OM SAI COMPLEX
RG-MH-26884 · RERA P99000010987 · Last updated on MahaRERA portal: 31 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 60 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 3 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OM SAI COMPLEX is a Residential / Group Housing project by VARSHA PRAKASH NAIK in Palghar, Maharashtra, registered with MahaRERA as P99000010987 on 31 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 55 of the 132 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameOM SAI COMPLEX
- TypeResidential / Group Housing
- Location
- Survey No 109/1
- 2
- 3
- Betegaon
- Palghar
- 401501
- Pincode401501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000010987
- ReraGenie IDRG-MH-26884
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
- Buildings2 building records
- Documents filed101 files
Current status
Figures as on 31 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING NO 1 | NA | 3 | 3 | 0 | 92 | 92 |
| BUILDING NO 3 | NA | 5 | 4 | 40 | 0 | 40 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 85%.
BUILDING NO 151%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING NO 391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 85% |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 40% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 40% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING NO 1 | 0 | 12 | 12 |
| BUILDING NO 3 | 1 | 7 | 8 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SUBHASH RATILAL PAREKH | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| BUILDING NO 1 | NA | Rs 7.11 cr | Rs 5.53 cr |
| - | NA | Rs 3.30 cr | Rs 1.33 cr |
| BUILDING NO 3 | NA | Rs 2.78 cr | Rs 2.78 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YASH MILIND NANSI |
| Engineer | GANESH RAGHUNATH AWHAD |
| Engineer | Vyas Mishra |
| Chartered Accountant | D N FARGOES & CO |
| Chartered Accountant | Sankhala & Co |
| Chartered Accountant | DOLLY MILAN ASHAR |
| Chartered Accountant | MISHRA MAYEKAR AND CO. |
| Partner | Role in project |
|---|---|
| VARSHA PRAKASH NAIK | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of OM SAI COMPLEX’ - As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30/12/2023 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing prices of th
Reason as filed by the promoterThe CC consist of 3 Buildings, Building No 1 consist of G+2 of which we have completed fully G+1, Building no 2 not yet constructed, Building No 3 G+4 fully constructed. Due to major impact of Covid-19 in the rural area, we were unable to complete the project in time. Hence request you to please grant us the extension of 1 year to complete the same.
Reason as filed by the promoterThe COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materials to the project site. In particular, the delivery timeli
Reason as filed by the promoterAS THE SAID PROJECT IS IN BETEGOAN AND THERE IS SHORTAGE OF LABOUR AS OUTSIDE LABOUR WAS NOT ALLOWED BY THE VILLAGERS.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001849 | Ashwin Parekh | Varsha Prakash Naik-sugandhi builders | 12/11/2017 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed101
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Architect Certificate- Om Sai Complex March 260001.pdf | 31 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_June 2026.pdf | 31 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate -Om Sai Complex March 26001.pdf | 31 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_June 2026.pdf | 31 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate - Om Sai Complex - March 260001.pdf | 31 Jul 2026 |
| Withdrawal Update Form 3File: Neww Form 3_merged.pdf | 31 Jul 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A MARCH 2026.pdf | 13 Jul 2026 |
| Form 2A (FY 2022-2023)File: Form 2A March 2023.pdf | 13 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A march 2024.pdf | 13 Jul 2026 |
| Form 2A (FY 2024-2025)File: FORM 2A MARCH 2025.pdf | 13 Jul 2026 |
| Form 1File: Form 1 - June 24.pdf | 11 Jul 2026 |
| Form 2File: Form 2 June 24.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - June 24_compressed.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold June 24.pdf | 11 Jul 2026 |
| Form 1File: Form 1 - Sept 24.pdf | 11 Jul 2026 |
| Form 2File: Form 2 Sept 24.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - Sept 24_compressed.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 24.pdf | 11 Jul 2026 |
| Form 1File: Form 1 - Architect Certificate- Om Sai Complex Dec 24.pdf | 11 Jul 2026 |
| Form 2File: Form 2 - Engineer Certificate -Om Sai Complex Dec 24.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - CA Certificate - Om Sai Complex - Dec 24.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 24.pdf | 11 Jul 2026 |
| Form 1File: Form 1 - Architect Certificate- Om Sai Complex March 250001.pdf | 11 Jul 2026 |
| Form 2File: Form 2 - Engineer Certificate -Om Sai Complex March 250001.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - CA Certificate - Om Sai Complex - March 25_0001.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory - Om Sai March 25001.pdf | 11 Jul 2026 |
| Form 1File: Form 1 - June 24.pdf | 11 Jul 2026 |
| Form 2File: Form 2 June 24.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - June 24_compressed.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold June 24.pdf | 11 Jul 2026 |
| Form 1File: Form 1 - Sept 24.pdf | 11 Jul 2026 |
| Form 2File: Form 2 Sept 24.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - Sept 24_compressed.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 24.pdf | 11 Jul 2026 |
| Form 1File: Form 1 - Architect Certificate- Om Sai Complex Dec 24.pdf | 11 Jul 2026 |
| Form 2File: Form 2 - Engineer Certificate -Om Sai Complex Dec 24.pdf | 11 Jul 2026 |
| Form 3File: Form 3 - CA Certificate - Om Sai Complex - Dec 24.pdf | 11 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 24.pdf | 11 Jul 2026 |
| Form 5 (FY 2024-2025)File: FORM 5.pdf | 11 Jul 2026 |
| Form 5 (FY 2023-2024)File: Form 5 Audit Report (FY 2023-24) - OM SAI COMPLEX.pdf | 9 Jun 2026 |
| Form 5 (FY 2022-2023)File: Form 5 FY 22-23 - Om Sai.pdf | 9 Jun 2026 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Om Sai .pdf | 19 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 Dec 23.pdf | 19 Mar 2024 |
| Declaration in FORM BFile: FORM B.pdf | 18 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 23.pdf | 18 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 23.pdf | 18 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf | 18 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Dec 23.pdf | 18 Mar 2024 |
| Proforma of Agreement for saleFile: Draft Sale Agreement-Om Sai Complex.pdf | 15 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2018.pdf | 7 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019.pdf | 7 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020.pdf | 7 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf | 7 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2022.pdf | 7 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf | 3 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2018.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2019.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2020.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2022.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2023.pdf | 3 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2018.pdf | 3 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2019.pdf | 3 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2020.pdf | 3 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2021.pdf | 3 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022.pdf | 3 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 2018_compressed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 2019_compressed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 2020_compressed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 2022_compressed.pdf | 3 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format Decleration about separate bank accounts.pdf | 3 Jul 2023 |
| Deviation Report with respect to Allotment letterFile: No Deviation with respect to allotment letter.pdf | 3 Jul 2023 |
| Deviation Report with respect to model copy of AgreementFile: No Deviation with respect to model copy of Agreement.pdf | 3 Jul 2023 |
| Declaration about Commencement CertificateFile: Declearation about commencement certificate.pdf | 29 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A 2020.pdf | 29 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021.pdf | 29 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021.pdf | 29 Jun 2023 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHIV SUGANDH | OPP DISHA HOTEL KHARODI NAKA VIRAR WEST | 41 | Completed | Oct 2013 | Feb 2013 |
| CHHAYA SUGANDH | OPP DISHA HOTEL KHARODI NAKA VIRAR WEST | 72 | Completed | Sep 2013 | Feb 2013 |
| SMRUTI SUGANDH | OPP DISHA HOTEL KHARODI NAKA VIRAR WEST | 60 | Completed | Aug 2013 | Feb 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 101 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep OM SAI COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Betegaon3,200+ in Palghar
Filed coordinates, straight-line distance. 59 registered projects within 2 km.
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: VARSHA PRAKASH NAIK
VARSHA PRAKASH NAIK has 2 registrations on MahaRERA, including SUGANDHI VIHAR and OM SAI COMPLEX. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if OM SAI COMPLEX is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OM SAI COMPLEX?
The registered promoter entity is VARSHA PRAKASH NAIK, an individual as per the filing. Its GSTIN 27ADEPN2499R1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OM SAI COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against OM SAI COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for OM SAI COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OM SAI COMPLEX?
The professionals named in the filing: Architect: YASH MILIND NANSI; Engineer: GANESH RAGHUNATH AWHAD; Engineer: Vyas Mishra; Chartered Accountant: D N FARGOES & CO; Chartered Accountant: Sankhala & Co; Chartered Accountant: DOLLY MILAN ASHAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OM SAI COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback