Home / Browse projects / Kolhapur, Maharashtra / NITYANAND RESIDENCY C WING
NITYANAND RESIDENCY C WING
RG-MH-56049 · RERA P53000052180 · Last updated on MahaRERA portal: 19 Dec 2025
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NITYANAND RESIDENCY C WING is a Residential / Group Housing project by D G ASSOCIATES in Kolhapur, Maharashtra, registered with MahaRERA as P53000052180 on 27 Jul 2023. The registration is recorded completed; possession was promised by 31 Dec 2026. 11 of the 28 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameNITYANAND RESIDENCY C WING
- TypeResidential / Group Housing
- Location
- SHIVAJI PARK
- SANE GURUJI VASAHAT
- Balinge
- Karvir
- Kolhapur
- 416003
- Pincode416003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53000052180
- ReraGenie IDRG-MH-56049
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jul 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 19 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NITYANAND RESIDENCY C WING | NA | 7 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
NITYANAND RESIDENCY C WING: 88% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 19 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed70
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sahas Patil |
| Engineer | Suil Desai |
| Chartered Accountant | Jayantkumar Ganatra |
| Chartered Accountant | Kinjal Vajani |
| Partner | Role in project |
|---|---|
| D G ASSOCIATES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Jun 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed68
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Completion Certificate.pdf | 19 Dec 2025 |
| Form 1File: Form 1 Q2 20205.pdf | 24 Oct 2025 |
| Form 2File: Form 2 Q2 2025.pdf | 24 Oct 2025 |
| Form 3File: Form 3 q2 2025 Upload.pdf | 24 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 24 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 CA 24-25.pdf | 1 Oct 2025 |
| Form 5 (FY 2023-2024)File: Form 5 23-24.pdf | 1 Oct 2025 |
| Form 1File: Form 1 Q1 2025.pdf | 18 Jul 2025 |
| Form 2File: Form 2 Q1 2025.pdf | 18 Jul 2025 |
| Form 3File: FOrm 3 Q1 2025.pdf | 18 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Q1 2025 Rera.pdf | 18 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Rera Q1 2025.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Q1 2025.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Q1 2025_compress.pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2A Engineering Q1 2025.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Q1 2025.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 18 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_compress.pdf | 18 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer_compress.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf | 18 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24_compress.pdf | 6 Dec 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_Asset_Id_Based_Search_25_11_2024_12_12_34_471.pdf | 25 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: D G Associates -sanction letter.pdf | 20 Nov 2024 |
| Details of encumbrances concerned to LegalFile: D G Associates -sanction letter.pdf | 20 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Rera.pdf | 1 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Corrected Sep 2024.pdf | 16 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Corrected Sold Unsold Inventory Sep 2024.pdf | 16 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Rera Sep 2024.pdf | 15 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Compress Sep 2024.pdf | 15 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Enginnering Certificate Rera Sept 2024.pdf | 15 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate June 2024.pdf | 10 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate June 2024-compressed.pdf | 10 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Sold Unsold List June 2024.pdf | 10 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate June 2024_compressed.pdf | 10 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 31-03-2024.pdf | 13 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_Certificate_31-03-2024.pdf | 13 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory List.pdf | 13 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: certificate Rera form 3.pdf | 13 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 2 Architect Certificate Jan 2024.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: LIST OF SOLD UNSOLD INVENTORY_compressed.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers Certificate Form 2.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Jan 2024.pdf | 17 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -I.pdf | 25 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf | 25 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 25 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 14 Jul 2023 |
| Proforma of Agreement for saleFile: AGREEMENT_FOR_SALE_Highlighted Corrected 2.pdf | 30 Jun 2023 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment letter with Annexure A.pdf | 30 Jun 2023 |
| Deviation Report with respect to Allotment letterFile: NO DEVIATION REPORT ALLOTMENT.pdf | 30 Jun 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A Seprate BANK ACCOUNT corrected.pdf | 23 Jun 2023 |
| Layout approvalFile: approved plana_compressed 1.pdf | 5 Jun 2023 |
| Building plan approvalFile: approvedplan1_compressed (1).pdf | 5 Jun 2023 |
| PAN CardFile: PAN D G ASSO.pdf | 5 Jun 2023 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 5 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: NO ENCUMBRACES.pdf | 5 Jun 2023 |
| Details of encumbrances concerned to LegalFile: NO ENCUMBRACES.pdf | 5 Jun 2023 |
| Copy of Layout Approval (in case of layout)File: approved plana_compressed 1.pdf | 5 Jun 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: approvedplan1_compressed (1).pdf | 5 Jun 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: KMC (1).pdf | 5 Jun 2023 |
| Declaration about Commencement CertificateFile: CC DECLARATION.pdf | 5 Jun 2023 |
| Declaration in FORM BFile: FORM B 1.pdf | 5 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 5 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate.pdf | 5 Jun 2023 |
| CERSAI detailsFile: CERSAI DECLARATION.pdf | 5 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: INTEREST IN OTHER PROJECTS.pdf | 5 Jun 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT.pdf | 5 Jun 2023 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT.pdf | 5 Jun 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NITYANAND RESIDENCY B WING | SANE GURUJI VASAHAT | 14 | Completed | Apr 2016 | Apr 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kolhapur
Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 68 filed documents as one ZIP, foldered, with a manifest
Keep NITYANAND RESIDENCY C WING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SANE GURUJI VASAHAT880+ in Kolhapur
Filed coordinates, straight-line distance. 49 registered projects within 2 km.
24 KEYWEST EAST AND WEST AVENUE
KEYWEST INFRA
Loknagari Karande Mala
VIKESH ABHAYKUMAR OSWAL
KRYSTAL TOWERS
RAYSONS CONSTRUCTIONS
GAYATRI-BHAWANI APARTMENT
Vijaykumar Vasudev Patki
EMINENT VISION TOWER
ACE DEVELOPERS
THE PARKSIDE
DESHPANDE INFRA
See every Kolhapur project, with the district possession charts
Builder: D G ASSOCIATES
D G ASSOCIATES has 2 registrations on MahaRERA, including ATHARVA PLAZA and NITYANAND RESIDENCY C WING. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.
Frequently asked questions
What are my rights if NITYANAND RESIDENCY C WING is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NITYANAND RESIDENCY C WING?
The registered promoter entity is D G ASSOCIATES, a partnership as per the filing. Its GSTIN 27AAIFD2476K1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NITYANAND RESIDENCY C WING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NITYANAND RESIDENCY C WING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NITYANAND RESIDENCY C WING?
The professionals named in the filing: Architect: Sahas Patil; Engineer: Suil Desai; Chartered Accountant: Jayantkumar Ganatra; Chartered Accountant: Kinjal Vajani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NITYANAND RESIDENCY C WING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback