Pankaj Aasmaan Phase III

By Pankaj Developers

RG-MH-72408 · RERA P52100016512 · Last updated on MahaRERA portal: 17 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 62 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 62 months from the original
44 of 44Construction stages doneacross 4 buildings; every applicable stage filed complete
29 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 125 documents Report an error

Pankaj Aasmaan Phase III is a Residential / Group Housing project by Pankaj Developers in Pune, Maharashtra, registered with MahaRERA as P52100016512 on 21 May 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 62 months from the original filing. 91 of the 120 units on this registration are recorded sold or booked, and 44 of 44 construction stages are filed complete.

At a glance

Project

  • NamePankaj Aasmaan Phase III
  • TypeResidential / Group Housing
  • Location
    • Lohagoan Wagholi Road
    • Sant Nagar
    • LOHGAON
    • Haveli
    • Pune
    • 411047
  • Pincode411047
  • RERA no.P52100016512
  • ReraGenie IDRG-MH-72408

Builder

  • NamePankaj Developers
  • Entity typePartnership
  • PartnerVanita Anil Gogavale
  • Other registrations6 more →
  • Completed1 of 7
  • Declared earlier projects3 →

Key dates

this monthRegisteredMay 2018First promiseOct 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 May 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 1 Oct 2021)
  • Buildings4 building records
  • Documents filed125 files

Current status

76%91 of 120 units booked
98.4%Work done, per cost certificate

Figures as on 17 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
JNA5432032
INA5432032
FNA5432032
ENA5424024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

44 of 44 construction stages are filed complete across 4 buildings.

J100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes20%
Landscaping & Tree PlantingYes50%
Street LightingYes100%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes25%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes0%

Parking filed120

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots120
Closed/Covered120
BuildingClosed/CoveredTotal
J3232
I3232
F3232
E2424

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,686 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 May 2025
LandownerVillageDistrict
Pandurang Eknath KheseLOHGAONPune
Baban Mahadev KheseLOHGAONPune
Sandeep Raghunath GarudLOHGAONPune
Pankaj DevelopersHadapsarPune
Sambaji Damodar GarudLOHGAONPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI9686.48
Proposed, not sanctioned9,686 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEmpire Estate Chinchwad Pune 411019
Estimated costRs 17.92 cr
Cost incurredRs 17.63 cr
Work done98.36%
BuildingWingEstimatedIncurred
JNARs 4.56 crRs 4.56 cr
INARs 4.55 crRs 4.55 cr
FNARs 4.55 crRs 4.55 cr
ENARs 3.49 crRs 3.49 cr
-NARs 77.26 lakhRs 47.90 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkur Associates
EngineerAjit Popatrao Mahadik
Chartered AccountantSS YelawandeAssociates
Chartered AccountantSPCM and Associates
Chartered AccountantRSMS AND ASSOCIATES
PartnerRole in project
Pankaj Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100006311Oct 2021 → Sep 2022

Reason as filed by the promoterI, Anil Ramrao Gogavale Partner of M/s Pankaj Developers having Maha RERA registered project Pankaj Aasmaan Phase III with Maha RERA registration No.P52100016512 hereby declare that while initial registration there was typo error in respect of Proposed Date of Completion. The Proposed Date of Completion as per Maha RERA Registration Certificate was 1-April-2021 which was due to Typo Error and should be considered as 1-April-2022. Further due to COVID-19 pandemic situation the proposed date of completion should be considered as 1-October-2022 after considering universal extension extended to al

EXT52100015294Oct 2021 → Sep 2024

Reason as filed by the promoterDue to COVID Pandemic project has been delayed. So we are requesting you to please Extent project completion Date up to 30/09/2024

EXT52100025037Oct 2021 → Dec 2026

Reason as filed by the promoterRespected Sir, We are providing you an update on the construction progress of our project. Despite the challenges of COVID-19 pandemic, We informing you that we have successfully completed 99% of the construction work. Currently, we are working on completing the common amenities and obtaining the completion certificate. We kindly request an extension of our project deadline until December 31, 2026. This extension will allow us to finalize the remaining tasks and ensure the successful completion of the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 May 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 May 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 May 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed125

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 125 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Phase III.pdf17 Jun 2026
Withdrawal Update Form 1File: Phase III Architect.pdf23 Apr 2026
Withdrawal Update Form 2File: Form 2 Phase III.pdf23 Apr 2026
Withdrawal Update Form 3File: CA Phase III.pdf23 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Phase III.pdf22 Apr 2026
Withdrawal Update Form 2File: Form-2 Phase III.pdf22 Apr 2026
Withdrawal Update Form 3File: CA Certificate Form III.pdf22 Apr 2026
Withdrawal Update Form 1File: Phase III.pdf21 Apr 2026
Withdrawal Update Form 2File: Phase III.pdf21 Apr 2026
Withdrawal Update Form 3File: Phase III.pdf21 Apr 2026
Withdrawal Update Form 1File: Architec Certificate Phase III.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 Phase III.pdf20 Apr 2026
Withdrawal Update Form 3File: CA Phase III.pdf20 Apr 2026
Form 2A (FY 2024-2025)File: Phase III Form 2A.pdf28 Oct 2025
Form 2A (FY 2024-2025)File: Phase III Form 2A.pdf28 Oct 2025
Form 5 (FY 2024-2025)File: From 5 Phase III.pdf14 Oct 2025
Form 1File: ARCHITECTS CERTIFICATE PHASE--lll.pdf30 May 2025
Form 2File: Engineer Certificate Phase III.pdf30 May 2025
Form 3File: CA Certificate Phase III.pdf30 May 2025
Disclosure of Sold and Booked InventoryFile: Sold & Unsold - Phase III.pdf30 May 2025
Declaration in FORM BFile: Affidavit cum Declaration (RERA).pdf23 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration.pdf13 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf12 Nov 2024
Deviation Report with respect to model copy of AgreementFile: Model Agreement to Sale.pdf12 Nov 2024
Details of encumbrances concerned to FinanceFile: Pankaj Developers- No Dues Prachay.pdf11 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Phase-III.pdf11 Nov 2024
Certificates of CA (Form 3)File: CA Phase III .pdf11 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE, Phase III.pdf11 Nov 2024
Deviation Report with respect to Allotment letterFile: ALLOTMENT LETTER.pdf11 Nov 2024
Details of encumbrances concerned to LegalFile: Pankaj Developers- No Dues Prachay.pdf11 Nov 2024
Proforma of Agreement for saleFile: Agreement Draft.pdf11 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Phase III.pdf11 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate Phase III.pdf29 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Phase III.pdf23 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Phase III.pdf23 Jul 2024
Disclosure of sold/ booked inventoryFile: Phase-III.pdf23 Jul 2024
Certificates of CA (Form 3)File: CA Certificate Phase III.pdf23 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Phase III.pdf20 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE Phase III.pdf20 Jun 2024
Certificates of CA (Form 3)File: CA Certificate Phase III.pdf20 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Rera Phase III.pdf20 Jun 2024
Disclosure of sold/ booked inventoryFile: Phase III- 31-12-2023 Sold Unsold.pdf15 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Phase III 31-12-2023.pdf10 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Phase III- 31-12-2023.pdf10 Jan 2024
Certificates of CA (Form 3)File: CA Certificate Phase-III 31-12-2023.pdf10 Jan 2024
Disclosure of sold/ booked inventoryFile: Phase III.pdf4 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase III 30-09-2023.pdf29 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate Phase III 30-09-2023.pdf29 Nov 2023
Certificates of CA (Form 3)File: CA Certificate Phase III- 30-09-2023.pdf29 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase- III (30th June 2023).pdf1 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase - III June-2023.pdf1 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Phase III 2022-23.pdf1 Sep 2023
Certificates of CA (Form 3)File: CA Cert Phase- III June 2023.pdf1 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III - March 23.pdf4 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III - March 23.pdf4 May 2023
Certificates of CA (Form 3)File: Form 3 Phase III - March 23.pdf4 May 2023
Declaration about Commencement CertificateFile: Form D Commencement Cert Phase III.pdf21 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Phase III 2019-20.pdf21 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Phase III 2020-21.pdf21 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Phase III 2021-22.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III March 2019.pdf8 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III March 2020.pdf8 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III March 2021.pdf8 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III Sept 2022.pdf8 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III Dec 2022.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III March 2019.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III March 2020.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III March 2021.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III March 2022.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III Sep 22.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III Dec 2022.pdf8 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold Phase - III Up to Dec 2022.pdf8 Apr 2023
Certificates of CA (Form 3)File: CA Certificate March 2019.pdf8 Apr 2023
Certificates of CA (Form 3)File: CA Certificate March 2020.pdf8 Apr 2023
Certificates of CA (Form 3)File: CA Certificate March 2021.pdf8 Apr 2023
Certificates of CA (Form 3)File: CA Certificate Sept 2022.pdf8 Apr 2023
Certificates of CA (Form 3)File: CA Certificate Dec 2022.pdf8 Apr 2023
Declaration about Commencement CertificateFile: Declaration Phase- III.pdf17 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect certificate phase 3 up to March 2022_compressed.pdf17 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase III.pdf17 Oct 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Pankaj Aasmaan phase 172 73 lohegaon Haveli Pune119CompletedDec 2019Aug 2017

How this compares with Pune

76%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 62 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pankaj Aasmaan Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sant Nagar13,700+ in Pune

Builder: Pankaj Developers

Pankaj Developers has 7 registrations on MahaRERA, including Pankaj Aasmaan Phase II and Pankaj Aasmaan Phase I. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Pankaj Aasmaan Phase III is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pankaj Aasmaan Phase III?

The registered promoter entity is Pankaj Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pankaj Aasmaan Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Pankaj Aasmaan Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pankaj Aasmaan Phase III?

The professionals named in the filing: Architect: Ankur Associates; Engineer: Ajit Popatrao Mahadik; Chartered Accountant: SS YelawandeAssociates; Chartered Accountant: SPCM and Associates; Chartered Accountant: RSMS AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pankaj Aasmaan Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pankaj Aasmaan Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pankaj Aasmaan Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.