Home / Browse projects / Nagpur, Maharashtra / NIRMAL TRINITY TOWERS
NIRMAL TRINITY TOWERS
By The Nirmal Ujjwal Credit Co-operative Society Limited
RG-MH-35967 · RERA P50500076597 · Last updated on MahaRERA portal: 16 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NIRMAL TRINITY TOWERS is a Others project by The Nirmal Ujjwal Credit Co-operative Society Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500076597 on 18 Jun 2024. Possession is promised by 30 Dec 2028. 10 of the 614 units on this registration are recorded sold or booked, and 5 of 121 construction stages are filed complete.
At a glance
Project
- NameNIRMAL TRINITY TOWERS
- TypeOthers
- Location
- Umred Road
- Mouza-Harpur
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440009
- Pincode440009
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500076597
- ReraGenie IDRG-MH-35967
Builder
- NameThe Nirmal Ujjwal Credit Co-operative Society Limited
- Entity typeSociety
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Jun 2024
- Promised completion30 Dec 2028
- Revised completionNone
- Buildings11 building records
- Documents filed128 files
Current status
Figures as on 16 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| T4 | NA | 30 | 28 | 102 | 16 | 118 |
| T5 | NA | 29 | 25 | 148 | 0 | 148 |
| T6 | NA | 29 | 25 | 148 | 0 | 148 |
| T7 | NA | 28 | 24 | 94 | 0 | 94 |
| T1 | NA | 4 | 3 | 4 | 16 | 20 |
| T2 | NA | 4 | 3 | 4 | 15 | 19 |
| T3 | NA | 4 | 3 | 4 | 15 | 19 |
| T10 | NA | 4 | 3 | 6 | 12 | 18 |
| T11 | NA | 4 | 3 | 6 | 16 | 22 |
| T8 | NA | 3 | 1 | 4 | 0 | 4 |
| T9 | NA | 3 | 1 | 4 | 0 | 4 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building11
As on 16 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Basement (if any), at 65%.
T410%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 11% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T515%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 65% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T615%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 60% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T718%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T10%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T100%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T110%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
T90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed1904
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| T4 | 516 | 516 |
| T5 | 531 | 531 |
| T6 | 531 | 531 |
| T7 | 326 | 326 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| The Nirmal Ujjwal Credit Cooperative Society Ltd. | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| T7 | NA | Rs 55.00 cr | Rs 14.03 cr |
| T5 | NA | Rs 50.00 cr | Rs 7.89 cr |
| T6 | NA | Rs 50.00 cr | Rs 9.80 cr |
| T4 | NA | Rs 45.00 cr | Rs 4.61 cr |
| T1 | NA | Rs 8.63 cr | - |
| T2 | NA | Rs 8.63 cr | - |
| T3 | NA | Rs 8.63 cr | - |
| T10 | NA | Rs 8.63 cr | - |
| T11 | NA | Rs 8.63 cr | - |
| T8 | NA | Rs 8.63 cr | - |
| T9 | NA | Rs 8.63 cr | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Harish Chandnani |
| Engineer | Naresh D Larokar |
| Engineer | Aman Kumar Singh |
| Engineer | Rachit Peter Micheal Rao |
| Chartered Accountant | Sumit Agrawal |
| Chartered Accountant | SALONI BANG |
| Chartered Accountant | SONAM THAKUR |
| Partner | Role in project |
|---|---|
| The Nirmal Ujjwal Credit Co-operative Society Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Feb 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Jan 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jan 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2028
Documents filed128
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: ArchitectCertificate Q4 25-26.pdf | 16 Apr 2026 |
| Withdrawal Update Form 2File: Engineer Certificate Q4 25-26.pdf | 16 Apr 2026 |
| Withdrawal Update Form 3File: CA Certificate Q4 25-26_11zon.pdf | 16 Apr 2026 |
| Withdrawal Update Form 1File: ARCHITECT CERTIFICATE Q3.pdf | 16 Jan 2026 |
| Withdrawal Update Form 2File: ENGINEER CERTIFICATE FORM 2.pdf | 16 Jan 2026 |
| Withdrawal Update Form 3File: Chartered Accountant Form 3 Compress.pdf | 16 Jan 2026 |
| Withdrawal Update Form 1File: Architectu0027s Certificate.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: Engineers Certificate.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: Chartered Accountants Certificate_compressed.pdf | 20 Oct 2025 |
| Form 2A (FY 2024-2025)File: Engineers Certificate For Quality Assurance Signed.pdf | 24 Sep 2025 |
| Form 5 (FY 2024-2025)File: Signed Form 5.pdf | 20 Sep 2025 |
| Withdrawal Update Form 1File: Architect Certificate form 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 1File: Architect Certificate form 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Engineers Certificate.pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Engineers Certificate.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: FINAL CA CERTIFICATE_compressed.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: FINAL CA CERTIFICATE_compressed.pdf | 19 Jul 2025 |
| Commencement certificateFile: Commencement certificate.pdf | 14 Jul 2025 |
| Form 1File: Form 1.pdf | 14 Jul 2025 |
| Form 2File: Form 2 Engineer certificate.pdf | 14 Jul 2025 |
| Form 3File: Forrm 3 final COMPRESSED.pdf | 14 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Forrm 3 final COMPRESSED-5.pdf | 14 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Forrm 3 final COMPRESSED.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architects Certificate.pdf | 17 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 certificate Nirmal Nagari_compressed.pdf | 17 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate.pdf | 17 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 CERTIFIED Architect certificare.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Sep 2024.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate-Qtr ended JUne 24.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Sep 2024_compressed.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Certified engineer Documents.pdf | 21 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Certified Engineer Certificate Sep 2024.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: nirmal ujjwal form-3_compressed.pdf | 11 Jun 2024 |
| Other - TechnicalFile: ARCHITECT CERTIFICATE_06062024.pdf | 7 Jun 2024 |
| Other - TechnicalFile: CARPET AREA TOWER WISE_06062024.pdf | 7 Jun 2024 |
| Other - TechnicalFile: New Document(56) 06-Jun-2024 18-32-53.pdf | 7 Jun 2024 |
| Other - TechnicalFile: AREA STATEMENT_06062024.pdf | 7 Jun 2024 |
| Other - TechnicalFile: NOS OF FLATS AND SHOPS_06062024.pdf | 7 Jun 2024 |
| Declaration in FORM BFile: Form B-.pdf | 17 May 2024 |
| Other - TechnicalFile: LETTERHEAD- AREA STATEMENT.pdf | 7 May 2024 |
| Other - TechnicalFile: Letter from NMC.pdf | 29 Apr 2024 |
| Other - TechnicalFile: LETTER_NIRMAL TRINITY.pdf | 2 Apr 2024 |
| Other - TechnicalFile: Annexure B.pdf | 16 Mar 2024 |
| Declaration about Commencement CertificateFile: Form D.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari-Letter 1 to 5.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari-Letter 6 to 8.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari-Letter 9 to 11.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari-Letter 12 to 15.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari-Letter 16 to 18.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari-Letter 19 to 22_compressed.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari- Letter 23 to 25_compressed.pdf | 15 Mar 2024 |
| Other - TechnicalFile: Nirmal Nagari- Letter 26 to 27.pdf | 15 Mar 2024 |
| Other - TechnicalFile: No of Shops.pdf | 26 Feb 2024 |
| Other - TechnicalFile: 2OtherTechnical.pdf | 23 Feb 2024 |
| Copy of the legal title reportFile: legal title report.pdf | 5 Feb 2024 |
| PAN CardFile: Pan Card -.pdf | 25 Jan 2024 |
| Building plan approvalFile: 1st Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: Sacsion CC.pdf | 18 Jan 2024 |
| Building plan approvalFile: Site Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: Upper GF Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: T1 T2 T3 T4 Plan 1.pdf | 18 Jan 2024 |
| Building plan approvalFile: T4 T5 T6 T7 4 to 24 Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: 26th Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: 26th Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: 27th Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: 6-10-14-18-22 Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: T5 to T11 Plan 1.pdf | 18 Jan 2024 |
| Building plan approvalFile: T5 to T11 Plan 2.pdf | 18 Jan 2024 |
| Building plan approvalFile: T5 to T11 Plan 4.pdf | 18 Jan 2024 |
| Building plan approvalFile: T1 T2 T3 T4 Plan 2.pdf | 18 Jan 2024 |
| Building plan approvalFile: T5 to T11 Plan 3.pdf | 18 Jan 2024 |
| Building plan approvalFile: T5 to T11 Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: Upper GF Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: NIRMAL TRINITY SANCTIONED DWGS.pdf | 18 Jan 2024 |
| Building plan approvalFile: 2BHK 25th Floor.pdf | 18 Jan 2024 |
| Building plan approvalFile: 3 BHK Tower 27 Floor.pdf | 18 Jan 2024 |
| Building plan approvalFile: Ground Floor Plan.pdf | 18 Jan 2024 |
| Building plan approvalFile: Open Space.pdf | 18 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 128 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NIRMAL TRINITY TOWERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mouza-Harpur2,800+ in Nagpur
Filed coordinates, straight-line distance. 26 registered projects within 2 km.
ROYAL PARK
RAI UDYOG GLOBE ASSOCIATES
Jyoti Thakare
JYOTI RAJESHWAR THAKARE
SHREE VIDHATA
SHIVCHARAN DEVELOPERS
JAIS INDUSTRIAL PARKK
SUBHASHCHANDRA DAYARAM JAIS
AFFORDABLE HOUSING PROPOSED ON KH.NO.54,CITY S
Nagpur Improvement Trust
ARMAN GRACIA
AQUEEL ANWAR UL HAQ SIDDIQUI
See every Nagpur project, with the district possession charts
Builder: The Nirmal Ujjwal Credit Co-operative Society Limited
The Nirmal Ujjwal Credit Co-operative Society Limited has 1 registration on MahaRERA, including NIRMAL TRINITY TOWERS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if NIRMAL TRINITY TOWERS is delayed beyond 30 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NIRMAL TRINITY TOWERS?
The registered promoter entity is The Nirmal Ujjwal Credit Co-operative Society Limited, a society as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NIRMAL TRINITY TOWERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NIRMAL TRINITY TOWERS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NIRMAL TRINITY TOWERS?
The professionals named in the filing: Architect: Harish Chandnani; Engineer: Naresh D Larokar; Engineer: Aman Kumar Singh; Engineer: Rachit Peter Micheal Rao; Chartered Accountant: Sumit Agrawal; Chartered Accountant: SALONI BANG. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NIRMAL TRINITY TOWERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback