ReraGenieLog inGet a buyer report

Home / Browse projects / Yavatmal, Maharashtra / Om Varco Regency Phase-1

Registration lapsed No litigation declared Residential / Group Housing project

Om Varco Regency Phase-1

By Om Varco Developers

RG-MH-00638 · RERA P51000003720 · Last updated on MahaRERA portal: 8 Mar 2018

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 79 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Yavatmal registration emailed to you, free during the pilot beta.
Mar 2020Possession promised79 months past this date
73 of 176Construction stages doneacross 16 buildings; furthest along: Installation of Lifts, 95%
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Om Varco Regency Phase-1 is a Residential / Group Housing project by Om Varco Developers in Yavatmal, Maharashtra, registered with MahaRERA as P51000003720 on 6 Aug 2017. Possession was promised by 30 Mar 2020 and is now 79 months past that date.

At a glance

Project

  • NameOm Varco Regency Phase-1
  • TypeResidential / Group Housing
  • Location
    • Yavatmal (M Cl)
    • Yavatmal
    • 445001
  • Pincode445001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51000003720
  • ReraGenie IDRG-MH-00638

Builder

  • NameOm Varco Developers
  • Entity typePartnership
  • PartnersShailesh Prakashrao Daulatkar, Ashwinikumar Amarlalji Maniyar, Shyam Gopaldas Mundhada, Vikramsingh Arjunsingh Dalwala, Rajesh Ramswaroopji Gupta, Rajesh Ramswaroopji Gupta, Anand Rameshchandra Mor, Sanjay Rameshchandra Bajaj
  • Other registrations4 more →
  • Completed4 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

79 months past promisethis monthRegisteredAug 2017PromisedMar 2020

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion30 Mar 2020
  • Revised completionNone
  • Buildings16 building records
  • Documents filed73 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bungalow No 6ANA20000
Bungalow No 6BNA20000
Bungalow No 7NA20000
Bungalow No 8ANA20000
Bungalow No 8BNA20000
Bungalow No 8CNA20000
Bungalow No 9ANA20000
Bungalow No 9BNA20000
Bungalow No 9CNA20000
Bungalow No 10ANA20000
Bungalow No 10BNA20000
Bungalow No 10CNA20000
Bungalow No 11ANA20000
Bungalow No 11BNA20000
Bungalow No 11CNA20000
Magadha AppartmentNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building16

As on 8 Mar 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

73 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is Installation of Lifts, at 95%.

Bungalow No 6A56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 6B64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bungalow No 8A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bungalow No 8B45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 8C82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bungalow No 9A73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 9B73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 9C73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 10A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 10B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 10C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 11A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 11B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bungalow No 11C0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Magadha Appartment88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities17

As on 8 Mar 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes60%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes40%
Energy managemcntYes50%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes25%
Open ParkingNoNot applicable
CCTV Security SystemYes10%
Compound WallYes80%

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered1
Open Space5

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,997 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10796.89
Proposed, not sanctioned6,913 sq m
Buildings approved16
Buildings sanctioned16

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDatta Chowk, Yavatmal

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnand Jain
EngineerAbay Patil
PartnerRole in project
Om Varco Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: CC1.pdf8 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: CC2.pdf8 Mar 2018
Layout approvalFile: sheet_no_1_.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: sheet_no_1_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_1_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_2_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_3_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_4_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_5_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_6_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_7_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_8_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p_9_.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: p0009.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0001.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0002.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0003.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0004.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0005.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0006.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0007.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0008.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: p0010.pdf30 Jul 2017
Certificates of CA (Form 3)File: gandhi sir 1.pdf30 Jul 2017
Certificates of CA (Form 3)File: gandhi sir 2.pdf30 Jul 2017
Certificates of CA (Form 3)File: gandhi sir 3.pdf30 Jul 2017
Certificates of CA (Form 3)File: gandhi sir 4.pdf30 Jul 2017
Details of encumbrancesFile: EncumbaranceCertificate.pdf29 Jul 2017
Declaration in FORM BFile: Affidavitp1pdf.pdf29 Jul 2017
Declaration in FORM BFile: Affidavitp2.pdf29 Jul 2017
Building plan approvalFile: sheet_no_1_.pdf28 Jul 2017
Building plan approvalFile: sheet_no_2.pdf28 Jul 2017
Building plan approvalFile: SheetNo3.pdf28 Jul 2017
Building plan approvalFile: sheet_no_4.pdf28 Jul 2017
Building plan approvalFile: sheet_no_5.pdf28 Jul 2017
Building plan approvalFile: sheet_no_6.pdf28 Jul 2017
Building plan approvalFile: sheet_no_7.pdf28 Jul 2017
Building plan approvalFile: sheet_no_8.pdf28 Jul 2017
Building plan approvalFile: sheet_no_10.pdf28 Jul 2017
PAN CardFile: Om_VARCO_PAN_CARD_1.pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100001.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100002.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100003.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100004.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100005.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100006.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100007.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100008.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100009.Pdf28 Jul 2017
Copy of the legal title reportFile: P1 TO P100010.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200001.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200002.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200003.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200004.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200005.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200006.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200007.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200008.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200009.Pdf28 Jul 2017
Copy of the legal title reportFile: P11 TO P200010.Pdf28 Jul 2017
Copy of the legal title reportFile: P21 TO P220001.Pdf28 Jul 2017
Copy of the legal title reportFile: P21 TO P220002.Pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_1_.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_2.pdf28 Jul 2017
Building Plan Approval (IOD)File: SheetNo3.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_4.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_5.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_6.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_7.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_8.pdf28 Jul 2017
Building Plan Approval (IOD)File: sheet_no_10.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment letter.pdf28 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
Dream CityYavatmalCompletedMay 2015May 2015

How this compares with Yavatmal

11%of Yavatmal projects moved their completion datethis one has not
32%of Yavatmal registrations have lapsed or been cancelledthis one is among them

Computed across the 67 Yavatmal projects on ReraGenie, from their own filings.

Keep Om Varco Regency Phase-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Yavatmal (M Cl)67 in Yavatmal

Builder: Om Varco Developers

Om Varco Developers has 5 registrations on MahaRERA, including Om Varco Regency Phase-1 and Om Varco City 57. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Yavatmal district page.

Frequently asked questions

What does it mean that Om Varco Regency Phase-1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Om Varco Regency Phase-1 is delayed beyond 30 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Om Varco Regency Phase-1?

The registered promoter entity is Om Varco Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Om Varco Regency Phase-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Om Varco Regency Phase-1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Om Varco Regency Phase-1?

The professionals named in the filing: Architect: Anand Jain; Engineer: Abay Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Om Varco Regency Phase-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Om Varco Regency Phase-1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Om Varco Regency Phase-1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.