ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / ORCHID BLISS

Completed No litigation declared Residential / Group Housing project

ORCHID BLISS

By SUNNY BUILDTECH PRIVATE LIMITED

RG-MH-09859 · RERA P52000002967 · Last updated on MahaRERA portal: 4 Jun 2022

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2020Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
1Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

ORCHID BLISS is a Residential / Group Housing project by SUNNY BUILDTECH PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000002967 on 4 Aug 2017. The registration is recorded completed; possession was promised by 30 Dec 2020. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameORCHID BLISS
  • TypeResidential / Group Housing
  • Location
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000002967
  • ReraGenie IDRG-MH-09859

Builder

  • NameSUNNY BUILDTECH PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorRAJU BHONURAM GUPTA

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Aug 2017
  • Promised completion30 Dec 2020
  • Revised completionRevised to 30 Dec 2020 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed59 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ORCHID BLISSNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

ORCHID BLISS: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered13
Open Space36

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6794.73
Proposed, not sanctioned6,795 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHAVIR CENTRE PREMISES, PLOT NO 77, SECTOR 17, VASHI, NAVI MUMBAI - 4000703

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDimensions Architects Pvt Ltd
PartnerRole in project
SUNNY BUILDTECH PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000005287Dec 2019 → Jun 2020

Reason as filed by the promoterWe have our Occupancy Certificate date mentioned in RERA on 31/12/2019. Our work on site is 100% completed and for occupancy certificate we have to obtaine several NOC's from various authorities out of which some NOC's received and balance yet receive

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000199027Sonika GoyalSunny Buildtech Pvt. Ltd27/11/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Dec 2021

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 April 19 to june-19.pdf4 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 July 19 to Sep 19.pdf4 Jun 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Oct 19 to Dec 19.pdf4 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 April 19 to June 19.pdf4 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 July 19 to Sep 19.pdf4 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Oct19 to Dec 19.pdf4 Jun 2022
Certificates of CA (Form 3)File: Form-3 April19 to June-19.pdf4 Jun 2022
Certificates of CA (Form 3)File: Form 3 July 19 to Sep 19.pdf4 Jun 2022
Certificates of CA (Form 3)File: Form 3 Oct 19 to Dec 19.pdf4 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: BP-10401OCC.pdf27 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: RERA Form 4.pdf27 Dec 2021
Certificates of CA (Form 3)File: 1 april to 30june 18.pdf5 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (March-2018).pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (June-2018).pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (Sep-2018).pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (Dec-2018).pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (M-19).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (Sep-17).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (Dec-2017).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (March-2018).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (Jun-2018).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (Sep-2018).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (Dec-2018).pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (March-2019).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (Sep-2017).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (Dec-2017).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (March-2018).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (June-2018).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (Sept-2018).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (Dec-2018).pdf22 Aug 2019
Certificates of CA (Form 3)File: CA Certificate (March-2019).pdf22 Aug 2019
Proforma of Allotment letterFile: Engineer Certificate (March-2019).pdf22 Aug 2019
Certificates of CA (Form 5)File: Annual Report.pdf31 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sep2017.pdf6 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate Dec2017.pdf6 Jul 2018
Building plan approvalFile: CC Copy.pdf29 Jul 2017
Layout approvalFile: Layout 1.pdf29 Jul 2017
Layout approvalFile: Layout 2.pdf29 Jul 2017
Layout approvalFile: Layout 3.pdf29 Jul 2017
Layout approvalFile: Layout 4.pdf29 Jul 2017
Layout approvalFile: Layout 5.pdf29 Jul 2017
Layout approvalFile: Layout 6.pdf29 Jul 2017
PAN CardFile: Pan Card.pdf29 Jul 2017
Copy of the legal title reportFile: Legal Title Report.pdf29 Jul 2017
Details of encumbrancesFile: Incombrance Certificate.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 1.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 2.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 3.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 4.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 5.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 6.pdf29 Jul 2017
Building Plan Approval (IOD)File: CC Copy.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf29 Jul 2017
Declaration in FORM BFile: Form B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf29 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf29 Jul 2017
Proforma of Allotment letterFile: Allotment Letter.pdf29 Jul 2017
Proforma of Allotment letterFile: DRAFT AGREEMENT AS PER RERA.pdf29 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 12 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ORCHID BLISS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ulawe5,900+ in Raigarh

2 kmORCHID BLISSCompleted 117Lapsed / revoked 34Other 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 257 registered projects within 2 km.

Builder: SUNNY BUILDTECH PRIVATE LIMITED

SUNNY BUILDTECH PRIVATE LIMITED has 1 registration on MahaRERA, including ORCHID BLISS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if ORCHID BLISS is delayed beyond 30 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ORCHID BLISS?

The registered promoter entity is SUNNY BUILDTECH PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ORCHID BLISS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ORCHID BLISS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ORCHID BLISS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ORCHID BLISS?

The professionals named in the filing: Architect: Dimensions Architects Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORCHID BLISS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORCHID BLISS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORCHID BLISS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.