Home / Browse projects / Pune, Maharashtra / PARAMOUNT SMART CITY

Registration lapsed No litigation declared Residential / Group Housing project

PARAMOUNT SMART CITY

By AMARNATH BUILDERS AND DEVELOPERS

RG-MH-07782 · RERA P52100001196 · Last updated on MahaRERA portal: 25 Jul 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 33 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 49 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2024Possession promised33 months past this date
22 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 0%
1Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

PARAMOUNT SMART CITY is a Residential / Group Housing project by AMARNATH BUILDERS AND DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100001196 on 27 Jul 2017. Possession was promised by 31 Jan 2024 and is now 33 months past that date. The completion date has moved by 49 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePARAMOUNT SMART CITY
  • TypeResidential / Group Housing
  • Location
    • Porwal Road
    • Lohgaon
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001196
  • ReraGenie IDRG-MH-07782

Builder

  • NameAMARNATH BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersBALBHIM DASHRATH MORE, CHETAN GOVARDHAN GHULE, NARESH NARAYAN BARGE, BHAGWAT KERABA SHINDE
  • Declared earlier projects1 →

Key dates

33 months past promisethis monthRegisteredJul 2017First promiseDec 2019Revised toJan 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Jul 2017
  • Promised completion31 Jan 2024
  • Revised completionRevised to 31 Jan 2024 (originally 31 Dec 2019)
  • Buildings4 building records
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ENA100000
WING BNA130000
WING CNA100000
WING DNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 25 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 0%.

WING E0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING D0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities33

As on 25 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes75%
Street LightingYes75%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%
KITCHEN CHIMNEYYes0%
KITCHEN TROLLYYes100%
OPEN AMPHITHEATREYes0%
OPEN PARTY LAWNYes0%
KIDS ZONEYes0%
POP CEILING IN LIVING ROOMYes100%
POWER BACK FOR COMMON AREAYes0%
SOCIETY OFFICEYes0%
SWIMMING POOL AND KIDS POOLYes0%
YOGA CENTER AND MULTIPURPOSE HALLYes0%
CCTV CAMERAS IN COMMON AREAYes0%
ENTRANCE LOBBYYes100%
GAS PIPELINEYes0%
GAS STOVEYes0%
GREEN COMPOUND WALLYes0%
JOGGING TRACKYes0%
GYMNASIUMYes0%
ICONIC ENTRANCE PROJECT GATEYes100%

Parking filed316

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots316
Closed/Covered260
Open Space56
BuildingClosed/CoveredOpen SpaceTotal
WING E13424158
WING B721688
WING C541670

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
MOHINI BABULAL CHOUDHARY-Pune
JOGARAM MOTIJI CHOUDHARY-Pune
KALURAM GHISARAMJI CHOUDHARIMumbai CityMumbai City
SOHANLAL NARAYANLALJI CHOUDHARI-Pune
SANTOSH NIVRUTI MOZELOHGAONPune
OM BUILDCONLOHGAONPune
PANDURANG MURKUTELOHGAONPune
DNYANESHWAR SHELKELOHGAONPune

Approvals and building plan

Permissible FSI11637.84
Proposed, not sanctioned9,961 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKalyani Nagar , Vadgaonsheri Pune 411014

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr. Yogesh Waghchoure
EngineerKISHOR PREMCHAND JAIN
PartnerRole in project
AMARNATH BUILDERS AND DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005432Dec 2019 → Dec 2020

Reason as filed by the promoterIn our agreement to sale we have mentioned the possession date as December 2019. But due to the less booking of flat of our project have affected our financial strength, hence we are not able to give possession in the said time period. But we assure you that we are now able to give possession to our clients till 31st December 2020.

EXT52100010554Dec 2019 → Dec 2021

Reason as filed by the promoterProject work is in process , project possession date is postpone due to Manpower & Material unavailability. 80% work completed and expected work completion date will be Dec 2021

EXT52100017208Dec 2019 → Jan 2024

Reason as filed by the promoter1. As the entire country including Pune District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. In view of the curbs and measures imposed by the Governments, we stopped work till such time as the said lockdowns, curbs and measures were relaxed by the respective Governments. 2. In spite of our best efforts, the said Project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and we

