Home / Browse projects / Palghar, Maharashtra / OM SAI COMPLEX

Registered No litigation declared Residential / Group Housing project

OM SAI COMPLEX

By VARSHA PRAKASH NAIK

RG-MH-26884 · RERA P99000010987 · Last updated on MahaRERA portal: 31 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 60 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 60 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 85%
77 of 132Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

OM SAI COMPLEX is a Residential / Group Housing project by VARSHA PRAKASH NAIK in Palghar, Maharashtra, registered with MahaRERA as P99000010987 on 31 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 60 months from the original filing. 55 of the 132 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameOM SAI COMPLEX
  • TypeResidential / Group Housing
  • Location
    • Survey No 109/1
    • 2
    • 3
    • Betegaon
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000010987
  • ReraGenie IDRG-MH-26884

Builder

  • NameVARSHA PRAKASH NAIK
  • Entity typeIndividual
  • GSTIN27ADEPN2499R1ZM
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed101 files

Current status

42%55 of 132 units booked
73.1%Work done, per cost certificate

Figures as on 31 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA3309292
BUILDING NO 3NA5440040

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 85%.

BUILDING NO 151%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes85%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes50%
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered1
Open Space19
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 101212
BUILDING NO 3178

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,235 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Jul 2026
LandownerVillageDistrict
SUBHASH RATILAL PAREKHMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityTOWN PLANNER PALGHAR
Permissible FSI13525.59
Proposed, not sanctioned3,874 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBANGLI SANDOR POST VASAI DIST PALGHAR PIN 401201
Estimated costRs 13.19 cr
Cost incurredRs 9.65 cr
Work done73.13%
BuildingWingEstimatedIncurred
BUILDING NO 1NARs 7.11 crRs 5.53 cr
-NARs 3.30 crRs 1.33 cr
BUILDING NO 3NARs 2.78 crRs 2.78 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYASH MILIND NANSI
EngineerGANESH RAGHUNATH AWHAD
EngineerVyas Mishra
Chartered AccountantD N FARGOES & CO
Chartered AccountantSankhala & Co
Chartered AccountantDOLLY MILAN ASHAR
Chartered AccountantMISHRA MAYEKAR AND CO.
PartnerRole in project
VARSHA PRAKASH NAIK-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019343Dec 2022 → Dec 2024

Reason as filed by the promoterExplanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of OM SAI COMPLEX’ - As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30/12/2023 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing prices of th

EXT99000016621Dec 2022 → Dec 2023

Reason as filed by the promoterThe CC consist of 3 Buildings, Building No 1 consist of G+2 of which we have completed fully G+1, Building no 2 not yet constructed, Building No 3 G+4 fully constructed. Due to major impact of Covid-19 in the rural area, we were unable to complete the project in time. Hence request you to please grant us the extension of 1 year to complete the same.

EXT99000027379Dec 2022 → Dec 2025

Reason as filed by the promoterThe COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materials to the project site. In particular, the delivery timeli

EA13072621740Dec 2022 → Dec 2027

Reason as filed by the promoterAS THE SAID PROJECT IS IN BETEGOAN AND THERE IS SHORTAGE OF LABOUR AS OUTSIDE LABOUR WAS NOT ALLOWED BY THE VILLAGERS.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000001849Ashwin ParekhVarsha Prakash Naik-sugandhi builders12/11/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Architect Certificate- Om Sai Complex March 260001.pdf31 Jul 2026
Withdrawal Update Form 1File: Form 1_June 2026.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate -Om Sai Complex March 26001.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2_June 2026.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3 - CA Certificate - Om Sai Complex - March 260001.pdf31 Jul 2026
Withdrawal Update Form 3File: Neww Form 3_merged.pdf31 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A MARCH 2026.pdf13 Jul 2026
Form 2A (FY 2022-2023)File: Form 2A March 2023.pdf13 Jul 2026
Form 2A (FY 2023-2024)File: Form 2A march 2024.pdf13 Jul 2026
Form 2A (FY 2024-2025)File: FORM 2A MARCH 2025.pdf13 Jul 2026
Form 1File: Form 1 - June 24.pdf11 Jul 2026
Form 2File: Form 2 June 24.pdf11 Jul 2026
Form 3File: Form 3 - June 24_compressed.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold June 24.pdf11 Jul 2026
Form 1File: Form 1 - Sept 24.pdf11 Jul 2026
Form 2File: Form 2 Sept 24.pdf11 Jul 2026
Form 3File: Form 3 - Sept 24_compressed.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 24.pdf11 Jul 2026
Form 1File: Form 1 - Architect Certificate- Om Sai Complex Dec 24.pdf11 Jul 2026
Form 2File: Form 2 - Engineer Certificate -Om Sai Complex Dec 24.pdf11 Jul 2026
Form 3File: Form 3 - CA Certificate - Om Sai Complex - Dec 24.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 24.pdf11 Jul 2026
Form 1File: Form 1 - Architect Certificate- Om Sai Complex March 250001.pdf11 Jul 2026
Form 2File: Form 2 - Engineer Certificate -Om Sai Complex March 250001.pdf11 Jul 2026
Form 3File: Form 3 - CA Certificate - Om Sai Complex - March 25_0001.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory - Om Sai March 25001.pdf11 Jul 2026
Form 1File: Form 1 - June 24.pdf11 Jul 2026
Form 2File: Form 2 June 24.pdf11 Jul 2026
Form 3File: Form 3 - June 24_compressed.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold June 24.pdf11 Jul 2026
Form 1File: Form 1 - Sept 24.pdf11 Jul 2026
Form 2File: Form 2 Sept 24.pdf11 Jul 2026
Form 3File: Form 3 - Sept 24_compressed.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 24.pdf11 Jul 2026
Form 1File: Form 1 - Architect Certificate- Om Sai Complex Dec 24.pdf11 Jul 2026
Form 2File: Form 2 - Engineer Certificate -Om Sai Complex Dec 24.pdf11 Jul 2026
Form 3File: Form 3 - CA Certificate - Om Sai Complex - Dec 24.pdf11 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 24.pdf11 Jul 2026
Form 5 (FY 2024-2025)File: FORM 5.pdf11 Jul 2026
Form 5 (FY 2023-2024)File: Form 5 Audit Report (FY 2023-24) - OM SAI COMPLEX.pdf9 Jun 2026
Form 5 (FY 2022-2023)File: Form 5 FY 22-23 - Om Sai.pdf9 Jun 2026
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Om Sai .pdf19 Mar 2024
Certificates of CA (Form 3)File: Form 3 Dec 23.pdf19 Mar 2024
Declaration in FORM BFile: FORM B.pdf18 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 23.pdf18 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 23.pdf18 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf18 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Dec 23.pdf18 Mar 2024
Proforma of Agreement for saleFile: Draft Sale Agreement-Om Sai Complex.pdf15 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2018.pdf7 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019.pdf7 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020.pdf7 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf7 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2022.pdf7 Jul 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf3 Jul 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2018.pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2019.pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2020.pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2022.pdf3 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2023.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2018.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2019.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2020.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2021.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022.pdf3 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023.pdf3 Jul 2023
Certificates of CA (Form 3)File: Form 3 2018_compressed.pdf3 Jul 2023
Certificates of CA (Form 3)File: Form 3 2019_compressed.pdf3 Jul 2023
Certificates of CA (Form 3)File: Form 3 2020_compressed.pdf3 Jul 2023
Certificates of CA (Form 3)File: Form 3_compressed.pdf3 Jul 2023
Certificates of CA (Form 3)File: Form 3 2022_compressed.pdf3 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format Decleration about separate bank accounts.pdf3 Jul 2023
Deviation Report with respect to Allotment letterFile: No Deviation with respect to allotment letter.pdf3 Jul 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation with respect to model copy of Agreement.pdf3 Jul 2023
Declaration about Commencement CertificateFile: Declearation about commencement certificate.pdf29 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A 2020.pdf29 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2021.pdf29 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021.pdf29 Jun 2023

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHIV SUGANDHOPP DISHA HOTEL KHARODI NAKA VIRAR WEST41CompletedOct 2013Feb 2013
CHHAYA SUGANDHOPP DISHA HOTEL KHARODI NAKA VIRAR WEST72CompletedSep 2013Feb 2013
SMRUTI SUGANDHOPP DISHA HOTEL KHARODI NAKA VIRAR WEST60CompletedAug 2013Feb 2013

How this compares with Palghar

42%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 60 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OM SAI COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Betegaon3,200+ in Palghar

2 kmOM SAI COMPLEXCompleted 8Lapsed / revoked 17Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 59 registered projects within 2 km.

Builder: VARSHA PRAKASH NAIK

VARSHA PRAKASH NAIK has 2 registrations on MahaRERA, including SUGANDHI VIHAR and OM SAI COMPLEX. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if OM SAI COMPLEX is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM SAI COMPLEX?

The registered promoter entity is VARSHA PRAKASH NAIK, an individual as per the filing. Its GSTIN 27ADEPN2499R1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM SAI COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against OM SAI COMPLEX?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for OM SAI COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OM SAI COMPLEX?

The professionals named in the filing: Architect: YASH MILIND NANSI; Engineer: GANESH RAGHUNATH AWHAD; Engineer: Vyas Mishra; Chartered Accountant: D N FARGOES & CO; Chartered Accountant: Sankhala & Co; Chartered Accountant: DOLLY MILAN ASHAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM SAI COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM SAI COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM SAI COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.