Home / Browse projects / Kolhapur, Maharashtra / PALLAVI COOPERATIVE HOUSING SOCIETY
PALLAVI COOPERATIVE HOUSING SOCIETY
By VARADLAXMI AND KAPADE DEVELOPERS
RG-MH-32930 · RERA P53000080500 · Last updated on MahaRERA portal: 30 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PALLAVI COOPERATIVE HOUSING SOCIETY is a Residential / Group Housing project by VARADLAXMI AND KAPADE DEVELOPERS in Kolhapur, Maharashtra, registered with MahaRERA as P53000080500 on 11 Jun 2025. Possession is promised by 31 Dec 2028. 2 of the 34 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NamePALLAVI COOPERATIVE HOUSING SOCIETY
- TypeResidential / Group Housing
- Location
- NAGALA PARK
- Kolhapur (M Corp.)
- Karvir
- Kolhapur
- 416003
- Pincode416003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53000080500
- ReraGenie IDRG-MH-32930
Builder
- NameVARADLAXMI AND KAPADE DEVELOPERS
- Entity typePartnership
- PartnersSATYAJIT ANIL KAPADE, RAHUL PRAKASH BANDIWADEKAR
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on11 Jun 2025
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed50 files
Current status
Figures as on 30 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| PALLAVI COOPERATIVE HOUSING SOCIETY | NA | 10 | 9 | 34 | 0 | 34 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Plinth, at 90%.
PALLAVI COOPERATIVE HOUSING SOCIETY: 31% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 30% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 30% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| VARDLAXMI AND KAPADE DEVELOPERS | Kolhapur (M Corp.) | Kolhapur |
| PALLAVI COOPERATIVE HOUSING SOCIETY | Kolhapur (M Corp.) | Kolhapur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| PALLAVI COOPERATIVE HOUSING SOCIETY | NA | Rs 11.36 cr | Rs 1.42 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAMBHAJI PATIL |
| Engineer | UDAYRAJ MALKAR |
| Chartered Accountant | SAMIR BHAGWAT |
| Chartered Accountant | Shankar Vitthal Patil |
| Partner | Role in project |
|---|---|
| VARADLAXMI AND KAPADE DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Feb 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Feb 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Feb 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed50
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form_1_Architect_Certificate.pdf | 30 Apr 2026 |
| Withdrawal Update Form 2File: Form_2_engineers_Certificate.pdf | 30 Apr 2026 |
| Withdrawal Update Form 3File: From_3_Varadlaxmi_Kapade_31032026.pdf | 30 Apr 2026 |
| Withdrawal Update Form 1File: Form_1_Architects Certificate.pdf | 13 Mar 2026 |
| Withdrawal Update Form 1File: Form_1_Architects Certificate.pdf | 13 Mar 2026 |
| Withdrawal Update Form 1File: Form_1_Architects Certificate.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: Form_2_ENGINEERS CERTIFICATE 30062025.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: Form_2_ENGINEERS CERTIFICATE 30092025.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: Form_2_ENGINEERS CERTIFICATE 31122025.pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: Form_3_Varadlaxmi And Kapade_30062025.pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: Form_3_Vardlaxmi And Kapade_30092025.pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: Form_3_VaradlaxmI And Kapade_31122025.pdf | 13 Mar 2026 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST 2.pdf | 20 May 2025 |
| Other - FinanceFile: ENCUM-2025.pdf | 15 Apr 2025 |
| Declaration in FORM BFile: CHS-FORMB.pdf | 15 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 15 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf | 15 Mar 2025 |
| Other - TechnicalFile: PALLAVI-DEC.pdf | 15 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B.pdf | 15 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: NO-BOJA.pdf | 19 Feb 2025 |
| Details of encumbrances concerned to LegalFile: NO-BOJA.pdf | 19 Feb 2025 |
| Proforma of Agreement for saleFile: PALLAVI-AFS-RERA.pdf | 19 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER-ORG.pdf | 19 Feb 2025 |
| Layout approvalFile: Pallavi Nakashya New.pdf | 13 Feb 2025 |
| Copy of the legal title reportFile: rera-search-report.pdf | 13 Feb 2025 |
| Copy of Layout Approval (in case of layout)File: Pallavi Nakashya New.pdf | 13 Feb 2025 |
| Proforma of Allotment letterFile: pallavi-allot-letter.pdf | 12 Feb 2025 |
| Declaration in FORM BFile: pallavi-formB.pdf | 12 Feb 2025 |
| Building plan approvalFile: 01-04.pdf | 10 Feb 2025 |
| Building plan approvalFile: 02-04.pdf | 10 Feb 2025 |
| Building plan approvalFile: 03-04.pdf | 10 Feb 2025 |
| Building plan approvalFile: 04-04.pdf | 10 Feb 2025 |
| PAN CardFile: pan-card.pdf | 10 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: NO-MORTGAGE.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 10 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Bandkam Parvana.pdf | 10 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 01-04.pdf | 10 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 02-04.pdf | 10 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 03-04.pdf | 10 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 04-04.pdf | 10 Feb 2025 |
| Declaration about Commencement CertificateFile: CC-DECLARATION.pdf | 10 Feb 2025 |
| CERSAI detailsFile: NO-MORTGAGE.pdf | 10 Feb 2025 |
| Deviation Report with respect to Allotment letterFile: ALLOTMENT-NO-DEVIATION.pdf | 10 Feb 2025 |
| Details of encumbrances concerned to LegalFile: NO-MORTGAGE.pdf | 10 Feb 2025 |
| Other - TechnicalFile: Property Card New Pallavi.pdf | 10 Feb 2025 |
| Other - TechnicalFile: Pallavi Nakashya New.pdf | 10 Feb 2025 |
| Deviation Report with respect to model copy of AgreementFile: AFS-DEVIATION.pdf | 10 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST 1.pdf | 10 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE OF SECURED AND UNSECURED FINANCE.pdf | 10 Feb 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 50 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PALLAVI COOPERATIVE HOUSING SOCIETY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAGALA PARK880+ in Kolhapur
Filed coordinates, straight-line distance. 156 registered projects within 2 km.
24 KEYWEST EAST AND WEST AVENUE
KEYWEST INFRA
Loknagari Karande Mala
VIKESH ABHAYKUMAR OSWAL
KRYSTAL TOWERS
RAYSONS CONSTRUCTIONS
GAYATRI-BHAWANI APARTMENT
Vijaykumar Vasudev Patki
EMINENT VISION TOWER
ACE DEVELOPERS
THE PARKSIDE
DESHPANDE INFRA
See every Kolhapur project, with the district possession charts
Builder: VARADLAXMI AND KAPADE DEVELOPERS
VARADLAXMI AND KAPADE DEVELOPERS has 1 registration on MahaRERA, including PALLAVI COOPERATIVE HOUSING SOCIETY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if PALLAVI COOPERATIVE HOUSING SOCIETY is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PALLAVI COOPERATIVE HOUSING SOCIETY?
The registered promoter entity is VARADLAXMI AND KAPADE DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PALLAVI COOPERATIVE HOUSING SOCIETY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for PALLAVI COOPERATIVE HOUSING SOCIETY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PALLAVI COOPERATIVE HOUSING SOCIETY?
The professionals named in the filing: Architect: SAMBHAJI PATIL; Engineer: UDAYRAJ MALKAR; Chartered Accountant: SAMIR BHAGWAT; Chartered Accountant: Shankar Vitthal Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PALLAVI COOPERATIVE HOUSING SOCIETY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback