browse projects / Mumbai Suburban, Maharashtra / Parinee Essence

Registration lapsed No litigation declared Residential / Group Housing project

Parinee Essence

By Parinee Contour Construction Private Limited

RG-MH-19897 · RERA P51800001334 · Last updated on MahaRERA portal: 26 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
11 of 11Construction stages doneevery applicable stage filed complete
5Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

Parinee Essence is a Residential / Group Housing project by Parinee Contour Construction Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001334 on 27 Jul 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 18 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameParinee Essence
  • TypeResidential / Group Housing
  • Location
    • Babrekar Nagar Road
    • Near Charkop
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001334
  • ReraGenie IDRG-MH-19897

Builder

  • NameParinee Contour Construction Private Limited
  • Entity typeCompany

Key dates

52 months past promisethis monthRegisteredJul 2017First promiseDec 2020Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Jul 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Dec 2020)
  • Buildings1 building record
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Parinee EssenceNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

Parinee Essence: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed106

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots106
Closed/Covered102
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,792 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI17773.0
Proposed, not sanctioned13,304 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR UNIT NO 001A HALLMARK BUSINESS PLAZA NEAR COLLECTOR OFFICE BANDRA EAST MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDHARMESH CHEVLI
EngineerJW Consultants LLP
PartnerRole in project
Parinee Contour Construction Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008428Dec 2020 → Dec 2021

Reason as filed by the promoter“Parinee Essence” is SRA project having 1 Rehab (with two wings) and 1 Sale Building (with three wings). The RCC construction of all buildings are completed. One wing of Rehab building is fully ready and OC is already obtained. The other wing of Rehab building is also nearly completed. The RCC of Sale building is entirely completed and finishing works have started. The project has got delayed due to various reasons beyond the control of Promoter, which are enlisted below:- A. There was a delay in demolition of existing commercial structure which occupied front portion of Wing A of the Sale Bui

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000000127VIJAY JAVLEKARPARINEE CONTOUR CONSTRUCTION PRIVATE LIMITED11/08/2017
CC006000000057208MR. YOGESH LAKHANI AND MRS. MANISHA LAKHANIPARINEE CONTOUR CONSTRUCTION PVT. LTD.24/12/2018
CC006000000292288Joshua Max DsouzaParinee Contour Construction Pvt Ltd08/08/2022
CC006000000480049MANGESH RAMESH MEHTAPARINEE CONTOUR CONSTRUCTION PVT LTD12/04/2024
CC12602184BRAZILLIA VAZParinee Contour Construction Private Limited14/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Jul 2022

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: Form 5 - Parinee Essence - FY 2023-24.pdf26 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Parinee Essence - FY 2023-24.pdf26 Dec 2024
Certificates of CA (Form 5)File: Essence - Rera Form 5 FY 2022-23.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Essence - Rera Form 5 FY 2022-23.pdf29 Sep 2023
Declaration in FORM BFile: Form B.pdf22 Jul 2023
Disclosure of sold/ booked inventoryFile: Dislcosure of sold unsold Booked Inventory 30th June 2023.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Essence March 2020.pdf6 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Essence March 2021.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence March 2018 Optimized.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 - Essence June 2022_opt_1.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 - Essence June 2022_opt_2.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence September 2022_opt_1.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence September 2022_opt_2.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence December 2022_opt_1.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence December 2022_opt_2.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence March 2023_opt_1.pdf6 Jul 2023
Certificates of CA (Form 3)File: Form 3 Essence March 2023_opt_2.pdf6 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence March 2018.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence March 2019.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence March 2020.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence March 2021.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence MARCH 2022.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence JUNE 2022.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence SEPT 2022.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence DEC 2022.pdf20 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Essence MARCH 2023.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Essence March 2018.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Essence March 2019.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Essence March 2020.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Essence March 2021.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 1 Essence MARCH 2022.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Essence June 2022.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Essence Sep 2022.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Essence Dec 2022.pdf20 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Essence March 2023.pdf20 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Essence March 2022.pdf20 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Essence March 2023.pdf20 Jun 2023
Certificates of CA (Form 3)File: Form 3 Essence March 2020.pdf7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 6 Certificates of CA (Form 5).pdf10 Jan 2023
Certificates of CA (Form 5)File: RERA Form 5 Parinee Essence FY 2021 22.pdf30 Aug 2022
Certificates of CA (Form 3)File: Parinee Essence Rera Form 3 FY 2021 22.pdf24 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Essence OC.pdf30 Jul 2022
Other - TechnicalFile: 1 RERA Disclosure.pdf2 Jul 2022
Other - TechnicalFile: 2 RD.pdf2 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PCCPL Form 1.pdf1 Jul 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Parinee Essence Society Reg Certificate.pdf17 Jun 2022
Certificates of CA (Form 3)File: Rera Form no 3 Essence Project dated 31_03_2021.pdf31 Dec 2021
Certificates of CA (Form 3)File: Rera Form no 3 Essence Project dated 31_03_2021.pdf31 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Essence 20_21.pdf31 Dec 2021
Certificates of CA (Form 5)File: Parinee Essence Rera Form 5 FY 2020-21.pdf29 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Engg Cert Essence_m.pdf31 Jul 2021
Declaration about Commencement CertificateFile: CC Declaration.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Engg Cert Essence_m.pdf30 Jul 2021
Disclosure of sold/ booked inventoryFile: RERA_Disclosure Sold.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificates of CA (Form 5) 2018-19.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Certificates of CA (Form 5) 2019-20.pdf30 Jul 2021
Details of encumbrancesFile: Index 2_indiabulls_105crore.pdf8 Feb 2021
Details of encumbrancesFile: Index 2_Swamini fund.pdf8 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: Essence Full CC sale Dt 23 11 2020.pdf25 Nov 2020
Certificates of CA (Form 5)File: Essence Form no 5 2020.pdf30 Sep 2020
Building plan approvalFile: 20190523 ESSENCE.pdf5 Aug 2020
Building Plan Approval (IOD)File: 20190523 ESSENCE.pdf5 Aug 2020
Certificates of CA (Form 3)File: Rera Form 3 - Essence.pdf7 Oct 2019
Certificates of CA (Form 5)File: Rera Form 5 - Essence.pdf7 Oct 2019
Certificates of CA (Form 3)File: Form 3 Rera - Essence.pdf30 Sep 2019
Certificates of CA (Form 5)File: Essence Form 5 FY_18_19.pdf30 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: Essence 2019 05 28 further C C .pdf30 May 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: Essence society name reservation.pdf1 Nov 2018
Certificates of CA (Form 5)File: Form 5 - Essence.pdf13 Oct 2018
Building plan approvalFile: IOD.pdf10 Oct 2018
Building plan approvalFile: IODaa.pdf10 Oct 2018
Building Plan Approval (IOD)File: IOD.pdf10 Oct 2018
Building Plan Approval (IOD)File: IODaa.pdf10 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Essence F C C 02 08 2018.pdf7 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch area cert ESSENCE.pdf31 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: Essence Sale CC - 06 Sep 2017_opt.pdf9 Sep 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4) Architect Certificate_Parinee Adney.pdf24 Jul 2017
Building plan approvalFile: 11)Building Plan Approval (IOD)_Parinee Essence.pdf22 Jul 2017
Layout approvalFile: 14)Copy of Layout Approval.pdf22 Jul 2017
PAN CardFile: 2)Parinee Contour Construction Pvt Ltd-PAN.pdf22 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Parinee Essence on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Charkop6,700+ in Mumbai Suburban

2 kmParinee EssenceCompleted 85Lapsed / revoked 53Other 104Dot size: filed unitsN

Filed coordinates, straight-line distance. 242 registered projects within 2 km.

Builder: Parinee Contour Construction Private Limited

Parinee Contour Construction Private Limited has 1 registration on MahaRERA, including Parinee Essence. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Parinee Essence shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Parinee Essence is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Parinee Essence?

The registered promoter entity is Parinee Contour Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Parinee Essence?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Parinee Essence?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Parinee Essence?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Parinee Essence?

The professionals named in the filing: Architect: DHARMESH CHEVLI; Engineer: JW Consultants LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Parinee Essence?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Parinee Essence. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Parinee Essence to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.