Litigation declared1

CaseCourtStatus
410/2013/2013Pune district courtJudgement in favor of developer

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000290006Kamal Kumar GhoshAMARNATH BUILDERS & DEVELOPERS06/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Final Form B.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - March 20.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - March 21.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - March 22.pdf25 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - March 23.pdf25 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Dec 22.pdf22 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate March 23.pdf22 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate June 23.pdf22 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Dec 22.pdf22 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate March 23.pdf22 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate June 2023.pdf22 Jul 2023
Certificates of CA (Form 3)File: Amarnath Builders CA Cert Dec 22.pdf22 Jul 2023
Certificates of CA (Form 3)File: Amarnath Builders CA Cert Mar 23.pdf22 Jul 2023
Certificates of CA (Form 3)File: Amarnath Builders CA Cert June 23.pdf22 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERA Audit Report_17-18.pdf17 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Audit Report_18-19.pdf17 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit Report_21-22.pdf17 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: F Y 19-20.pdf7 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer quality 19-20-compressed.pdf7 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer quality 19-20-compressed.pdf7 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer quality 20-21-compressed.pdf7 Aug 2021
Disclosure of sold/ booked inventoryFile: disclosure sold unsold (1).pdf5 Aug 2021
Declaration about Commencement CertificateFile: DECLARATION FOR COMM.pdf3 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Letter.pdf3 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Cert (1).pdf3 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Cert (1).pdf3 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: F Y 19-20.pdf3 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: F Y 20-21.pdf3 Aug 2021
Building plan approvalFile: 1IOD.pdf31 Jul 2019
Building plan approvalFile: 2IOD.pdf31 Jul 2019
Building plan approvalFile: 3IOD.pdf31 Jul 2019
Building plan approvalFile: 4IOD.pdf31 Jul 2019
Building Plan Approval (IOD)File: 1IOD.pdf31 Jul 2019
Building Plan Approval (IOD)File: 2IOD.pdf31 Jul 2019
Building Plan Approval (IOD)File: 3IOD.pdf31 Jul 2019
Building Plan Approval (IOD)File: 4IOD.pdf31 Jul 2019
Details of encumbrancesFile: Index.pdf23 Jul 2019
OtherFile: MAHARERA other.pdf28 Oct 2018
Layout approvalFile: COPY OF LAYOUT.pdf23 Oct 2018
Building plan approvalFile: REDUCE PLAN RERA.pdf23 Oct 2018
Copy of Layout Approval (in case of layout)File: COPY OF LAYOUT.pdf23 Oct 2018
Building Plan Approval (IOD)File: REDUCE PLAN RERA.pdf23 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: PMC SANCTIONED RERA.pdf23 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: PMC SANCTIONED RERA.pdf23 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: PMC SANCTIONED RERA.pdf23 Oct 2018
Building plan approvalFile: final plan.pdf24 Jul 2017
Building plan approvalFile: final plan.pdf24 Jul 2017
Layout approvalFile: 1new1.pdf24 Jul 2017
Copy of Layout Approval (in case of layout)File: 1new1.pdf24 Jul 2017
Building Plan Approval (IOD)File: final plan.pdf24 Jul 2017
Building Plan Approval (IOD)File: final plan.pdf24 Jul 2017
Declaration in FORM BFile: amarnath from B new.pdf23 Jul 2017
Details of encumbrancesFile: pune court.pdf15 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf10 Jul 2017
PAN CardFile: PAN - AMARNATH.pdf9 Jul 2017
Copy of the legal title reportFile: Serch.pdf9 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From 1 Wing A.pdf9 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from 1 wing B.pdf9 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from A wing C.pdf9 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2.pdf9 Jul 2017
Certificates of CA (Form 3)File: From 3 CA - Final.pdf9 Jul 2017
Proforma of Allotment letterFile: Draft agreement.pdf27 Jun 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHIVNANDAN PARKSURVEY NO 156 COLONY NO 13 GANESH NAGAR BOPKHEL PUNE 41103116CompletedApr 2014Apr 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 49 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARAMOUNT SMART CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lohgaon13,700+ in Pune

2 kmPARAMOUNT SMART CITYCompleted 61Lapsed / revoked 20Other 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 152 registered projects within 2 km.

Builder: AMARNATH BUILDERS AND DEVELOPERS

AMARNATH BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including PARAMOUNT SMART CITY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that PARAMOUNT SMART CITY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARAMOUNT SMART CITY is delayed beyond 31 Jan 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARAMOUNT SMART CITY?

The registered promoter entity is AMARNATH BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARAMOUNT SMART CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARAMOUNT SMART CITY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARAMOUNT SMART CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARAMOUNT SMART CITY?

The professionals named in the filing: Architect: Mr. Yogesh Waghchoure; Engineer: KISHOR PREMCHAND JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARAMOUNT SMART CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARAMOUNT SMART CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARAMOUNT SMART CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.