ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Orchid Enclave

Completed No litigation declared Residential / Group Housing project

Orchid Enclave

By SIDDHIVINAYAK ASSOCIATES

RG-MH-22858 · RERA P52000024194 · Last updated on MahaRERA portal: 28 May 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedregistration recorded completed
6 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 85%
1Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

Orchid Enclave is a Residential / Group Housing project by SIDDHIVINAYAK ASSOCIATES in Raigarh, Maharashtra, registered with MahaRERA as P52000024194 on 24 Jan 2020. The registration is recorded completed; possession was promised by 30 Dec 2026. 1 complaint is on record with the regulator.

At a glance

Project

  • NameOrchid Enclave
  • TypeResidential / Group Housing
  • Location
    • Siddheshwar Mandir
    • Taloje Majkur
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000024194
  • ReraGenie IDRG-MH-22858

Builder

  • NameSIDDHIVINAYAK ASSOCIATES
  • Entity typePartnership
  • PartnersVAIBHAV PURUSHOTTAM AGRAWAL, NANDGOPAL MADHAVRAO KOLARAO
  • Other registrations8 more →
  • Completed6 of 9
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2020PromisedDec 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2020
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA130000
BUILDING NO 2, A and B WINGNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 28 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 85%.

BUILDING NO 129%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor11%
Slabs of Super Structure11%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 2, A and B WING43%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor11%
Slabs of Super Structure11%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
BUILDING NO 111
BUILDING NO 2, A and B WING11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,930 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7822.55
Proposed, not sanctioned5,323 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop number 1, Sector-1 Plot number 23, Satyam Paradise, 2,3,4, Kalamboli, Panvel, Navi Mumbai, Maha

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Neha Jain
EngineerNILESH KUMAR
Chartered AccountantRASHMIKESH PANIGRAHI
PartnerRole in project
SIDDHIVINAYAK ASSOCIATES-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12601486Chirag Jitendra TrivediSIDDHIVINAYAK ASSOCIATES17/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 31-03-2025 (3)_compressed.pdf28 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3.pdf28 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2.pdf28 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 12.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 9.pdf21 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 6.pdf21 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1.pdf14 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1.pdf14 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 E.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 D.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 9.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30 6 23_compressed.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 3 23 B.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 12 22 A.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 3_compressed.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 2.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 1.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 4.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _compressed (1).pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 compressed.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 21.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (2.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf3 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ORCHID ENCLAVE FROM 5.pdf3 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 4 21.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1 3 21.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1 21 2.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 21.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form NEW 1.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 3.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (2).pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FROM 2A 19.pdf13 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FROM2A 2022.pdf13 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FROM 2A 2023.pdf13 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FROM 2A 2024.pdf13 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - OE - FY 2022-23.pdf25 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ORCHID ENCLAVE 1.pdf23 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: OE FORM 5.pdf21 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: OE FORM 5 20-21.pdf21 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf21 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AR 2023-2024 NEW.pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf19 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE 01-04-2023-compressed.pdf17 Apr 2023
Details of encumbrancesFile: Details Of Encumbers.pdf19 Nov 2022
Details of encumbrancesFile: Mortgage Index 2.pdf2 Nov 2022
Building plan approvalFile: HPSCANNER2863 New 2022.pdf3 Jan 2022
Building plan approvalFile: HPSCANNER2864-2022 8th floor plan New.pdf3 Jan 2022
Building plan approvalFile: HPSCANNER2865_2022 New Foor Plan 1 st.pdf3 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2863 New 2022.pdf3 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2864-2022 8th floor plan New.pdf3 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2865_2022 New Foor Plan 1 st.pdf3 Jan 2022
Proforma of Allotment letterFile: Orchid enclave Draft 2022.pdf3 Jan 2022
Building plan approvalFile: HPSCANNER2866_compressed-compressed_compressed_compressed-compressed.pdf27 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: HPSCANNER2866_compressed-compressed_compressed_compressed-compressed.pdf27 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: orchid enclave 11floor cc_compressed (3)_compressed-compressed.pdf22 Dec 2021
Declaration about Commencement CertificateFile: orchid enclave 11floor cc_compressed (3)_compressed-compressed.pdf21 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: orchid engineer letter_compressed.pdf21 Dec 2021
OtherFile: RERA Disclosure_OrchidEnclave.pdf5 May 2021
Commencement Certificates / NA Order for plotted developmentFile: Orchid Enclave CC_compressed.pdf10 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Orchid enclave Form 3_compressed.pdf10 Jan 2020
Proforma of Allotment letterFile: AGREEMENT_OR.pdf10 Jan 2020
Declaration in FORM BFile: Form B Orchid Enclave_compressed.pdf30 Dec 2019
Layout approvalFile: Layout Plan.pdf29 Dec 2019
Building plan approvalFile: Bldg 1 plan.pdf29 Dec 2019
Building plan approvalFile: Bldg 2 plan.pdf29 Dec 2019
Building plan approvalFile: bldg 1plan2.pdf29 Dec 2019
Building plan approvalFile: Bldg 2plan2.pdf29 Dec 2019
PAN CardFile: Pan Siddhivinayak Associates.pdf29 Dec 2019
Copy of the legal title reportFile: title Search report.pdf29 Dec 2019
Details of encumbrancesFile: Orchid Enclave Details of encumbrances.pdf29 Dec 2019
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf29 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: Bldg 1 plan.pdf29 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: Bldg 2 plan.pdf29 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: bldg 1plan2.pdf29 Dec 2019

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Orchid Enclave on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Taloje Majkur5,900+ in Raigarh

2 kmOrchid EnclaveCompleted 18Lapsed / revoked 7Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: SIDDHIVINAYAK ASSOCIATES

SIDDHIVINAYAK ASSOCIATES has 9 registrations on MahaRERA, including Dnyanesh Residency and BLOSSOM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Orchid Enclave is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Orchid Enclave?

The registered promoter entity is SIDDHIVINAYAK ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Orchid Enclave?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Orchid Enclave?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Orchid Enclave?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Orchid Enclave?

The professionals named in the filing: Architect: Ar Neha Jain; Engineer: NILESH KUMAR; Chartered Accountant: RASHMIKESH PANIGRAHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Orchid Enclave?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Orchid Enclave. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Orchid Enclave to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.