ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Nirvana Bougainvilla

Registered No litigation declared Plotted project

Nirvana Bougainvilla

By Kishor Otarmal Jain

RG-MH-05241 · RERA P52000050750 · Last updated on MahaRERA portal: 8 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
14 of 49Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

Nirvana Bougainvilla is a Plotted project by Kishor Otarmal Jain in Raigarh, Maharashtra, registered with MahaRERA as P52000050750 on 28 Apr 2023. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 35 of the 49 units on this registration are recorded sold or booked. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNirvana Bougainvilla
  • TypePlotted
  • Location
    • Survey No- 21/1
    • 22/0
    • 23/0
    • 25/0
    • 24/1
    • 24/4
    • 26/3
    • Usale
    • Sudhagad
    • Raigarh
    • 410205
  • Pincode410205
  • RERA no.P52000050750
  • ReraGenie IDRG-MH-05241

Builder

  • NameKishor Otarmal Jain
  • Entity typeIndividual

Key dates

this monthRegisteredApr 2023First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2023
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • BuildingsNot stated in filing
  • Documents filed53 files

Current status

71%35 of 49 units booked
87.4%Work done, per cost certificate

Figures as on 8 Apr 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 8 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes65%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes25%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,129 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityTOWN PLANNING
Permissible FSI12129.0
Proposed, not sanctioned12,129 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNagothane Branch 106 Bazaar Peth Nagothane Roha Raigarh 402106
Estimated costRs 9.14 cr
Cost incurredRs 7.98 cr
Work done87.36%
BuildingWingEstimatedIncurred
-NARs 9.14 crRs 7.98 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDeepak Hiremath
EngineerDeepak Hiremath
EngineerNAIK ASSOCIATES
Chartered AccountantSanjay R Soni and Associates
PartnerRole in project
Kishor Otarmal Jain-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA08042620583Dec 2025 → Dec 2027

Reason as filed by the promoterThe delay was due to a shortage of manpower and insufficient financial resources.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604112Shruti Vijaykumar NandaKishor Otarmal Jain01/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1(architect certificate) Ready Dec 25.pdf8 Apr 2026
Withdrawal Update Form 1File: Form 1(architect certificate) Ready Dec 25.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 Naik associates Letter head Ready Dec 25.pdf8 Apr 2026
Withdrawal Update Form 2File: Form 2 Naik associates Letter head Ready Dec 25.pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 self attested.pdf8 Apr 2026
Withdrawal Update Form 3File: Form 3 self attested.pdf8 Apr 2026
Withdrawal Update Form 1File: Form 1(architect certificate) Ready Dec 25.pdf17 Mar 2026
Withdrawal Update Form 2File: Form 2 Naik associates Letter head Ready Dec 25.pdf17 Mar 2026
Withdrawal Update Form 3File: Form 3 Bougainvilla.pdf17 Mar 2026
Form 1File: Form 1(architect certificate) Ready Dec 25.pdf2 Mar 2026
Form 2File: Form 2 Naik associates Letter head Ready Dec 25.pdf2 Mar 2026
Form 3File: Form 3 Bougainvilla.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf2 Mar 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Ready Mar 24.pdf5 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JUNE 23 BOGANVILLA.pdf19 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SEPT23 BOGANVILLA.pdf19 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: DEC23 BOGANVILLA.pdf19 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Nirvana Valley Jun 23.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Nirvana Valley Sept 23.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Nirvana Valley Dec 23.pdf29 Feb 2024
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD UNSOLD INVENTORY.pdf28 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Ready Sept 23.pdf24 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Ready Jun 23.pdf24 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1(architect certificate) Ready Dec 23.pdf24 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Letter head Ready Sept 23.pdf24 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Letter head Ready Jun 23.pdf24 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Naik associates Letter head Ready Dec 23.pdf24 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Engineers certificate for quality assurance Ready Sept 23.pdf24 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Engineers certificate for quality assurance Ready Jun 23.pdf24 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Engineers certificate for quality assurance Ready Dec 23.pdf24 Feb 2024
Copy of the legal title reportFile: organized (2).pdf14 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf10 Apr 2023
Other - TechnicalFile: Layout Phase II- Highlighted Plan_11zon (1).pdf10 Apr 2023
Other - TechnicalFile: Declaration.pdf10 Apr 2023
Details of encumbrances concerned to FinanceFile: Encubrance letter-Finance.pdf18 Mar 2023
Details of encumbrances concerned to FinanceFile: Encumbrance letter-legal.pdf18 Mar 2023
Details of encumbrances concerned to LegalFile: Encubrance letter-Finance.pdf18 Mar 2023
Details of encumbrances concerned to LegalFile: Encumbrance letter-legal.pdf18 Mar 2023
Declaration about Commencement CertificateFile: Format-D.pdf18 Mar 2023
Declaration in FORM BFile: Form-B_compressed.pdf18 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report_200263117813_For_Asset_Based_Search_16_03_2023_12_03_04_069.pdf18 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-1_compressed.pdf18 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Formate-A.pdf18 Mar 2023
Deviation Report with respect to Allotment letterFile: Deviation in allotment letter.pdf18 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation in agreement.pdf18 Mar 2023
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (1).pdf16 Mar 2023
Building plan approval or NA orderFile: 1 Building Plan Approval _ NA Order for plotted development (2).pdf16 Mar 2023
PAN CardFile: 1 PAN Card (1).pdf16 Mar 2023
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (1).pdf16 Mar 2023
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development (2).pdf16 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development (1).pdf16 Mar 2023
Proforma of Agreement for saleFile: Agreement for Sale.pdf16 Mar 2023
Proforma of Allotment letterFile: Allottment letter.pdf16 Mar 2023

How this compares with Raigarh

71%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 24 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nirvana Bougainvilla on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Usale5,900+ in Raigarh

Builder: Kishor Otarmal Jain

Kishor Otarmal Jain has 1 registration on MahaRERA, including Nirvana Bougainvilla. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Nirvana Bougainvilla is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nirvana Bougainvilla?

The registered promoter entity is Kishor Otarmal Jain, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nirvana Bougainvilla?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Nirvana Bougainvilla?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Nirvana Bougainvilla?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nirvana Bougainvilla?

The professionals named in the filing: Architect: Deepak Hiremath; Engineer: Deepak Hiremath; Engineer: NAIK ASSOCIATES; Chartered Accountant: Sanjay R Soni and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nirvana Bougainvilla?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nirvana Bougainvilla. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nirvana Bougainvilla to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.