Home / Browse projects / Udupi, Karnataka / NIRMALA SERENITY

Registration approved No litigation declared Residential/Group Housing project

NIRMALA SERENITY

By Nirmala Constructions

RG-KA-43559 · RERA PRM/KA/RERA/1273/318/PR/010723/006028 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2026Possession promisedmoved 12 months from the original
17 of 17Construction stages doneevery applicable stage filed complete
15 of 32Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 132 documents Report an error

NIRMALA SERENITY is a Residential/Group Housing project by Nirmala Constructions in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/010723/006028 on 1 Jul 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 17 of the 32 units on this registration are recorded sold or booked, and 17 of 17 construction stages are filed complete.

At a glance

Project

  • NameNIRMALA SERENITY
  • TypeResidential/Group Housing
  • Location
    • Udupi
    • 576102
  • Pincode576102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1273/318/PR/010723/006028
  • ReraGenie IDRG-KA-43559

Builder

  • NameNirmala Constructions
  • Entity typeProprietorship Firm
  • GSTIN29AOEPK1838A1Z8
  • Authorized SignatoryK. NITHYANANDA KAMATH
  • Other registrations1 more →
  • Past their filed date1
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on1 Jul 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed132 files

Current status

53%17 of 32 units booked
111.4%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIRMALA SERENITY---32032

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 17 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes95%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes100%
Street LightingYes95%
ElectricityYes95%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes75%
Club HouseYes90%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes50%
ParksNoNot applicable
Power BackupYes100%
Piped GasYes100%
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,483 sq m
Land owned byNot the promoter
Named landowners2
LandownerVillageDistrict
U SURESH SHENOY--
U SURESH SHENOY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.49 cr
Cost incurredRs 16.15 cr
Spent of the estimate111.39%
BuildingWingEstimatedIncurred
-NARs 13.64 crRs 13.00 cr
-NARs 39.50 lakhRs 61.91 lakh
-NARs 35.00 lakhRs 2.31 cr
-NARs 10.72 lakh-
-NA-Rs 22.15 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamani Hande P S
EngineerU. Rajendra Maiya
Chartered AccountantCHANDRASHEKAR A G

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1273/318/PR/260526/006028Dec 2025 → Dec 2026

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed132

As listed on the registration, under the names the promoter filed them with; the newest 80 of 132 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/010723/006028 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE QU-Q1-2026-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate QU-01-2026-27.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate QU-01-2026-27.pdf15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE QU4-20256-26.pdf9 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate QU-04-2025-26.pdf9 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate QU-04-2025-26.pdf9 Jul 2026
Q4 2025-26 KPTCL- BESCOM9 Jul 2026
Q4 2025-26 Fire and Safety9 Jul 2026
upload self attested engineer licence of engineerFile: Engineer Licence 2026-27.pdf19 May 2026
renewed NOC's.File: Affidavit NOC.pdf19 May 2026
FIREFile: Fire NOCcompressed.pdf19 May 2026
KSPCBFile: KSPCBPOLLUTION REPORT.pdf19 May 2026
WATERFile: Water NOC.pdf19 May 2026
sold and unsold unitsFile: Sold & Unsold Units Nirmala Serenity .pdf19 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate QU3-2025-26.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate QU3-2025-26.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate QU3-2025-26.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
AkharbandhaFile: Akharbandha.pdf22 Jun 2023
area detailsFile: area details.pdf22 Jun 2023
Form_1 CA CertificateFile: Form_1 CA Certificate.pdf22 Jun 2023
Form_3 Engineer CertificateFile: Form_3 Engineer Certificate.pdf22 Jun 2023
Hissa MutationFile: Hissa Mutation.pdf22 Jun 2023
MESCOM NOCFile: MESCOM NOC.jpeg22 Jun 2023
VILLAGE MAPFile: VILLAGE MAP.pdf22 Jun 2023
Once again updated area details - Once again updated - ground floor exclusively meant for parking.File: area details.pdf6 May 2023
Once again updated cost details are incorrect - Add Rs.10,72,000 to the engineer cost.File: NIRMALA CONSTRUCTIONS CA CERTIFICATE.pdf6 May 2023
Address mentioned in the drawing - joint venture project hence owner address mentionedFile: Aproval Certificate(BUILDING LICENSE).pdf6 May 2023
Therefore Please update the Project bank account and time line completion date - GOKFile: Agreement of Sale Proforma - Nirmala Serenity.pdf6 May 2023
RERA Designated accountFile: Nirmala constructions Bank account details.pdf6 May 2023
2. Uploaded akhar banda and proper sketchFile: Akharbandha.pdf19 Apr 2023
total built area(All the floors) and plinth area(at Ground level) properly as per drawing and updateFile: area details.pdf19 Apr 2023
Please upload the renewed Engineer license certificate. - UploadedFile: renewed engineer certificate.pdf19 Apr 2023
Cost of the Project is Rs. 13,75,00,000 - Rs. 10,72,000 = Rs. 13,64,28,000 (Eng estd cost)File: NIRMALA CONSTRUCTIONS CA CERTIFICATE.pdf19 Apr 2023
NOC issued by Power supply authorities along with the copy of fee recipt paid towards NOCFile: Power supply receipt (1).pdf19 Apr 2023
concerned water supply Authority alomg with the copy of fee receipt paid towards water supplyFile: Water NOC.pdf19 Apr 2023
NOC issued by Airport Authority. - Not requiredFile: Clarification certificate for Airport authority.pdf19 Apr 2023
reason for delay - Licence obtained recently on 27-12-20222 before two monthsFile: Aproval CertificateBUILDING LICENSE.pdf19 Apr 2023
proforma of Agreement for sale as notified by GOK.File: Agreement of Sale Proforma - Nirmala Serenity.pdf19 Apr 2023
Number of parking mentioned in the project details - clarifiedFile: Engineer certificate for extra parking.pdf19 Apr 2023
Upload CDP map showing the proposed site.File: CDP Map.pdf19 Apr 2023
Upload village map showing the proposed site.File: VILLAGE MAP (1).pdf19 Apr 2023
Upload relinquishment deed (Road widening area) - Acquired for road formation letter uploadedFile: TDR letter .pdf19 Apr 2023
Cost of the Project is Rs. 13,75,00,000 - Rs. 10,72,000 = Rs. 13,64,28,000 (Eng estd cost)File: NIRMALA CONSTRUCTIONS CA CERTIFICATE.pdf4 Mar 2023
CD UDIN number 22029950AVVVQY5088 clearly mentioned in Balance Sheet along with scheduleFile: BALANCE SHEET AS ON 31-03-2022.pdf4 Mar 2023
Total extent of land is 64 out of it 61.36 of land utilised for projectFile: Municipal letter.pdf4 Mar 2023
Original jda dated 23/01/2023File: JDA before rectification.pdf4 Mar 2023
proper title deed to conversion land owner - Previous Owner Sale Deed ProducedFile: Sale Deed - Prescilla Aurelia Dilima.pdf4 Mar 2023
hissa phody copyFile: Mutation.pdf4 Mar 2023
Akarband and Survey SketchFile: Servey Sketch.pdf4 Mar 2023
certified copy rate list obtained by the concerned Sub-registrarFile: SRO Rate List -Serenity.pdf4 Mar 2023
Number of parking mentioned in the project details page not matching with the sanction plan clarifyFile: Engineer certificate for extra parking.pdf4 Mar 2023
Clear Single plot layoutFile: Single lay out.pdf4 Mar 2023
Clear Single plot layout OrderFile: Single lay out.pdf4 Mar 2023
certified Carpet area calculationFile: Certified carpet area and common area.pdf4 Mar 2023
village map showing the proposed siteFile: Village Map.pdf4 Mar 2023
relinquishment deed (Road widening area) - Not required under acquisitionFile: Municipal letter.pdf4 Mar 2023
Promoter name in the Sanction plan and KSPCB is not matching - Owner name suresh sehnoy mentionedFile: KSPCB(POLLUTION REPORT).pdf4 Mar 2023
Ground floor sanctioned drawingFile: APPROVED GROUND FLOOR PLAN.pdf4 Mar 2023
the renewed Engineer license certificateFile: ACKNOWLEDGEMENT RECEIPT Rajendra Maiya.pdf4 Mar 2023
Common Area Alloted To Association on the project detail pageFile: Certified carpet area and common area.pdf4 Mar 2023
Cost of the Project is Rs. 13,75,00,000 - Rs. 10,72,000 = Rs. 13,64,28,000 (Eng estd cost)File: ENGINEER'S CERTIFICATE.pdf4 Mar 2023
signed copy of the project specification by incorporating with the project name and project addressFile: Builder letterhead.pdf4 Mar 2023
NOC issued by Water supply authorities along with the copyFile: Water NOC.pdf4 Mar 2023
NOC issued by Fire forceFile: Fire NOC_compressed.pdf4 Mar 2023
STP design drawing and STP demarcation drawing as per the guidelines of KSPCB NOCFile: STP drawing.pdf4 Mar 2023
section 3(1) notarized affidavit by incorporating with the project name and addressFile: Affidavit Section 3 - Nirmala Serenity.pdf4 Mar 2023
proforma of Allotment letterFile: Proforma Allotment Letter - Nirmala Serenity.pdf4 Mar 2023
Licence obtained recently on 27-12-20222 before two monthsFile: Aproval Certificate(BUILDING LICENSE).pdf4 Mar 2023
CDP map showing the proposed siteFile: CDP Map.pdf4 Mar 2023
proforma of Agreement for sale(AFS)File: Agreement of Sale Proforma - Nirmala Serenity.pdf4 Mar 2023
Proprietorship registration certificateFile: Nirmala GST Certificate-New.pdf4 Mar 2023
Registration CertificateFile: Nirmala GST Certificate-New.pdf-
Certificate issued by CA Form 1File: NIRMALA CONSTRUCTIONS CA CERTIFICATE.pdf-
Certificate issued by Architect Form 2File: ARCHITECT CERTIFICATE.pdf-
Certificate issued by Engineer Form 3File: ENGINEER'S CERTIFICATE.pdf-
Project Chartered Accountant-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Nirmala ProvinceNear Sharada Kalyana Mantapa, KunjibettuCompleted-Not delivered

How this compares with Udupi

53%of this project is bookeddistrict median 0%
22%of Udupi projects moved their completion datethis one moved by 12 months
0%of Udupi registrations have lapsed or been cancelledthis one is on the register

Computed across the 260+ Udupi projects on ReraGenie, from their own filings.

Keep NIRMALA SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Udupi260+ in Udupi

2 kmNIRMALA SERENITYOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: Nirmala Constructions

Nirmala Constructions has 2 registrations on RERA Karnataka, including NIRMALA SERENITY and Nirmala Province. Its filings disclose 1 earlier RERA Karnataka project, none completed yet. Read the full track record. See more projects on the Udupi district page.

Frequently asked questions

What are my rights if NIRMALA SERENITY is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NIRMALA SERENITY?

The registered promoter entity is Nirmala Constructions, a proprietorship firm as per the filing. Its GSTIN 29AOEPK1838A1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NIRMALA SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NIRMALA SERENITY?

The professionals named in the filing: Architect: Ramani Hande P S; Engineer: U. Rajendra Maiya; Chartered Accountant: CHANDRASHEKAR A G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIRMALA SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIRMALA SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIRMALA SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.