Home / Browse projects / Pune, Maharashtra / Orion, Viva, Pirangut
Orion, Viva, Pirangut
By K Raheja Corp Real Estate Private Limited
RG-MH-17185 · RERA P52100028173 · Last updated on MahaRERA portal: 30 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 26 months past the filed date
- Litigation declared, 8 cases
Clear
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Orion, Viva, Pirangut is a Residential / Group Housing project by K Raheja Corp Real Estate Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100028173 on 10 Feb 2021. Possession was promised by 29 Aug 2024 and is now 26 months past that date.
At a glance
Project
- NameOrion, Viva, Pirangut
- TypeResidential / Group Housing
- Location
- Pune Paud Raod
- Near Aditya Nisarg
- Pirangut
- Mulshi
- Pune
- 412115
- Pincode412115
- RERA no.P52100028173
- ReraGenie IDRG-MH-17185
Builder
- NameK Raheja Corp Real Estate Private Limited
- Entity typeCompany
- CINU40300MH2007PTC287012
- GSTIN27AABCF1838M1ZF
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsRavi Chandru Raheja, Neel Chandru Raheja, Sunil Madhav Hingorani, Ramesh Ranganathan
- Company SecretoryJignasha Thakkar
- Other registrations20 more →
- Completed1 of 21
- No longer live8 lapsed, de-registered or revoked
- Past their filed date1
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Feb 2021
- Promised completion29 Aug 2024
- Revised completionNone
- Buildings26 building records
- Documents filed145 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Twin Villa No F1 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F2 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F3 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F4 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F5 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F6 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F7 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F8 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F9 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F10 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F11 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F12 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F13 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F14 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F15 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F16 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F17 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F18 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F19 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F20 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F21 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F22 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F23 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F24 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F25 | NA | 2 | 0 | 0 | 0 | 0 |
| Twin Villa No F26 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 26 buildings; the table lists the first 20.
Twin Villa No F1Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F2Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F3Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F4Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F5Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F6Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F7Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F8Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F9Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F10Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F11Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F12Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F13Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F14Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F15Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F16Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F17Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F18Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F19Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Twin Villa No F20Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed26
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Twin Villa No F1 | 1 | 1 |
| Twin Villa No F2 | 1 | 1 |
| Twin Villa No F3 | 1 | 1 |
| Twin Villa No F4 | 1 | 1 |
| Twin Villa No F5 | 1 | 1 |
| Twin Villa No F6 | 1 | 1 |
| Twin Villa No F7 | 1 | 1 |
| Twin Villa No F8 | 1 | 1 |
| Twin Villa No F9 | 1 | 1 |
| Twin Villa No F10 | 1 | 1 |
| Twin Villa No F11 | 1 | 1 |
| Twin Villa No F12 | 1 | 1 |
| Twin Villa No F13 | 1 | 1 |
| Twin Villa No F14 | 1 | 1 |
| Twin Villa No F15 | 1 | 1 |
| Twin Villa No F16 | 1 | 1 |
| Twin Villa No F17 | 1 | 1 |
| Twin Villa No F18 | 1 | 1 |
| Twin Villa No F19 | 1 | 1 |
| Twin Villa No F20 | 1 | 1 |
| Twin Villa No F21 | 1 | 1 |
| Twin Villa No F22 | 1 | 1 |
| Twin Villa No F23 | 1 | 1 |
| Twin Villa No F24 | 1 | 1 |
| Twin Villa No F25 | 1 | 1 |
| Twin Villa No F26 | 1 | 1 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kapadia Associates |
| Architect | Crystal Arch |
| Architect | Laxman Thite |
| Engineer | ASCENT STRUCTURAL ENGINEERS PVT LTD CONSULTING STRUCTURAL ENGINEERS |
| Engineer | Satish Vishnu Marathe |
| Chartered Accountant | S N Doshi and Associates |
| Chartered Accountant | G. M. Kapadia & Co. |
| Chartered Accountant | AKPJ & Associates |
| Partner | Role in project |
|---|---|
| K Raheja Corp Real Estate Private Limited | - |
Litigation declared8
| Case | Court | Status |
|---|---|---|
| 2085/2010 | Civil Judge Senior Devision | Ongoing |
| 224/2016 | Additional District and Session Judge Pune | Ongoing |
| 5964/2021 | High Court of Bombay | Closed |
| 5967/2021 | High Court of Bombay | Closed |
| 185/2020 | Sub Divisional officer Maval | Closed |
| 186/2020 | Sub Divisional officer Maval | Closed |
| 2085/2010 | Civil Judge Senior Division | Ongoing |
| 2085/2010 | Civil Judge Senior Division | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Jan 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Apr 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jan 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 4 Apr 2024
Documents filed145
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 145 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5 Orion.pdf | 30 Sep 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Orion.pdf | 27 Jun 2025 |
| Home Buyer /Allottee Grievance Redressal CellFile: Orion.pdf | 17 Apr 2025 |
| Layout approvalFile: Layout Viva compressed.pdf | 15 Apr 2025 |
| Copy of Layout Approval (in case of layout)File: Layout Viva compressed.pdf | 15 Apr 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Viva.pdf | 15 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Orion.pdf | 15 Apr 2025 |
| Other - FinanceFile: Declaration Orion No withdrawal.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Delcaration Orion.pdf | 14 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Delcaration Orion.pdf | 14 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Delcaration Orion.pdf | 14 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Orion.pdf | 16 Jan 2025 |
| Home Buyer /Allottee Grievance Redressal CellFile: Orion.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Declaration Orion.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration Orion.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Declaration Orion.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Orion.pdf | 18 Oct 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: Orion.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Orion.pdf | 10 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Orion.pdf | 18 Jul 2024 |
| Status of ConveyanceFile: Conveyance Declaration Orion.pdf | 18 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - Quality Assurance certificate Orion - March 24.pdf | 18 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - Quality Assurance certificate Orion - March 24.pdf | 18 Jun 2024 |
| Declaration in FORM BFile: Form B Orion.pdf | 30 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Orion KRCREPL.pdf | 30 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Orion KRCREPL.pdf | 30 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Orion.pdf | 30 May 2024 |
| Other - LegalFile: NCLT Order.pdf | 30 May 2024 |
| Other - LegalFile: Scheme of Demerger compresseddd.pdf | 30 May 2024 |
| Disclosure of sold/ booked inventoryFile: Orion_20240417162548.pdf | 18 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC B39 F01 TO 04 F11 TO 12 F19 TO 26.pdf | 4 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC - B39 - F09 -F10.pdf | 4 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Orion.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Orion.pdf | 19 Jan 2024 |
| Layout approvalFile: DP layout 01 compressed.pdf | 20 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: DP layout 01 compressed.pdf | 20 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 18082023.pdf | 20 Oct 2023 |
| Declaration about Commencement CertificateFile: CC Declaration Orion.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Orion.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Orion.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Orion 25 July 2023 as on July 2023.pdf | 20 Oct 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Orion.pdf | 20 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: ORION_.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Orion.pdf | 28 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Orion_20230712201807.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A Orion.pdf | 13 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A Orion.pdf | 31 May 2023 |
| Disclosure of sold/ booked inventoryFile: pact.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: ORION -INVENTORY.pdf | 23 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: orion.pdf | 20 Feb 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Orion_Condominium Formation Letter_09022023.pdf | 9 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Orion_Dec'22.pdf | 20 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Orion_Dec'22.pdf | 20 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Orion_Dec'22.pdf | 20 Jan 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Orion Condo Declaration.pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Orion.pdf | 19 Jan 2023 |
| Other - LegalFile: Orion Demerger Declaration.pdf | 19 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: ORION SOLD-BOOKED INVENTORY.pdf | 20 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: ORION_20221109134016.pdf | 17 Nov 2022 |
| Layout approvalFile: DP LAYOUT PLAN Compressed 060922.pdf | 19 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: DP LAYOUT PLAN Compressed 060922.pdf | 19 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: REVISED SANCTION CC DATED 060922 compressed.pdf | 19 Oct 2022 |
| Declaration about Commencement CertificateFile: CC Declaration Orion.pdf | 19 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 Orion.pdf | 19 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form-2_Pact_OrionB39.pdf | 18 Oct 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration of Allottees Orion.pdf | 18 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Orion- RERA SOLD-BOOKED INVENTORY.pdf | 17 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Orion_compressed.pdf | 30 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: ORION_001.pdf | 12 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Viva- Orion.pdf | 9 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: ORION SOLDBOOKED INVENT_001.pdf | 8 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Orion_001.pdf | 7 Jul 2022 |
| CERSAI detailsFile: CERSAI PACT.pdf | 7 Jul 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Allottes- Orion_001.pdf | 7 Jul 2022 |
| Other - LegalFile: Demeger-Orion_001.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: ORION SOLDBOOKED INVENT_001.pdf | 8 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory disclosure _B-39.pdf | 11 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert B-39 Dec 21.pdf | 2 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - PACT - B39 - Orion - Dec 21 - V2 - Signed Set.pdf | 2 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Orion Form 1.pdf | 7 Apr 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| PLOT NO.7, VIVA, PIRANGUTP52100002681 | Pirangut, Pune | Aug 2017 | Certificate Signed | Dec 2023 | Dec 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 20 other registrations, which the RERA portal never shows together
- All 145 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Orion, Viva, Pirangut on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Aditya Nisarg13,700+ in Pune
Avian Valley - Solaire
KAKADE ESTATE DEVELOPERS PVT. LTD.
Park Pebbles Phase I
M/s Rainbow Purple Construction LLP
Mahindra Rivenza Phase 2
Mahindra Lifespace Developers limited
Mahindra Rivenza Phase 1
Mahindra Lifespace Developers limited
FOREST TRAILS ATHASHRI B3
LAVIM DEVELOPERS PVT LTD
KOHINOOR WOODSHIRE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: K Raheja Corp Real Estate Private Limited
K Raheja Corp Real Estate Private Limited has 21 registrations on MahaRERA, including Estrella, Viva, Pirangut and Orion, Viva, Pirangut. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 16 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Orion, Viva, Pirangut shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Orion, Viva, Pirangut is delayed beyond 29 Aug 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Orion, Viva, Pirangut?
The registered promoter entity is K Raheja Corp Real Estate Private Limited, a company as per the filing. Its CIN U40300MH2007PTC287012 and GSTIN 27AABCF1838M1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Orion, Viva, Pirangut?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Orion, Viva, Pirangut?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Orion, Viva, Pirangut?
The professionals named in the filing: Architect: Kapadia Associates; Architect: Crystal Arch; Architect: Laxman Thite; Engineer: ASCENT STRUCTURAL ENGINEERS PVT LTD CONSULTING STRUCTURAL ENGINEERS; Engineer: Satish Vishnu Marathe; Chartered Accountant: S N Doshi and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Orion, Viva, Pirangut?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback