ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / OZEN ESTEEM

Completed No litigation declared Plotted project

OZEN ESTEEM

By GOPAL RAMPRASAD SHARMA

RG-MH-03826 · RERA P50500031999 · Last updated on MahaRERA portal: 25 Nov 2021

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Sep 2023Possession promisedregistration recorded completed
14 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

OZEN ESTEEM is a Plotted project by GOPAL RAMPRASAD SHARMA in Nagpur, Maharashtra, registered with MahaRERA as P50500031999 on 3 Dec 2021. The registration is recorded completed; possession was promised by 30 Sep 2023. 0 of the 14 units on this registration are recorded sold or booked.

At a glance

Project

  • NameOZEN ESTEEM
  • TypePlotted
  • Location
    • SHANKARPUR
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500031999
  • ReraGenie IDRG-MH-03826

Builder

  • NameGOPAL RAMPRASAD SHARMA
  • Entity typeOthers
  • Named personsABHISHEK SATYNARAYAN SHARMA, PRANAV GOPAL SHARMA, SATYANARAYAN RAMPRASHAD SHARMA, GOPAL RAMPRASAD SHARMA

Key dates

this monthRegisteredDec 2021PromisedSep 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on3 Dec 2021
  • Promised completion30 Sep 2023
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed15 files

Current status

0%0 of 14 units booked

Figures as on 25 Nov 2021, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Nov 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 25 Nov 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7604.0
Proposed, not sanctioned7,604 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch204, MASHURWALA BAUG DHARAMPETH EXTN SHANKAR NAGAR ROAD NAGPUR 440010

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAMIR V SANDE
EngineerSAMIR SANDE
Chartered AccountantHARSHWARDHAN MAHESHWARI
PartnerRole in project
GOPAL RAMPRASAD SHARMA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CERSAI detailsFile: FORM B.pdf25 Nov 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf25 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed.pdf22 Nov 2021
Declaration in FORM BFile: FORM B.pdf9 Nov 2021
Layout approvalFile: Shankarpur-118 FINAL MAP_compressed.pdf23 Oct 2021
Building plan approval or NA orderFile: NMRDA Letter_compressed.pdf23 Oct 2021
PAN CardFile: 11.pdf23 Oct 2021
Copy of the legal title reportFile: TITLE REPORT_compressed (1).pdf23 Oct 2021
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf23 Oct 2021
Copy of Layout Approval (in case of layout)File: Shankarpur-118 FINAL MAP_compressed.pdf23 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: NMRDA Letter_compressed.pdf23 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: NMRDA Letter_compressed.pdf23 Oct 2021
Declaration about Commencement CertificateFile: FORM D.pdf23 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shankarpur 118 architect certificate.pdf23 Oct 2021
Proforma of Allotment letterFile: PROFOMA.pdf23 Oct 2021

How this compares with Nagpur

0%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OZEN ESTEEM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHANKARPUR2,800+ in Nagpur

2 kmOZEN ESTEEMCompleted 41Lapsed / revoked 19Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 112 registered projects within 2 km.

Builder: GOPAL RAMPRASAD SHARMA

GOPAL RAMPRASAD SHARMA has 1 registration on MahaRERA, including OZEN ESTEEM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if OZEN ESTEEM is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OZEN ESTEEM?

The registered promoter entity is GOPAL RAMPRASAD SHARMA, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OZEN ESTEEM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OZEN ESTEEM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OZEN ESTEEM?

The professionals named in the filing: Architect: SAMIR V SANDE; Engineer: SAMIR SANDE; Chartered Accountant: HARSHWARDHAN MAHESHWARI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OZEN ESTEEM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OZEN ESTEEM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OZEN ESTEEM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.