Home / Browse projects / Raigarh, Maharashtra / Panvel Pride

Registration lapsed No litigation declared Residential / Group Housing project

Panvel Pride

By Ashiana Lifestyle

RG-MH-04246 · RERA P52000021424 · Last updated on MahaRERA portal: 9 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 12 months past the filed date
  • Completion date moved by 16 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 5 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Oct 2025Possession promised12 months past this date
94 of 110Construction stages doneacross 10 buildings; furthest along: Podiums (if any), 0%
282 of 477Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

Panvel Pride is a Residential / Group Housing project by Ashiana Lifestyle in Raigarh, Maharashtra, registered with MahaRERA as P52000021424 on 28 Jun 2019. Possession was promised by 31 Oct 2025 and is now 12 months past that date. The completion date has moved by 16 months from the original filing. 195 of the 477 units on this registration are recorded sold or booked, and 94 of 110 construction stages are filed complete.

At a glance

Project

  • NamePanvel Pride
  • TypeResidential / Group Housing
  • Location
    • 75/1/A
    • Kevale
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000021424
  • ReraGenie IDRG-MH-04246

Builder

  • NameAshiana Lifestyle
  • Entity typePartnership
  • PartnersSamarth Jigar Mehta, Shreyas Anandkumar Podar, Anita Mahendra Kachhara, Anandkumar Shyamsunder Podar, Ashok Moolchand Jain
  • Declared earlier projects6 →

Key dates

12 months past promisethis monthRegisteredJun 2019First promiseJun 2024Revised toOct 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Jun 2019
  • Promised completion31 Oct 2025
  • Revised completionRevised to 31 Oct 2025 (originally 30 Jun 2024)
  • Buildings10 building records
  • Documents filed101 files

Current status

41%195 of 477 units booked

Figures as on 9 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA5444044
B WINGNA5440040
C WINGNA5444044
D WINGNA5450050
E WINGNA5450050
F WING EWS and SalesNA5489089
G WINGNA5454054
H WINGNA5450050
I WINGNA5440040
J WINGNA5416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 9 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

94 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Podiums (if any), at 0%.

A WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F WING EWS and Sales73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
J WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes10%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed95

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots95
Closed/Covered94
Open Space1
BuildingClosed/CoveredOpen SpaceTotal
A WING15015
B WING15015
C WING15015
D WING15015
H WING15015
I WING15015
J WING415

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area15,070 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jun 2025

Approvals and building plan

Sanctioning authorityNaina
Permissible FSI14576.96
Proposed, not sanctioned14,577 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGroun floor Krishna Kamal CHS Shop 1-2 plot no 111 E 1 Sector 21 Nerul East

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Patel Architects
EngineerB S Sukthankar and Associates
Chartered AccountantVira & Gor
Chartered AccountantTarun H Tater
PartnerRole in project
Ashiana Lifestyle-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017861Jun 2024 → Jun 2025

Reason as filed by the promoterWe humbly submit herewith that the project got delayed slightly due to the COVID-19 pandemic.We would like to inform that we received plinth completion certificate on 21/02/2023 for wings B, C, D, E, H, I, J. Since that, work has been going at full speed and as on 30.09.2023, we have already completed 21 out of 35 slabs {B (4), C (4), D (2), E (4), H (3), I (4), J (0)} and plinth for A wing is 100% complete and for F and G wing, the plinth work is about 85% complete. Also as on 12th October, 2023. We are expected to complete the project and receive the occupancy certificate in the extended dea

EA26062501806Jun 2024 → Oct 2025

Reason as filed by the promoterConstruction of buildings B, C, D, E, F EWS, G, H, I, J is complete; Lift installation and finishing works everything is done. Wings A, F Sale and G are almost complete with only final stage tasks where work is in progress like completing the lift installation, painting etc is pending. Infrastructure works is almost completely ready. Trimix work is started. Drainage, electric, water supply lines are laid. Application process for occupancy certificate has also begun and we are planning to do submission within next week itself. Kindly request you to just provide an extension for 04 months so tha

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Nov 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 .pdf9 Jun 2025
Certificates of CA (Form 3)File: Form 3 .pdf13 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (2024 SEPTEMBER).pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (2024 DECEMBER).pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (1).pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unite1.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf16 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf16 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 24.pdf11 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf11 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf11 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold 1.pdf11 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf25 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold Final.pdf13 Jan 2024
Certificates of CA (Form 3)File: Form 3_compressed.pdf13 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2a.pdf31 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf31 Oct 2023
Certificates of CA (Form 3)File: Form 3.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold Final.pdf20 Oct 2023
Certificates of CA (Form 3)File: Form 3.pdf28 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2023.pdf11 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf2 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Book Inventory Jun 2023.pdf2 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold march 23.pdf16 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 23.pdf11 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 23.pdf9 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2022.pdf14 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2022.pdf14 Feb 2023
Proforma of Agreement for saleFile: Draft Agreement.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2022.pdf7 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: AL Form 2A Dec 2022_.pdf7 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AL Form 5.pdf7 Feb 2023
Disclosure of sold/ booked inventoryFile: 1 Disclosure of sold booked inventory.pdf23 Nov 2022
Proforma of Agreement for saleFile: Proforma Agreement.pdf23 Nov 2022
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreemen.pdf23 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details including no encumbrances.pdf19 Nov 2022
Building plan approvalFile: 1 Amended 4th Floor CC Plan of 3 Building_ 11.pdf17 Nov 2022
Building plan approvalFile: Amended 4th Floor CC Plan of 3 Building 22.pdf17 Nov 2022
Details of encumbrances concerned to FinanceFile: No Encumbrances Certificate.pdf17 Nov 2022
Details of encumbrances concerned to LegalFile: No Encumbrances Certificate.pdf17 Nov 2022
Building Plan Approval (IOD)File: 1 Amended 4th Floor CC Plan of 3 Building_ 11.pdf17 Nov 2022
Building Plan Approval (IOD)File: Amended 4th Floor CC Plan of 3 Building 22.pdf17 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Amended CC 4th Floor.pdf17 Nov 2022
Declaration about Commencement CertificateFile: Format D.pdf17 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Kevale Sep 2022_compressed (1).pdf17 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep 2022.pdf17 Nov 2022
CERSAI detailsFile: CERSAI.pdf17 Nov 2022
Certificates of CA (Form 3)File: Form 3 Sep 2022_compressed.pdf17 Nov 2022
Proforma of Agreement for saleFile: Proforma Agreement.pdf17 Nov 2022
Certificates of CA (Form 3)File: Form 3.pdf12 Mar 2022
Proforma of Allotment letterFile: Draft Agreement_.pdf12 Mar 2022
Layout approvalFile: 0001 - 0003.pdf30 Jun 2021
Building plan approvalFile: 0004 - 0007.pdf30 Jun 2021
Building plan approvalFile: 0008 - 00010.pdf30 Jun 2021
Building plan approvalFile: 00011 - 00013.pdf30 Jun 2021
Layout approvalFile: Layout Plan.pdf30 Jun 2021
Copy of Layout Approval (in case of layout)File: 0001 - 0003.pdf30 Jun 2021
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf30 Jun 2021
Building Plan Approval (IOD)File: 0004 - 0007.pdf30 Jun 2021
Building Plan Approval (IOD)File: 0008 - 00010.pdf30 Jun 2021
Building Plan Approval (IOD)File: 00011 - 00013.pdf30 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Revised CC Ashiana Lifestyle.pdf30 Jun 2021
Building plan approvalFile: Final 1.pdf22 Jun 2019
Building plan approvalFile: Final 2.pdf22 Jun 2019
Building plan approvalFile: final 3.pdf22 Jun 2019
Building plan approvalFile: Final 4.pdf22 Jun 2019
Building plan approvalFile: final 5.pdf22 Jun 2019
Building plan approvalFile: final 6.pdf22 Jun 2019
Building plan approvalFile: final 7.pdf22 Jun 2019
Building plan approvalFile: Final 8.pdf22 Jun 2019
Building plan approvalFile: Final 9.pdf22 Jun 2019
Building plan approvalFile: final 10.pdf22 Jun 2019
Building plan approvalFile: Final 11.pdf22 Jun 2019
Building plan approvalFile: Final 12.pdf22 Jun 2019
Building plan approvalFile: final 13.pdf22 Jun 2019
Building Plan Approval (IOD)File: Final 1.pdf22 Jun 2019
Building Plan Approval (IOD)File: Final 2.pdf22 Jun 2019

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

5 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Panvel ParadiseNew Panvel159CompletedJul 2017Jul 2017
Elite ResidencyUlve28CompletedDec 2016Oct 2016
Tulip PlazaKaranjade40CompletedDec 2015May 2015
Pratik GardenKaranjade10CompletedOct 2015Jul 2015
Elite HomesSukhapur27CompletedJul 2015Feb 2015

How this compares with Raigarh

41%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 16 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Panvel Pride on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kevale5,900+ in Raigarh

Builder: Ashiana Lifestyle

Ashiana Lifestyle has 1 registration on MahaRERA, including Panvel Pride. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Panvel Pride shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Panvel Pride is delayed beyond 31 Oct 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Panvel Pride?

The registered promoter entity is Ashiana Lifestyle, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Panvel Pride?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Panvel Pride?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Panvel Pride?

The professionals named in the filing: Architect: Atul Patel Architects; Engineer: B S Sukthankar and Associates; Chartered Accountant: Vira & Gor; Chartered Accountant: Tarun H Tater. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Panvel Pride?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Panvel Pride. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Panvel Pride to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.