Home / Browse projects / Nashik, Maharashtra / NIRMAL PARK APARTMENT

Registered No litigation declared Others project

NIRMAL PARK APARTMENT

By JND HOMESS LLP

RG-MH-13822 · RERA P51600029227 · Last updated on MahaRERA portal: 29 Mar 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedno revision filed
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

NIRMAL PARK APARTMENT is a Others project by JND HOMESS LLP in Nashik, Maharashtra, registered with MahaRERA as P51600029227 on 10 May 2021. Possession is promised by 25 Feb 2027. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNIRMAL PARK APARTMENT
  • TypeOthers
  • Location
    • JAIL ROAD NASHIK-ROAD
    • MAUJE PANCHAK SHIWAR SHANI MANDIR CHOWK
    • Nashik (M Corp.)
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600029227
  • ReraGenie IDRG-MH-13822

Builder

  • NameJND HOMESS LLP
  • Entity typePartnership
  • PartnersBHAILAL RAMJI CHHEDA, JIGGAR NEMCHAND GALA

Key dates

this monthRegisteredMay 2021PromisedFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 May 2021
  • Promised completion25 Feb 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIRMAL PARK APARTMENTNA110000
NMC VEGETABLE MARKETNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

NIRMAL PARK APARTMENT85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
NMC VEGETABLE MARKET75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities16

As on 29 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes60%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
LIFTYes50%

Parking filed251

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots251
Closed/Covered35
Open Space216
BuildingClosed/CoveredOpen SpaceTotal
NIRMAL PARK APARTMENT34216250
NMC VEGETABLE MARKET101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,732 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3623.65
Proposed, not sanctioned3,624 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch04 SUYOJIT ORCHID BHODHALE NAGAR NASHIK PUNE ROAD NASHIK 422006

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMOHIT KARNAVAT and ASSOCIATES
EngineerJAYESH MAKWANA
Chartered AccountantKARAN MAHALE
PartnerRole in project
JND HOMESS LLP-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC001000000090427Reena GujralJND Homess Llp09/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 25 Feb 2027

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal Park Apt Form 1 30_06_2024.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal Park Apt Form 1 30_09_2024.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal Park Apt Form 1 31_12_2024.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirmal Park Apt Form 3 30_06_2024.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirmal Park Apt Form 3 30_09_2024.pdf29 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirmal Park Apt Form 3 31_12_2024.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirmal Park Apt Form 2 30_06_2024.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirmal Park Apt Form 2 30_09_2024.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirmal Park Apt Form 2 31_12_2024.pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nirmal Park Form 5 F Y 23_24 30_09_2024.pdf29 Mar 2025
Details of encumbrances concerned to FinanceFile: Nirmal Park Encumbrance Legal Charged 31032024.pdf2 May 2024
Details of encumbrances concerned to FinanceFile: Nirmal Park Encumbrance Finance Charged 31032024.pdf2 May 2024
Details of encumbrances concerned to LegalFile: Nirmal Park Encumbrance Legal Charged 31032024.pdf2 May 2024
Details of encumbrances concerned to LegalFile: Nirmal Park Encumbrance Finance Charged 31032024.pdf2 May 2024
CERSAI detailsFile: Nirmal Park CERSAI_Search_Report_200305542948_For_Asset_Based_Search_02_05_2024_18_02_15_22 May 2024
Other - LegalFile: Nirmal Park Charged 7_12 02052024.pdf2 May 2024
Other - FinanceFile: Nirmal ParkSBI Project Loan 31122023.pdf2 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal Park Form 1 31032024.pdf1 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirmal Park Form 2 03042024.pdf1 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirmal Park Form 3 20042024.pdf1 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Nirmal park Commencement Certificate 01122023 Final.pdf1 Dec 2023
Other - TechnicalFile: Nirmal Park NMC Fire 01122023 Final.pdf1 Dec 2023
Building plan approvalFile: Nirmal Park Revised IOD 1.pdf8 Nov 2023
Building plan approvalFile: Nirmal Park Revised IOD 2.pdf8 Nov 2023
Building plan approvalFile: Nirmal Park Revised IOD 3.pdf8 Nov 2023
Building plan approvalFile: Nirmal Park Revised IOD 4.pdf8 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Revised IOD 1.pdf8 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Revised IOD 2.pdf8 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Revised IOD 3.pdf8 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Revised IOD 4.pdf8 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal park Form 1 18102023.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nirmal park Form 2 18102023.pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirmal park Form 3 08112023.pdf8 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nirmal park Form 5 22_23 08112023.pdf8 Nov 2023
Copy of the legal title reportFile: Nirmal Park Title Report 07042021.pdf21 Apr 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal Park Arch Certificate 16042021.pdf21 Apr 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirmal Park Form 1 16042021.pdf21 Apr 2021
Layout approvalFile: Nirmal Park Apt LayOut - 1.pdf12 Mar 2021
Building plan approvalFile: Nirmal Park Apt IOD-1.pdf12 Mar 2021
Building plan approvalFile: Nirmal Park Apt IOD-2.pdf12 Mar 2021
Building plan approvalFile: Nirmal Park Apt IOD-3.pdf12 Mar 2021
PAN CardFile: JND Homess LLP PAN Card Firm.pdf12 Mar 2021
PAN CardFile: Surendra Mohbiya PAN Card.pdf12 Mar 2021
PAN CardFile: Bhailal Chheda PAN Card.pdf12 Mar 2021
PAN CardFile: Jiggar N Gala PAN Card.pdf12 Mar 2021
Details of encumbrancesFile: Nirmal Park Apt Self Declairation 08032021.pdf12 Mar 2021
Copy of Layout Approval (in case of layout)File: Nirmal Park Apt LayOut - 1.pdf12 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Apt IOD-1.pdf12 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Apt IOD-2.pdf12 Mar 2021
Building Plan Approval / NA Order for plotted developmentFile: Nirmal Park Apt IOD-3.pdf12 Mar 2021
Commencement Certificates / NA Order for plotted developmentFile: Nirmal Park Apt Commecement Certificate 05032021.pdf12 Mar 2021
Declaration in FORM BFile: Nirmal Park Apt Form B 08032021.pdf12 Mar 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nirmal Park Apt Form 3 08032021.pdf12 Mar 2021
Proforma of Allotment letterFile: Nirmal Park Apt Allottment Letter 08032021.pdf12 Mar 2021
Proforma of Allotment letterFile: Nirmal Park Agreement Draft Flat.pdf12 Mar 2021
Proforma of Allotment letterFile: Nirmal Park Agreement Draft Shop.pdf12 Mar 2021

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NIRMAL PARK APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAUJE PANCHAK SHIWAR SHANI MANDIR CHOWK4,100+ in Nashik

2 kmNIRMAL PARK APARTMENTCompleted 48Lapsed / revoked 21Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: JND HOMESS LLP

JND HOMESS LLP has 1 registration on MahaRERA, including NIRMAL PARK APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if NIRMAL PARK APARTMENT is delayed beyond 25 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIRMAL PARK APARTMENT?

The registered promoter entity is JND HOMESS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIRMAL PARK APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NIRMAL PARK APARTMENT?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NIRMAL PARK APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIRMAL PARK APARTMENT?

The professionals named in the filing: Architect: MOHIT KARNAVAT and ASSOCIATES; Engineer: JAYESH MAKWANA; Chartered Accountant: KARAN MAHALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIRMAL PARK APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIRMAL PARK APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIRMAL PARK APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.