ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / PARADISE GRANDEUR

Completed No litigation declared Residential / Group Housing project

PARADISE GRANDEUR

By PARIKH INVESTMENT AND DEVELOPMENT PVT. LTD.

RG-MH-24495 · RERA P99000004547 · Last updated on MahaRERA portal: 20 Feb 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 30 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
3 of 11Construction stages donefurthest along: Stilt Floor, 80%
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

PARADISE GRANDEUR is a Residential / Group Housing project by PARIKH INVESTMENT AND DEVELOPMENT PVT. LTD. in Palghar, Maharashtra, registered with MahaRERA as P99000004547 on 9 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2023. The completion date has moved by 30 months from the original filing.

At a glance

Project

  • NamePARADISE GRANDEUR
  • TypeResidential / Group Housing
  • Location
    • NEAR DMART
    • NEAR NEW VIVA COLLEGE
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000004547
  • ReraGenie IDRG-MH-24495

Builder

  • NamePARIKH INVESTMENT AND DEVELOPMENT PVT. LTD.
  • Entity typeCompany
  • DirectorsVINOD SHANTILAL PARIKH, CHETAN SHANTILAL PARIKH
  • Managing DirectorPANKAJ SHANTILAL PARIKH
  • Other registrations1 more →
  • Completed2 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2023
  • Revised completionRevised to 30 Jun 2023 (originally 31 Dec 2020)
  • Buildings1 building record
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PARADISE GRANDEURNA270000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.

PARADISE GRANDEUR: 36% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)15%
Plinth100%
Stilt Floor80%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed256

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots256
Closed/Covered242
Open Space14

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,922 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI14780.0
Proposed, not sanctioned14,780 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR VIKAS CHAMBER MITH CHOWKI LINK ROAD MALAD WEST MUMBAI 400064

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY NARANG
EngineerPARESH UNNARKAR
Chartered AccountantASHOK BANSAL
Chartered AccountantAKBINDER KAUR SAINI
PartnerRole in project
PARIKH INVESTMENT AND DEVELOPMENT PVT. LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000003661Dec 2020 → Dec 2022

Reason as filed by the promoterAs per Revised Development Permission dated 25th October 2019

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Sep 2022

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5_Paradise Grandeur_FY 2020-21.pdf20 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5_Paradise Grandeur_FY 2021-22_signed by Promoter.pdf20 Feb 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form-4_Paradise Grandeur_signed by Promoter.pdf8 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: revised Form-2A_Paradise Grandeur_FY 2021-22.pdf7 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-5_Paradise Grandeur_FY 2019-20.pdf7 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Paradise Grandeur OC_08-09-22.pdf13 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_30-06-2022_Paradise Grandeur_signed by PID.pdf14 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_30-06-2022_Paradise Grandeur_compressed-signed by promoter.pdf14 Jul 2022
Certificates of CA (Form 3)File: Form 3 Paradise Grandeu_30-06-22-Final_compressed-signed by Promoter.pdf14 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_31-03-2022_Paradise Grandeur.pdf4 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_31-03-2022_Paradise Grandeur_compressed.pdf4 May 2022
Certificates of CA (Form 3)File: Form- 3_Paradise Grandeur_31-03-22_compressed.pdf4 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_Paradise Grandeur_30-09-21_compressed.pdf23 Nov 2021
Certificates of CA (Form 3)File: Paradise Grandeur_Form-3 30-09-21_compressed.pdf2 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_Paradise Grandeur _30-06-2020.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_Paradise Grandeur_30-09-20_compressed.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_Paradise Grandeur_31-12-20_compressed.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form-2A_Paradise Grandeur_31-03-21_compressed.pdf19 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_Paradise Grandeur_30-06-21-compressed.pdf17 Aug 2021
Certificates of CA (Form 3)File: FORM-3_Paradise Grandeur_30-06-21.pdf9 Aug 2021
Certificates of CA (Form 3)File: FORM 3_ Paradise Grandeur_31-03-21-1.pdf15 May 2021
Layout approvalFile: Layout Plan_26-03-2021.pdf9 Apr 2021
Building plan approvalFile: Gr-Stilt-1st Podium Parking Plan_26-03-2021.pdf9 Apr 2021
Building plan approvalFile: 2nd-4th Podium Parking _1st Floor-Amenity Floor plan_26-03-2021.pdf9 Apr 2021
Building plan approvalFile: 5th-9th-13th-Refuge Floor Plan_26-03-2021.pdf9 Apr 2021
Building plan approvalFile: Typical Floor Plan_26-03-2021.pdf9 Apr 2021
Copy of Layout Approval (in case of layout)File: Layout Plan_26-03-2021.pdf9 Apr 2021
Building Plan Approval (IOD)File: Gr-Stilt-1st Podium Parking Plan_26-03-2021.pdf9 Apr 2021
Building Plan Approval (IOD)File: 2nd-4th Podium Parking _1st Floor-Amenity Floor plan_26-03-2021.pdf9 Apr 2021
Building Plan Approval (IOD)File: 5th-9th-13th-Refuge Floor Plan_26-03-2021.pdf9 Apr 2021
Building Plan Approval (IOD)File: Typical Floor Plan_26-03-2021.pdf9 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: Revised Development permission_Bldg No1_26-03-2021.pdf9 Apr 2021
Details of encumbrancesFile: Self Certification of Promoters_Paradise Grandeur.pdf9 Oct 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1_Paradise Grandeur_30-06-20_compressed.pdf24 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2_Paradise Grandeur_30-06-20_compressed.pdf24 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A_Paradise Grandeur_31-12-2019.pdf24 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A_Paradise Grandeur_31-3-2020.pdf24 Aug 2020
Certificates of CA (Form 3)File: Form 3_Paradise Grandeur_30-06-20_compressed.pdf24 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A- Paradise Grandeur_30-06-19.pdf7 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM-2A- Paradise Grandeur_30-09-19.pdf7 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM-5_CA-Annual Report_Paradise Grandeur-FY 2017-18.pdf7 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Paradise Grandeur-FY 2018-19.pdf7 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC Gr-1st Floor_Paradise Grandeur-1.pdf18 Nov 2019
Layout approvalFile: Layout plan.pdf16 Nov 2019
Building plan approvalFile: Paradise Grandeur-Gr_1st floor plan.pdf16 Nov 2019
Building plan approvalFile: Paradsie Grandeur-1st Amenity_2-4 Podium parking floors.pdf16 Nov 2019
Building plan approvalFile: Paradsie Grandeur_2nd to 4th_6th to 8th_10th to 12th Floor plan_reduce.pdf16 Nov 2019
Building plan approvalFile: Paradise Grandeur-5th-9th-13th floor plan.pdf16 Nov 2019
Building plan approvalFile: Revised Development permission 25-10-2019.pdf16 Nov 2019
Copy of the legal title reportFile: RP Joshi Title_Paradise Grandeur.pdf16 Nov 2019
Copy of Layout Approval (in case of layout)File: Layout plan.pdf16 Nov 2019
Building Plan Approval (IOD)File: Paradise Grandeur-Gr_1st floor plan.pdf16 Nov 2019
Building Plan Approval (IOD)File: Paradsie Grandeur-1st Amenity_2-4 Podium parking floors.pdf16 Nov 2019
Building Plan Approval (IOD)File: Paradsie Grandeur_2nd to 4th_6th to 8th_10th to 12th Floor plan_reduce.pdf16 Nov 2019
Building Plan Approval (IOD)File: Paradise Grandeur-5th-9th-13th floor plan.pdf16 Nov 2019
Building Plan Approval (IOD)File: Revised Development permission 25-10-2019.pdf16 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: Revised Development permission 25-10-2019.pdf16 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Paradise Grandeur.pdf16 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Paradise Grandeur.pdf16 Nov 2019
Certificates of CA (Form 3)File: FORM 3 CA Certificate Paradise Grandeur.pdf16 Nov 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Paradise Grandeur-FY 2018-19.pdf16 Nov 2019
Certificates of CA (Form 3)File: Affidavit for CA Certificate Form 3 Bldg no 1.pdf29 Jul 2017
Building plan approvalFile: Revised Development Permission_31-03-17.pdf27 Jul 2017
Layout approvalFile: Layout Plan .pdf27 Jul 2017
PAN CardFile: PID PAN Card.pdf27 Jul 2017
Copy of the legal title reportFile: Title Report Bldg no 1.pdf27 Jul 2017
Details of encumbrancesFile: Self Certifiation Paradise Grandeur.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan .pdf27 Jul 2017
Building Plan Approval (IOD)File: Revised Development Permission_31-03-17.pdf27 Jul 2017
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Paradise Grandeur.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Egineer Certificate Paradise Grandeur.pdf27 Jul 2017
Proforma of Allotment letterFile: Form B Affidavit cum Declaration.pdf27 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
PARADISE TOWERBEHIND NEW VIVA COLLLEGE VILLAGE BOLINJ VIRAR WEST DIST PALGAHR - 401 303164CompletedDec 2015Oct 2015
PARADISE PARK BUILDING NO 4 5 AND 6BEHIND NEW VIVA COLLEGE VIRAR WEST DIST PALGHAR328CompletedDec 2010Late, Sep 2011

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 30 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARADISE GRANDEUR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR NEW VIVA COLLEGE3,200+ in Palghar

2 kmPARADISE GRANDEURCompleted 36Lapsed / revoked 21Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 63 registered projects within 2 km.

Builder: PARIKH INVESTMENT AND DEVELOPMENT PVT. LTD.

PARIKH INVESTMENT AND DEVELOPMENT PVT. LTD. has 2 registrations on MahaRERA, including PARADISE RESIDENCY and PARADISE GRANDEUR. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if PARADISE GRANDEUR is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARADISE GRANDEUR?

The registered promoter entity is PARIKH INVESTMENT AND DEVELOPMENT PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARADISE GRANDEUR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PARADISE GRANDEUR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARADISE GRANDEUR?

The professionals named in the filing: Architect: SANJAY NARANG; Engineer: PARESH UNNARKAR; Chartered Accountant: ASHOK BANSAL; Chartered Accountant: AKBINDER KAUR SAINI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARADISE GRANDEUR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARADISE GRANDEUR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARADISE GRANDEUR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.