ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Om Avaneesh Apartment

Completed No litigation declared Residential / Group Housing project

Om Avaneesh Apartment

By INFINITI INFRAVENTURES

RG-MH-75836 · RERA P50500021756 · Last updated on MahaRERA portal: 3 Jun 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 16 documents Report an error

Om Avaneesh Apartment is a Residential / Group Housing project by INFINITI INFRAVENTURES in Nagpur, Maharashtra, registered with MahaRERA as P50500021756 on 23 Jul 2019. The registration is recorded completed; possession was promised by 30 Dec 2023.

At a glance

Project

  • NameOm Avaneesh Apartment
  • TypeResidential / Group Housing
  • Location
    • Plot No 2
    • KH 118
    • 120/1
    • 121/1
    • Zingabai Takli
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440030
  • Pincode440030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500021756
  • ReraGenie IDRG-MH-75836

Builder

  • NameINFINITI INFRAVENTURES
  • Entity typePartnership
  • PartnersPRAJAKTA HARSHAVARDHAN RAUT, HARSHAVARDHAN RATNAKAR RAUT
  • Other registrations4 more →
  • Completed4 of 5
  • Declared earlier projects2 →

Key dates

this monthRegisteredJul 2019PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2019
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed16 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Om Avaneesh ApartmentNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Om Avaneesh Apartment: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,311 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2029.0
Proposed, not sanctioned2,029 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRavi Nagar Nagpur

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUmesh Lamge
PartnerRole in project
INFINITI INFRAVENTURES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jul 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jul 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Nov 2021

Documents filed16

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf3 Jun 2022
Architect’s Certificate on Completion of Project (Form 4)File: aRCHITECT COMPLETION CERTIFICATE.pdf11 Nov 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf5 Nov 2021
Building plan approvalFile: Map Plan 1.PDF18 Jul 2019
Building plan approvalFile: Map Plan 2.PDF18 Jul 2019
Layout approvalFile: Layout Plan.PDF18 Jul 2019
Copy of Layout Approval (in case of layout)File: Layout Plan.PDF18 Jul 2019
Building Plan Approval (IOD)File: Map Plan 1.PDF18 Jul 2019
Building Plan Approval (IOD)File: Map Plan 2.PDF18 Jul 2019
Copy of the legal title reportFile: Search Report.pdf11 Jul 2019
Certificates of CA (Form 3)File: CA Certificate.pdf11 Jul 2019
Proforma of Allotment letterFile: agromavanesshapartment.pdf11 Jul 2019
Details of encumbrancesFile: nonencumbrance.pdf5 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf28 May 2019
Declaration in FORM BFile: Form B.pdf28 May 2019
PAN CardFile: Pan Cardd.pdf22 May 2019

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
OM ARNESH APARTMENTP50500032036ZINGABAI TAKLI NAGPUR, Nagpur-Dec 2021CompletedDec 2024Jul 2023
Om Aaradhya ApartmentPlot no 3D KH No 141 Godhni Rly Nagpur11-CompletedJul 2018Late, Aug 2018

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Om Avaneesh Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Zingabai Takli2,800+ in Nagpur

2 kmOm Avaneesh ApartmentCompleted 14Lapsed / revoked 5Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: INFINITI INFRAVENTURES

INFINITI INFRAVENTURES has 5 registrations on MahaRERA, including OM AARADHYA APARTMENT and Om Amitesh Apartment. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Om Avaneesh Apartment is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Om Avaneesh Apartment?

The registered promoter entity is INFINITI INFRAVENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Om Avaneesh Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Om Avaneesh Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Om Avaneesh Apartment?

The professionals named in the filing: Architect: Umesh Lamge. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Om Avaneesh Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Om Avaneesh Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Om Avaneesh Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.