Home / Browse projects / Raigarh, Maharashtra / PANVEL PRIDE PHASE 2

Registered No litigation declared Residential / Group Housing project

PANVEL PRIDE PHASE 2

By Elysian Spaces Private Limited

RG-MH-30603 · RERA P52000030827 · Last updated on MahaRERA portal: 14 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 36 months from the original
10 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
33 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 143 documents Report an error

PANVEL PRIDE PHASE 2 is a Residential / Group Housing project by Elysian Spaces Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000030827 on 14 Sep 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 36 months from the original filing. 9 of the 42 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NamePANVEL PRIDE PHASE 2
  • TypeResidential / Group Housing
  • Location
    • Near Vidhyadhiraj Charitable Trust
    • Harigram Road
    • Kevale
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000030827
  • ReraGenie IDRG-MH-30603

Builder

  • NameElysian Spaces Private Limited
  • Entity typeCompany
  • DirectorSamarth Jigar Mehta
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2021First promiseDec 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Sep 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed143 files

Current status

21%9 of 42 units booked
36.9%Work done, per cost certificate

Figures as on 14 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA5519019
BNA5523023

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

A61%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
B61%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks82%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered8
Open Space15
BuildingClosed/CoveredOpen SpaceTotal
A448
B41115

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,275 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Aug 2026
LandownerVillageDistrict
Beena SinghGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityCIDCO /NAINA
Permissible FSI2034.08
Proposed, not sanctioned2,008 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Krishna Kamal CHS Shop No 1 - 2 Plot No 111/E/1 Sector 21 Nerul East Navi Mumbai
Estimated costRs 4.90 cr
Cost incurredRs 1.81 cr
Work done36.94%
BuildingWingEstimatedIncurred
ANARs 3.50 crRs 1.25 cr
BNARs 70.00 lakhRs 30.00 lakh
-NARs 70.00 lakhRs 26.00 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Rushabh Rathod Rushav Rathod
EngineerB S Sukthankar
EngineerSatish Hirkrishna Pandit
Chartered AccountantM H Kachhara
Chartered AccountantTarun Tater
PartnerRole in project
Elysian Spaces Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000024267Dec 2024 → Dec 2025

Reason as filed by the promoterWe humbly submit herewith that the project Panvel Pride Phase 2 located at Survey No 74/2/A/2/B/2 and 74/2/A/2/B/3, village Kevale, taluka Panvel, district Raigad- 410 206 was registered with MahaRERA in September, 2021. Due to unforeseen circumstances, the launch of the project was delayed. We did market, sell or receive any advances against the said project till date i.e 05th July, 2024. However, we have now started the construction of the project. We request you to humbly provide us an extension under Section 6 of RERA for one year till 31/12/2025 during which we plan on completing the proj

EA14102518117Dec 2024 → Dec 2027

Reason as filed by the promoterWe had received MahaRERA Registration for our above mentioned project on _//_ having validity till 31/12/2025. Due to market conditions, we did not begin the construction as well as sales of the project. Since 2025, we have begun the construction of the project and received Plinth Completion Certificate having Certificate No CIDCO/NAINA/Panvel/BP-414/PCC/Full/2025/0845 dated 18/02/2025. As on 07th October, 2025 the construction is in full swing and is currently at third slab. The same has been mentioned in Form 1 and photos attached. As on date, there has been no sale of any flat in the projec

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed143

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 143 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf14 Aug 2026
Withdrawal Update Form 2File: FORM 2.pdf14 Aug 2026
Withdrawal Update Form 3File: FORM-3.pdf14 Aug 2026
Withdrawal Update Form 1File: Form 1 Mar 26.pdf27 Apr 2026
Withdrawal Update Form 1File: Form 1 Mar 26.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 02 March 26.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 02 March 26.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 03 March 26.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 03 March 26.pdf27 Apr 2026
Form 5 (FY 2025-2026)File: ESPL Form 05 March 26.pdf27 Apr 2026
Withdrawal Update Form 1File: FORM 1 DEC 25.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 Dec 25.pdf24 Apr 2026
Form 2A (FY 2024-2025)File: 2A March 25.pdf10 Nov 2025
Form 2A (FY 2021-2022)File: 2A March 22.pdf10 Nov 2025
Form 2A (FY 2022-2023)File: 2A March 23.pdf10 Nov 2025
Form 2A (FY 2023-2024)File: 2A March 24.pdf10 Nov 2025
Form 5 (FY 2021-2022)File: Form 05 March 22.pdf10 Nov 2025
Form 5 (FY 2022-2023)File: Form 05 March 23.pdf10 Nov 2025
Form 5 (FY 2023-2024)File: Form 05 March 24.pdf10 Nov 2025
Form 5 (FY 2024-2025)File: Form 05 March 25.pdf10 Nov 2025
Building plan approvalFile: Approvel PLan.pdf4 Nov 2025
Withdrawal Update Form 1File: FORM 1 UPTO SEPT .pdf14 Oct 2025
Withdrawal Update Form 1File: FORM 1 UPTO SEPT .pdf14 Oct 2025
Withdrawal Update Form 1File: FORM 1 UPTO SEPT .pdf14 Oct 2025
Withdrawal Update Form 1File: FORM 1 UPTO SEPT .pdf14 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf14 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf14 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf14 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf14 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2025
Withdrawal Update Form 3File: Form 3.pdf14 Oct 2025
Self-declaration of Quarterly ProgressFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Untitled (2) 66.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Untitled (2) 66.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Untitled (2) 66.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: form 3 March 22.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Untitled (2) 66.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Untitled (2) 66.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: form -1 Dec 22.pdf13 Oct 2025
Form 2File: form 2A Dec 2022_.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: form - 1 March 23.pdf13 Oct 2025
Form 2File: form 2 March 23.pdf13 Oct 2025
Form 3File: form 3 March 23.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Untitled (2) 66.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: form 3 Jun 23.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: form - 1 Sep 23.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: form 3 Sep 23.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: form - 1 Dec 23 .pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: form - 1 March 24.pdf13 Oct 2025
Form 2File: Untitled (2) 66.pdf13 Oct 2025
Form 3File: Untitled (2) 66.pdf13 Oct 2025
Disclosure of Sold and Booked InventoryFile: Untitled (2) 66.pdf13 Oct 2025
Form 1File: Form - 1 Jun 24 .pdf13 Oct 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
PRATIK HILLSP52000019701Sector R3, RaigarhFeb 2019CompletedAug 2022Jun 2022

How this compares with Raigarh

21%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 36 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PANVEL PRIDE PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Harigram Road5,900+ in Raigarh

2 kmPANVEL PRIDE PHASE 2Completed 3Lapsed / revoked 5Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: Elysian Spaces Private Limited

Elysian Spaces Private Limited has 1 registration on MahaRERA, including PANVEL PRIDE PHASE 2. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if PANVEL PRIDE PHASE 2 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PANVEL PRIDE PHASE 2?

The registered promoter entity is Elysian Spaces Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PANVEL PRIDE PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PANVEL PRIDE PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PANVEL PRIDE PHASE 2?

The professionals named in the filing: Architect: Ar Rushabh Rathod Rushav Rathod; Engineer: B S Sukthankar; Engineer: Satish Hirkrishna Pandit; Chartered Accountant: M H Kachhara; Chartered Accountant: Tarun Tater. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PANVEL PRIDE PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PANVEL PRIDE PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PANVEL PRIDE PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.