OMKAR COMPLEX
RG-MH-16932 · RERA P52100027276 · Last updated on MahaRERA portal: 1 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 48 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OMKAR COMPLEX is a Others project by RAHUL BABAN KAMBLE in Pune, Maharashtra, registered with MahaRERA as P52100027276 on 1 Dec 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 48 months from the original filing. 13 of the 15 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameOMKAR COMPLEX
- TypeOthers
- Location
- PAUD ROAD
- KASARAMBOLI
- Kasar Amboli
- Mulshi
- Pune
- 412115
- Pincode412115
- RERA no.P52100027276
- ReraGenie IDRG-MH-16932
Builder
- NameRAHUL BABAN KAMBLE
- Entity typeIndividual
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Dec 2020
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2022)
- Buildings1 building record
- Documents filed167 files
Current status
Figures as on 1 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| OMKAR COMPLEX | NA | 7 | 4 | 10 | 5 | 15 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
OMKAR COMPLEX: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 1 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 95% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed21
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| OMKAR COMPLEX | NA | Rs 1.50 cr | Rs 1.45 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SACHIN DHAVALIKAR Dhavalikar |
| Engineer | ARVIND DHANAWADE Dhanawade |
| Chartered Accountant | DINESH KUDALE Kudale |
| Partner | Role in project |
|---|---|
| RAHUL BABAN KAMBLE | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to COVID 19 we have faced shortage of labor. And therefore project is being delayed for one year only.
Reason as filed by the promoterDue to financial and PMRDA rule
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Nov 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Nov 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Nov 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed167
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 167 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Arch March 24.pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Omkar Complex Arch Certificate Dec 25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 1File: Omkar Complex Arch Certificate Mar 26.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Omkar Complex Engg Sept 25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Omkar Complex Engg Dec25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 2File: Omkar Complex Engg March 26.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: CA March 24.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Omkar Complex CA Certificate Dec 25.pdf | 1 Jun 2026 |
| Withdrawal Update Form 3File: Omkar Complex CA Certificate March 26.pdf | 1 Jun 2026 |
| Form 1File: Arch Dec23.pdf | 15 Sep 2025 |
| Form 2File: Engg Dec 23.pdf | 15 Sep 2025 |
| Form 3File: CA Dec 23.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Dec 23.pdf | 15 Sep 2025 |
| Form 1File: Arch Sept 23.pdf | 15 Sep 2025 |
| Form 2File: Engineer Sep 23.pdf | 15 Sep 2025 |
| Form 3File: CA Sept 23.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Sep 23.pdf | 15 Sep 2025 |
| Form 1File: Arch june23.pdf | 15 Sep 2025 |
| Form 2File: Engg June 22.pdf | 15 Sep 2025 |
| Form 3File: CA June 23.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Jun 23.pdf | 15 Sep 2025 |
| Form 1File: Arch march 23.pdf | 15 Sep 2025 |
| Form 2File: Engg March 23.pdf | 15 Sep 2025 |
| Form 3File: CA March 23.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Mar 23.pdf | 15 Sep 2025 |
| OthersFile: Form 5 2022-23.pdf | 15 Sep 2025 |
| Form 1File: Arch Jun 25.pdf | 15 Sep 2025 |
| Form 2File: Eng Jun 25.pdf | 15 Sep 2025 |
| Form 3File: CA Jun 25.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold Jun 25.pdf | 15 Sep 2025 |
| Form 1File: Arch Dec 22.pdf | 15 Sep 2025 |
| Form 2File: Engg Dec 22.pdf | 15 Sep 2025 |
| Form 3File: CA Dec 22.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Dec 22.pdf | 15 Sep 2025 |
| Form 1File: Arch Spet22.pdf | 15 Sep 2025 |
| Form 2File: Engg Sept 22.pdf | 15 Sep 2025 |
| Form 3File: CA Sept 22.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Sep 22.pdf | 15 Sep 2025 |
| Form 1File: Arch June 22.pdf | 15 Sep 2025 |
| Form 2File: Engg June 22.pdf | 15 Sep 2025 |
| Form 3File: CA June 22.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Jun 22.pdf | 15 Sep 2025 |
| Form 1File: Arch March22.pdf | 15 Sep 2025 |
| Form 2File: Engg March 22.pdf | 15 Sep 2025 |
| Form 3File: CA March 22.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Mar 22.pdf | 15 Sep 2025 |
| OthersFile: OC QA 21 to 22.pdf | 15 Sep 2025 |
| Form 1File: Arch Dec21.pdf | 15 Sep 2025 |
| Form 2File: Engg Dec 21.pdf | 15 Sep 2025 |
| Form 3File: CA Dec 21.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Dec 21.pdf | 15 Sep 2025 |
| Form 1File: Arch Sept 21.pdf | 15 Sep 2025 |
| Form 2File: Engineer Sep 21.pdf | 15 Sep 2025 |
| Form 3File: CA Sept 21.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Engineer Sep 21.pdf | 15 Sep 2025 |
| Form 1File: Arch june 21.pdf | 15 Sep 2025 |
| Form 2File: Engg June21.pdf | 15 Sep 2025 |
| Form 3File: CA June 21.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Jun 21.pdf | 15 Sep 2025 |
| Form 1File: Arch March 21.pdf | 15 Sep 2025 |
| Form 2File: Engg March 21.pdf | 15 Sep 2025 |
| Form 3File: CA March 21.pdf | 15 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Mar 21.pdf | 15 Sep 2025 |
| OthersFile: OC QA 20 to 21.pdf | 15 Sep 2025 |
| Form 1File: Arch Jun 24.pdf | 12 Sep 2025 |
| Form 2File: Eng Jun 24.pdf | 12 Sep 2025 |
| Form 3File: CA Jun 24.pdf | 12 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold Jun 24.pdf | 12 Sep 2025 |
| Form 1File: Arch Sep 24.pdf | 12 Sep 2025 |
| Form 2File: Eng Sep 24.pdf | 12 Sep 2025 |
| Form 3File: CA Sep 24.pdf | 12 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold Sep 24.pdf | 12 Sep 2025 |
| Form 1File: Arch Dec 24.pdf | 12 Sep 2025 |
| Form 2File: Eng Dec 24.pdf | 12 Sep 2025 |
| Form 3File: CA Dec 24.pdf | 12 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold Dec 24.pdf | 12 Sep 2025 |
| Form 1File: Arch Mar 25.pdf | 12 Sep 2025 |
| Form 2File: Eng Mar 25.pdf | 12 Sep 2025 |
| Form 3File: CA Mar 25.pdf | 12 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold Mar 25.pdf | 12 Sep 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 167 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep OMKAR COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KASARAMBOLI13,700+ in Pune
Avian Valley - Solaire
KAKADE ESTATE DEVELOPERS PVT. LTD.
Park Pebbles Phase I
M/s Rainbow Purple Construction LLP
Mahindra Rivenza Phase 2
Mahindra Lifespace Developers limited
Mahindra Rivenza Phase 1
Mahindra Lifespace Developers limited
FOREST TRAILS ATHASHRI B3
LAVIM DEVELOPERS PVT LTD
KOHINOOR WOODSHIRE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: RAHUL BABAN KAMBLE
RAHUL BABAN KAMBLE has 2 registrations on MahaRERA, including OMKAR COMPLEX and OMKAR HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that OMKAR COMPLEX shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if OMKAR COMPLEX is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OMKAR COMPLEX?
The registered promoter entity is RAHUL BABAN KAMBLE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OMKAR COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OMKAR COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OMKAR COMPLEX?
The professionals named in the filing: Architect: SACHIN DHAVALIKAR Dhavalikar; Engineer: ARVIND DHANAWADE Dhanawade; Chartered Accountant: DINESH KUDALE Kudale. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OMKAR COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback