Home / Browse projects / Palghar, Maharashtra / OSTWAL EMPIRE M1 AND M2
OSTWAL EMPIRE M1 AND M2
RG-MH-02902 · RERA P99000020635 · Last updated on MahaRERA portal: 18 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OSTWAL EMPIRE M1 AND M2 is a Residential / Group Housing project by SAMTA ENTERPRISES in Palghar, Maharashtra, registered with MahaRERA as P99000020635 on 30 Apr 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 2 complaints are on record with the regulator.
At a glance
Project
- NameOSTWAL EMPIRE M1 AND M2
- TypeResidential / Group Housing
- Location
- OPP. GURUDWARA
- NAVAPUR ROAD
- BOISAR
- Saravali
- Palghar
- 401501
- Pincode401501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000020635
- ReraGenie IDRG-MH-02902
Builder
- NameSAMTA ENTERPRISES
- Entity typePartnership
- PartnerKULDEEP UMRAOSINGH OSTWAL
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on30 Apr 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings2 building records
- Documents filed35 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING M1 | NA | 8 | 0 | 0 | 0 | 0 |
| BUILDING M2 | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 18 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 50%.
BUILDING M170%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING M270%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 18 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed10
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| BUILDING M1 | 5 | 5 |
| BUILDING M2 | 5 | 5 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHRIKANT YEVLE |
| Engineer | Mr. Shrikant yevle |
| Engineer | BHAVESH BHALCHANDRA TODANKAR |
| Engineer | SUNIL PAWAR |
| Chartered Accountant | ABHISHEK SURANA |
| Partner | Role in project |
|---|---|
| SAMTA ENTERPRISES | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000397521 | SAMTA ENTERPRISES | MRS SHILPA PARAG PIMPLE | 22/09/2023 |
| CC006000000479951 | Shilpa Parag Pimple | SAMTA ENTERPRISES | 11/05/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Apr 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Mar 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Mar 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed35
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: Self Certification Form-3 _31032025-M1 M2 .pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold_31032025-M1 M2.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_March-25_M1-M2.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD_OSTWAL EMPIRE M1 M2_31122024.pdf | 14 Jan 2025 |
| Other - FinanceFile: SELF CERTIFICATION_OSTWAL EMPIRE M1 M2_31122024.pdf | 14 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_OSTWAL EMPIRE M1 M2_31122024.pdf | 14 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_OSTWAL EMPIRE M1 _M2.pdf | 20 Oct 2024 |
| Other - FinanceFile: Ostwal Empire M1 M2_Self Certification_30092024.pdf | 20 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate of Ostwal Empire M1 M2.pdf | 20 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Empire M1-M2 Quality Assurance Certificate.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Empire M1 M2 Sold Unsold Ostwal 30062024.pdf | 20 Jul 2024 |
| Other - FinanceFile: Self Declaration Ostwal Empire M1 and M2 as on 30 06 2024.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance_M1_M2_March-2024.pdf | 17 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold_ M1 M2.pdf | 17 Apr 2024 |
| Other - FinanceFile: Self Declaration_ M1 M2.pdf | 17 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 5 - M1 M2 - Discloser Sold Unsold Inventory.pdf | 13 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5 - Form - 2A - M-1 M-2.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: M1M2.pdf | 20 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM2A Ostwal Empire M1 M2.pdf | 19 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: UNSOLD INVENTORY Samta Ent.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: OSTWAL EMPIRE M1 M2.pdf | 14 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: M1 M2 - SOLD UNSOLD.pdf | 14 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM - 2A - OSTWAL M1 M2.pdf | 31 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: M1 M2.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: m1 m2.pdf | 3 Dec 2021 |
| Declaration in FORM BFile: SAMTA ENTERPRISES FORM B.pdf | 25 Apr 2019 |
| Copy of the legal title reportFile: Title Certificate .pdf | 6 Apr 2019 |
| Proforma of Allotment letterFile: RERA-M-1 M-2-DRAFT AGREEMENT.pdf | 6 Apr 2019 |
| Certificates of CA (Form 3)File: RERA Certificate.pdf | 5 Apr 2019 |
| Details of encumbrancesFile: encumbrances certificate.pdf | 1 Apr 2019 |
| Building plan approvalFile: COMMENCEMENT CERTIFICATE.pdf | 18 Mar 2019 |
| Layout approvalFile: LAYOUT PLAN.PDF | 18 Mar 2019 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.PDF | 18 Mar 2019 |
| Building Plan Approval (IOD)File: COMMENCEMENT CERTIFICATE.pdf | 18 Mar 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 18 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 35 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep OSTWAL EMPIRE M1 AND M2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BOISAR3,200+ in Palghar
Filed coordinates, straight-line distance. 334 registered projects within 2 km.
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: SAMTA ENTERPRISES
SAMTA ENTERPRISES has 1 registration on MahaRERA, including OSTWAL EMPIRE M1 AND M2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that OSTWAL EMPIRE M1 AND M2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if OSTWAL EMPIRE M1 AND M2 is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OSTWAL EMPIRE M1 AND M2?
The registered promoter entity is SAMTA ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OSTWAL EMPIRE M1 AND M2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against OSTWAL EMPIRE M1 AND M2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for OSTWAL EMPIRE M1 AND M2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OSTWAL EMPIRE M1 AND M2?
The professionals named in the filing: Architect: SHRIKANT YEVLE; Engineer: Mr. Shrikant yevle; Engineer: BHAVESH BHALCHANDRA TODANKAR; Engineer: SUNIL PAWAR; Chartered Accountant: ABHISHEK SURANA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OSTWAL EMPIRE M1 AND M2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.