ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / PALAI VILLAS - PHASE 2

Registered No litigation declared Residential / Group Housing project

PALAI VILLAS - PHASE 2

By N D DEVELOPERS

RG-MH-14270 · RERA P51600033459 · Last updated on MahaRERA portal: 29 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 60 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 60 months from the original
2 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 20%
135 of 150Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

PALAI VILLAS - PHASE 2 is a Residential / Group Housing project by N D DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600033459 on 22 Feb 2022. Possession is promised by 31 Dec 2029. The completion date has moved by 60 months from the original filing. 15 of the 150 units on this registration are recorded sold or booked, and 2 of 33 construction stages are filed complete.

At a glance

Project

  • NamePALAI VILLAS - PHASE 2
  • TypeResidential / Group Housing
  • Location
    • LAMROAD
    • DEOLALI
    • VIHITGAON
    • Nashik
    • 422101
  • Pincode422101
  • RERA no.P51600033459
  • ReraGenie IDRG-MH-14270

Builder

  • NameN D DEVELOPERS
  • Entity typePartnership
  • Partnersdhanji gala, bharti shah, NAVIN SHAH
  • Other registrations4 more →
  • No longer live2 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2022First promiseDec 2024Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Feb 2022
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2024)
  • Buildings3 building records
  • Documents filed38 files

Current status

10%15 of 150 units booked
22.4%Work done, per cost certificate

Figures as on 29 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE 1NA44404
TYPE 2NA44404
TYPE 3NA441420142

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 29 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 20%.

TYPE 13%
ActivityProgress
Excavation5%
Basement (if any)5%
Podiums (if any)0%
Plinth5%
Stilt Floor5%
Slabs of Super Structure5%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE 222%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth10%
Stilt Floor10%
Slabs of Super Structure10%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TYPE 32%
ActivityProgress
Excavation20%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Closed/Covered65
BuildingClosed/CoveredTotal
TYPE 16363
TYPE 211
TYPE 311

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,981 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityDeolali Cantonment Board
Permissible FSI10143.0
Proposed, not sanctioned10,143 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 16 GROUND FLOOR KANAKIA ZILLION KURLA WEST MUMBAI 400070
Estimated costRs 15.18 cr
Cost incurredRs 3.39 cr
Work done22.37%
BuildingWingEstimatedIncurred
TYPE 1NARs 11.45 crRs 2.59 cr
TYPE 2NARs 2.29 crRs 80.71 lakh
TYPE 3NARs 1.44 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectONE ARCHITECTURAL CONSULTANT
EngineerGAURAV NANDA
Chartered AccountantJRSM & ASSOCIATES
PartnerRole in project
N D DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA18092502629Dec 2024 → Dec 2029

Reason as filed by the promoterDear Sir/Madam, We hereby apply for extension of the project, Palai Villas - Phase 2. Owing to the financial difficulties and death of one of the partners, there was a delay in execution of the project. We have now secured financial closure and will endeavor to complete the project by 31 December 2030

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_Dec 25.pdf29 May 2026
Withdrawal Update Form 1File: Form 1_Dec 25.pdf29 May 2026
Withdrawal Update Form 1File: Form 1_Dec 25.pdf29 May 2026
Withdrawal Update Form 1File: Form 1_Mar 26.pdf29 May 2026
Withdrawal Update Form 229 May 2026
Withdrawal Update Form 229 May 2026
Withdrawal Update Form 229 May 2026
Withdrawal Update Form 2File: FORM 2_MAR 26.pdf29 May 2026
Withdrawal Update Form 3File: FORM 3_dec 25_new.pdf29 May 2026
Withdrawal Update Form 3File: FORM 3_dec 25_new.pdf29 May 2026
Withdrawal Update Form 3File: FORM 3_dec 25_new.pdf29 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (3) (1).pdf29 May 2026
Form 2A (FY 2024-2025)File: Form 2A_24-25.pdf23 Mar 2026
Form 1File: Form 1_Q2_compressed.pdf23 Feb 2026
Form 2File: Form 2_Q2.pdf23 Feb 2026
Form 3File: Form 3 - 6-June-25.pdf23 Feb 2026
Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD.pdf23 Feb 2026
Form 1File: Form 1_Q2_compressed.pdf23 Feb 2026
Form 2File: Form 2_Q2.pdf23 Feb 2026
Form 3File: Form 3 - 6-June-25.pdf23 Feb 2026
Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD.pdf23 Feb 2026
Withdrawal Update Form 1File: Form 1_Q2_compressed.pdf23 Feb 2026
Withdrawal Update Form 223 Feb 2026
Withdrawal Update Form 3File: PV 2 Signed.pdf23 Feb 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf23 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: cc_compressed.pdf18 Feb 2022
Declaration about Commencement CertificateFile: CC Declaration_signed.pdf18 Feb 2022
CERSAI detailsFile: CERSAI_Search_Report_200230599499_For_Debtor_Based_Search_18_02_2022_19_11_08_335.pdf18 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: pv form 3 v1.pdf18 Feb 2022
Layout approvalFile: layout approval_compressed.pdf12 Nov 2021
Building plan approvalFile: 1 Building Plan Approval (IOD).pdf12 Nov 2021
PAN CardFile: Pan- N D Developers.pdf12 Nov 2021
Copy of the legal title reportFile: title report_compressed.pdf12 Nov 2021
Details of encumbrancesFile: encumbrance Letter.pdf12 Nov 2021
Copy of Layout Approval (in case of layout)File: layout approval_compressed.pdf12 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval (IOD).pdf12 Nov 2021
Declaration in FORM BFile: FORM B,_compressed.pdf12 Nov 2021
Proforma of Allotment letterFile: draft agreement.pdf26 Oct 2021

How this compares with Nashik

10%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 60 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PALAI VILLAS - PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DEOLALI4,100+ in Nashik

Builder: N D DEVELOPERS

N D DEVELOPERS has 5 registrations on MahaRERA, including PALAI VILLAS and RATNA RESIDENCY. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if PALAI VILLAS - PHASE 2 is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PALAI VILLAS - PHASE 2?

The registered promoter entity is N D DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PALAI VILLAS - PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PALAI VILLAS - PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PALAI VILLAS - PHASE 2?

The professionals named in the filing: Architect: ONE ARCHITECTURAL CONSULTANT; Engineer: GAURAV NANDA; Chartered Accountant: JRSM & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PALAI VILLAS - PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PALAI VILLAS - PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PALAI VILLAS - PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.