Home / Browse projects / Udupi, Karnataka / OPULENCE
OPULENCE
RG-KA-58065 · RERA PRM/KA/RERA/1273/318/PR/160426/008587 · Last updated on RERA Karnataka portal: 13 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
OPULENCE is a Residential/Group Housing project by ONYX ASSETS LLP in Udupi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1273/318/PR/160426/008587 on 16 Apr 2026. Possession is promised by 31 Dec 2030. 7 of the 42 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.
At a glance
Project
- NameOPULENCE
- TypeResidential/Group Housing
- Location
- Udupi
- 576102
- Pincode576102
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1273/318/PR/160426/008587
- ReraGenie IDRG-KA-58065
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on16 Apr 2026
- Promised completion31 Dec 2030
- Revised completionNone
- Buildings1 building record
- Documents filed80 files
Current status
Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| OPULENCE | - | - | - | 42 | 0 | 42 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 25%.
Building: 22% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 20% |
| Retaining wall (All types) | 10% |
| RCC or MS Framed structure | 25% |
| Masonry Construction | 5% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities41
As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | Yes | 0% |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| watchman room | Yes | 0% |
| Staircases | Yes | 5% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| ONYX ASSETS LLP- HARISHA BHAT & ANAND KUDIGRAMA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 6.50 cr | Rs 1.30 cr |
| - | NA | Rs 20.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NAVANEETH S |
| Engineer | GANESH BADHYA |
| Chartered Accountant | B SENTHIL KUMAR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed80
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1273/318/PR/160426/008587 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Opulence.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: opulence architect 6-10-26.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: opulence engneer 06-10.pdf | 13 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - Opulence_compressed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: architect certificate.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate.pdf | 15 Jul 2026 |
| amenities declarationFile: amenities declaration.pdf | 9 Apr 2026 |
| self attested engineer licneceFile: self attested engineer licence.pdf | 9 Apr 2026 |
| form 3File: Form 3 engineer.pdf | 9 Apr 2026 |
| estimationFile: estimation.pdf | 9 Apr 2026 |
| structural stability certificate with decalration and licneceFile: stability certificate declaration with licence.pdf | 9 Apr 2026 |
| self attested structural engineer licence renewal copyFile: stractural engineer licence renewal copy.pdf | 9 Apr 2026 |
| stp drawingFile: STP drawing.pdf | 9 Apr 2026 |
| clariifcationFile: clarification.pdf | 9 Apr 2026 |
| RTC, survey 75/10 | - |
| Mutation, survey 75/10 | - |
| Encumbrance Certificate, survey 75/10 | - |
| Conversion/Alienation Order, survey 75/10 | - |
| Sale/Title/Gift Deed, survey 75/10 | - |
| Khatha, survey 75/10 | - |
| Registration CertificateFile: firm regsiatrtion certificate.jpeg | - |
| GST CertificateFile: GST.pdf | - |
| Partnership DeedFile: supplementary partnership deed 2026.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form -1.pdf | - |
| Certificate issued by Architect Form 2File: Architect certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form 3 engineer.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: litigation affidavit.pdf | - |
| Balance Sheet 2024 - 2025File: BS AY 2025-26.pdf | - |
| Balance Sheet 2023 - 2024File: BS AY 2024-25.pdf | - |
| Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: PL AY 2025-26.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: PL AY 2024-25.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: ITR AY 2025-26.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR AY 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf | - |
| building licence | - |
| approved plan | - |
| single layout | - |
| Stability certiifcate with mtech | - |
| specification | - |
| broucher | - |
| proforma AOS | - |
| Proforma allottment letter | - |
| form b | - |
| affidavit 3(1) | - |
| Search report | - |
| mescom noc | - |
| Water noc | - |
| UGD noc | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| mescom fee receipt | - |
| CDP plan | - |
| estimation | - |
| UGD noc | - |
| village map-shivalli | - |
| village map-site highlighted | - |
| Title deed_compressed | - |
| Partnership deed 2022 | - |
| Reconstitution of Partnership 2024 march | - |
| reconstitution of partnership deed 2024 sept | - |
| supplementary partnership deed 2026 | - |
| carpet area statement | - |
| land cost sheet with guidance value | - |
| STP drawing | - |
| location map with boundary point | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| RIVIERA BY ONYX | PROPOSED CONSTRUCTION OF RESIDENTIAL APARTMENT BUILDING WITH COMPOUND WALL BEARING IN , S.NO-88/251BP-13 ( PID NO: 31-4-29-26-0-1 AT 76 BADAGABETTU VILLAGE, IN UDUPI , 576101 | Ongoing | Dec 2030 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Udupi
Computed across the 260+ Udupi projects on ReraGenie, from their own filings.
Keep OPULENCE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Udupi260+ in Udupi
Filed coordinates, straight-line distance. 40 registered projects within 2 km.
MANDAVI DOWNTOWN
MANDAVI CONSTRUCTIONS
MANDAVI ROYAL GARDEN
MANDAVI INFRASTRUCTURES
SAI RADHA TOWNSHIP
MS SAI RADHA DEVELOPERS
ARCHANA SIGNATURE
ARCHANA PROJECTS
PLATINUM BY INTECH DEVELOPERS
INTECH DEVELOPERS
WESTEND HERITAGE
INDIAN DEVELOPERS
See every Udupi project, with the district possession charts
Builder: ONYX ASSETS LLP
ONYX ASSETS LLP has 3 registrations on RERA Karnataka, including OPULENCE and A.R. SATTVA. Its filings disclose 2 earlier RERA Karnataka projects, none completed yet. Read the full track record. See more projects on the Udupi district page.
Frequently asked questions
What are my rights if OPULENCE is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of OPULENCE?
The registered promoter entity is ONYX ASSETS LLP, a partnership firm as per the filing. Its LLPIN ABA-7078 and GSTIN 29AAHFO8455E1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in OPULENCE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at OPULENCE?
The professionals named in the filing: Architect: NAVANEETH S; Engineer: GANESH BADHYA; Chartered Accountant: B SENTHIL KUMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OPULENCE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.