ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / ORCHIDE

Registration lapsed No litigation declared Residential / Group Housing project

ORCHIDE

By SHIV SHAMBHU ENTERPRISES

RG-MH-85491 · RERA P52000048654 · Last updated on MahaRERA portal: 12 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • 3 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 50%
3Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

ORCHIDE is a Residential / Group Housing project by SHIV SHAMBHU ENTERPRISES in Raigarh, Maharashtra, registered with MahaRERA as P52000048654 on 10 Jan 2023. Possession was promised by 30 Sep 2025 and is now 13 months past that date. 3 complaints are on record with the regulator.

At a glance

Project

  • NameORCHIDE
  • TypeResidential / Group Housing
  • Location
    • SECTOR 19
    • ULWE
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000048654
  • ReraGenie IDRG-MH-85491

Builder

  • NameSHIV SHAMBHU ENTERPRISES
  • Entity typeCompany
  • PartnerSandeep Singh

Key dates

13 months past promisethis monthRegisteredJan 2023PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Jan 2023
  • Promised completion30 Sep 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ORCHIDENA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

ORCHIDE: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered3
Open Space12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area200 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
AYUB ISHAQUE MOHAMMED KHAN (PROP RHYTHM CONT CO.)Mumbai CityMumbai City

Approvals and building plan

Permissible FSI2.2
Proposed, not sanctioned1 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 3A SECTOR 15 NERUL NAVI MUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHEETAL P NEMANE
EngineerSHRAVANI CONSULTANT
Chartered AccountantS T P AND ASSOCIATES
PartnerRole in project
SHIV SHAMBHU ENTERPRISES-

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12501302SHIV SHAMBHU ENTERPRISESShaikh Mohammed Ebrahim20/04/2025
CC12602013Faizan AbdulRehman PathanSHIV SHAMBHU ENTERPRISES05/04/2026
CC12602860Mohammed Ebrahim ShaikhSHIV SHAMBHU ENTERPRISES15/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf12 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate_Shiv Shambhu Enterprises (2).pdf12 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate_Shiv Shambhu Enterprises (2).pdf12 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf12 Jul 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf12 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf12 Jul 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked Inventory 230 .pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Orchide Form 1.pdf17 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 03.pdf17 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Orchide Form 2.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Orchide form 1_11zon.pdf7 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shiv Shambhu Enterprises.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Orchide form 2.pdf7 Nov 2024
Disclosure of sold/ booked inventoryFile: Orchide sold_unsold Inventory .pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Orchide.pdf2 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 2 _orchide.pdf2 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 _orchide.pdf2 Aug 2024
Disclosure of sold/ booked inventoryFile: Shiv Shambhu Enterprises _SOLD UNSOLD.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate_Shiv Shambhu Enterprises.pdf2 Aug 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate_Shiv Shambhu Revised-1.pdf17 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Orchide.pdf26 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 shiv Shambhu.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Shiv Shambhu.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate_Shiv shambhu Enterprises.pdf20 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf10 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf9 Nov 2023
Disclosure of sold/ booked inventoryFile: sold unsod.pdf9 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31-03-2023.pdf9 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-06-2023 (2).pdf9 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-09-2023.pdf9 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-03-2023 SHIVSHMBHU.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-06-2023 shiv shmabhu.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 3 30-09-2023.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31-03-2023.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-06-2023.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30-09-2023.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 18-07-2023.pdf21 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: shiv new cc.pdf31 Dec 2022
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of Interest in other real estate organization.pdf31 Dec 2022
Proforma of Agreement for saleFile: AFS.pdf19 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SHIVSHAMBHU BANK AAC DEC.pdf19 Dec 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf8 Dec 2022
Deviation Report with respect to Allotment letterFile: deviation-allotment.pdf8 Dec 2022
Deviation Report with respect to model copy of AgreementFile: deviation-draft sale.pdf8 Dec 2022
Other - LegalFile: DA 1 to 22 (1).pdf8 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 03 CA.pdf22 Nov 2022
Commencement Certificates / NA Order for plotted developmentFile: Development Aggriment.pdf15 Nov 2022
Declaration about Commencement CertificateFile: DECLARATION OF CC.pdf22 Oct 2022
Declaration in FORM BFile: FORM-B.pdf22 Oct 2022
Copy of the legal title reportFile: Title Report .pdf20 Oct 2022
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE.pdf8 Oct 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE.pdf8 Oct 2022
Building plan approvalFile: APPROVAL PLAN 01.pdf3 Oct 2022
Layout approvalFile: DEMARCATION.pdf3 Oct 2022
Copy of Layout Approval (in case of layout)File: DEMARCATION.pdf3 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: APPROVAL PLAN 01.pdf3 Oct 2022
CERSAI detailsFile: CERSAI_Asset based.pdf3 Oct 2022
PAN CardFile: 01 PAN CARD.pdf1 Oct 2022

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ORCHIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ULWE5,900+ in Raigarh

2 kmORCHIDECompleted 10Lapsed / revoked 9Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: SHIV SHAMBHU ENTERPRISES

SHIV SHAMBHU ENTERPRISES has 1 registration on MahaRERA, including ORCHIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that ORCHIDE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ORCHIDE is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ORCHIDE?

The registered promoter entity is SHIV SHAMBHU ENTERPRISES, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ORCHIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ORCHIDE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ORCHIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ORCHIDE?

The professionals named in the filing: Architect: SHEETAL P NEMANE; Engineer: SHRAVANI CONSULTANT; Chartered Accountant: S T P AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORCHIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORCHIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORCHIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.