Home / Browse projects / Raigarh, Maharashtra / NOVA 10 ELEGANCE - PHASE 1

Registered Litigation declared Others project

NOVA 10 ELEGANCE - PHASE 1

By APEX REALTY

RG-MH-19571 · RERA P52000078523 · Last updated on MahaRERA portal: 15 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Rs 75.00 crore secured on the land, in favour of AU SMALL FINANCE BANK LTD

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
5 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 90%
84 of 228Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

NOVA 10 ELEGANCE - PHASE 1 is a Others project by APEX REALTY in Raigarh, Maharashtra, registered with MahaRERA as P52000078523 on 21 Dec 2024. Possession is promised by 31 Dec 2029. 144 of the 228 units on this registration are recorded sold or booked, and 5 of 22 construction stages are filed complete.

At a glance

Project

  • NameNOVA 10 ELEGANCE - PHASE 1
  • TypeOthers
  • Location
    • ROHINJAN
    • RAIGAD
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000078523
  • ReraGenie IDRG-MH-19571

Builder

  • NameAPEX REALTY
  • Entity typePartnership
  • PartnersDinesh Bherumal Bhojwani, RAJESH DOULATRAM RAHEJA
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredDec 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Dec 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed73 files

Current status

63%144 of 228 units booked
12.1%Work done, per cost certificate

Figures as on 15 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER BNA2015451358
TOWER ANA45341700170

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 90%.

TOWER B31%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)50%
Plinth100%
Stilt Floor90%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TOWER A38%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)60%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1293

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,293
Closed/Covered1,293
BuildingClosed/CoveredTotal
TOWER B420420
TOWER A873873

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area7,612 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAU SMALL FINANCE BANK LTD
Secured amountRs 75.00 crore
CERSAI search filedYes
Declared on12 Mar 2026

Approvals and building plan

Sanctioning authorityPANVEL MUNICIPAL CORPORATION
Permissible FSI31081.29
Proposed, not sanctioned31,081 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No. 70 ,Patel Heritage,Hiranandani Kharghar,Mumbai,Maharashtra-410210
Estimated costRs 265.00 cr
Cost incurredRs 32.12 cr
Work done12.12%
BuildingWingEstimatedIncurred
TOWER ANARs 140.62 crRs 20.24 cr
TOWER BNARs 84.38 crRs 10.80 cr
-NARs 40.00 crRs 1.08 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAARTI SAWANT SAWANT
EngineerASSOCIATED STRUCTURAL ENGINEER LLP
EngineerMUSTAFA SHABBIR MADARWALA
Chartered AccountantKISHNANI AND CO
Chartered AccountantK.R. MAKHIJA & ASSOCIATES
PartnerRole in project
APEX REALTY-

Litigation declared1

CaseCourtStatus
5/2024REGULAR CIVIL SUITClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A.pdf15 Jun 2026
Form 5 (FY 2025-2026)File: Form 5.pdf15 Jun 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE 31-03-2026.pdf25 May 2026
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE 31-03-2026.pdf25 May 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE 31-03-2026.pdf25 May 2026
Withdrawal Update Form 1File: Form 1.pdf18 Mar 2026
Withdrawal Update Form 2File: Form 2.pdf18 Mar 2026
Withdrawal Update Form 3File: FORM 3.pdf18 Mar 2026
Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf7 Jan 2026
Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf7 Jan 2026
Form 3File: FORM 3 CA CERTIFICATE.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf7 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5 2024-2025.pdf7 Jan 2026
Form 1File: Form-1.pdf30 Jul 2025
Form 2File: Form-2.pdf30 Jul 2025
Form 3File: Form-3.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold-Unsold.pdf30 Jul 2025
Form 1File: Form 1 as on 31-03-25.pdf11 Jun 2025
Form 2File: Form 2 as on 31-03-25.pdf11 Jun 2025
Form 3File: Form 3 as on 31-03-25.pdf11 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Unsold Units.pdf11 Jun 2025
Building plan approvalFile: DRAWING 6, 7 and 8.pdf12 Dec 2024
Building plan approvalFile: DRAWING 3, 4 and 5.pdf12 Dec 2024
Building plan approvalFile: DRAWING Page 1and 2.pdf12 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING Page 1and 2.pdf12 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 3, 4 and 5.pdf12 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 6, 7 and 8.pdf12 Dec 2024
Details of encumbrances concerned to FinanceFile: Encumbrances Concerned Too Legal.pdf3 Dec 2024
Details of encumbrances concerned to LegalFile: Encumbrances Concerned Too Legal.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf29 Nov 2024
Copy of the legal title reportFile: TITLE CERTIFICATE - NOVA 10 ELEGANCE - PHASE 1.pdf27 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A (2).pdf27 Nov 2024
Proforma of Agreement for saleFile: Agreement for Sale - latest.pdf27 Nov 2024
Other - TechnicalFile: output (13).pdf23 Nov 2024
Other - TechnicalFile: ud resolution proof.pdf23 Nov 2024
Proforma of Allotment letterFile: Model Form Of Allotment Letter (1).pdf22 Nov 2024
Other - TechnicalFile: order no 50.pdf22 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank.pdf22 Nov 2024
Layout approvalFile: DRAWING 1.pdf13 Nov 2024
Copy of Layout Approval (in case of layout)File: DRAWING 1.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf11 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: output (12).pdf8 Nov 2024
Building plan approvalFile: DRAWING 10.pdf7 Nov 2024
Building plan approvalFile: DRAWING 9.pdf7 Nov 2024
Building plan approvalFile: DRAWING 8.pdf7 Nov 2024
Building plan approvalFile: DRAWING 7.pdf7 Nov 2024
Building plan approvalFile: DRAWING 6.pdf7 Nov 2024
Building plan approvalFile: DRAWING 5.pdf7 Nov 2024
Building plan approvalFile: DRAWING 4.pdf7 Nov 2024
Building plan approvalFile: DRAWING 3.pdf7 Nov 2024
Building plan approvalFile: DRAWING 2.pdf7 Nov 2024
Building plan approvalFile: CC.pdf7 Nov 2024
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE TO LEGAL AND FINANCE.pdf7 Nov 2024
Declaration in FORM BFile: Form B Affidavit.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf7 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 8.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: CC.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 2.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 3.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 4.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 5.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 6.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 7.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 9.pdf7 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: DRAWING 10.pdf7 Nov 2024
Declaration about Commencement CertificateFile: Decleration About Commencement Certificate.pdf7 Nov 2024
CERSAI detailsFile: Cersai Letter.pdf7 Nov 2024
Deviation Report with respect to Allotment letterFile: No Deviation In Allotment Letter.pdf7 Nov 2024
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE TO LEGAL AND FINANCE.pdf7 Nov 2024
Deviation Report with respect to model copy of AgreementFile: No Deviation In Agreement.pdf7 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure For Secured Unsecured Finance Availed For the Projec.pdf7 Nov 2024
PAN CardFile: Apex Realty_PAN Card.pdf5 Nov 2024

How this compares with Raigarh

63%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NOVA 10 ELEGANCE - PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAIGAD5,900+ in Raigarh

2 kmNOVA 10 ELEGANCE - PHASECompleted 38Lapsed / revoked 36Other 88Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: APEX REALTY

Apex Realty has 3 registrations on MahaRERA, including Apex landmark and APEX AVENUE. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if NOVA 10 ELEGANCE - PHASE 1 is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NOVA 10 ELEGANCE - PHASE 1?

The registered promoter entity is APEX REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NOVA 10 ELEGANCE - PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NOVA 10 ELEGANCE - PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NOVA 10 ELEGANCE - PHASE 1?

The professionals named in the filing: Architect: AARTI SAWANT SAWANT; Engineer: ASSOCIATED STRUCTURAL ENGINEER LLP; Engineer: MUSTAFA SHABBIR MADARWALA; Chartered Accountant: KISHNANI AND CO; Chartered Accountant: K.R. MAKHIJA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NOVA 10 ELEGANCE - PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NOVA 10 ELEGANCE - PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NOVA 10 ELEGANCE - PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.