Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Sep 2024Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Installation of Lifts, 90%
2 of 11Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

NILAY RESIDENCY is a Others project by MANDAR UMESH KOKANE in Kolhapur, Maharashtra, registered with MahaRERA as P53000048555 on 6 Jan 2023. The registration is recorded completed; possession was promised by 30 Sep 2024. 9 of the 11 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameNILAY RESIDENCY
  • TypeOthers
  • Location
    • VASANT VISHWAS PARK
    • A ward NALE COLONY
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416007
  • Pincode416007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000048555
  • ReraGenie IDRG-MH-50391

Builder

  • NameMANDAR UMESH KOKANE
  • Entity typeIndividual
  • GSTIN27HSFPK1154M1ZE

Key dates

this monthRegisteredJan 2023PromisedSep 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Jan 2023
  • Promised completion30 Sep 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Current status

82%9 of 11 units booked
93.6%Work done, per cost certificate

Figures as on 9 Oct 2024, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NILAY RESIDENCYNA707411

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

NILAY RESIDENCY: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 9 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered23

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area250 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2024

Approvals and building plan

Sanctioning authorityKolhapur Municipal Corporation
Permissible FSI724.2
Proposed, not sanctioned724 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHAGITIRTHI HEIGHTS, 1116D E WARD, SHAHUPURI, KOLHAPUR
Estimated costRs 1.87 cr
Cost incurredRs 1.75 cr
Work done93.58%
BuildingWingEstimatedIncurred
NILAY RESIDENCYNARs 1.79 crRs 1.71 cr
-NARs 8.00 lakhRs 4.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectParshwa Consultants
EngineerSACHIN MEHTA Mehta
Chartered AccountantCA Nitish VandurePatil and Associates
Chartered AccountantSwapnil Narayan Vaidya
PartnerRole in project
MANDAR UMESH KOKANE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Dec 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Oct 2024

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf9 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf9 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupacy Certificate.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf7 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupacy Certificate.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf7 Oct 2024
Form 1File: Form 1.pdf25 Sep 2024
Form 2File: Form 2.pdf25 Sep 2024
Form 3File: Self Declaration.pdf25 Sep 2024
Disclosure of Sold and Booked InventoryFile: Sold unsold inventory.pdf25 Sep 2024
Form 5 (FY 2023-2024)File: Form 5.pdf24 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold unsold inventory.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf6 May 2024
Disclosure of sold/ booked inventoryFile: Sold unsold Final.pdf2 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate_compressed.pdf2 May 2024
Building plan approvalFile: Revised Sanctioned PLAN.pdf27 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Revised Sanctioned PLAN.pdf27 Apr 2024
Declaration about Commencement CertificateFile: Declaration About Commencement.pdf27 Apr 2024
Building plan approvalFile: Revised Sanctioned PLAN.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Revised Sanctioned PLAN.pdf25 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised Sanctioned ORDER.pdf25 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (10).pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold unsold april 24.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate_compressed.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf18 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Certification.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Declaration march.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 March.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 sep.pdf19 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory .pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Kokane.pdf19 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate-Kokane.pdf19 Jul 2023
Disclosure of sold/ booked inventoryFile: sold unsold Nilay residency-Kokane_compressed.pdf19 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Kokane.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Kokane04202023.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold unsold residency-Kokane04202023.pdf21 Apr 2023
Declaration about Commencement CertificateFile: Architect Letter.pdf16 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf16 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf16 Dec 2022
Copy of the legal title reportFile: Legal Title Report.pdf15 Dec 2022
Details of encumbrances concerned to FinanceFile: Concern to Finance.pdf15 Dec 2022
Details of encumbrances concerned to FinanceFile: Concern to legal.pdf15 Dec 2022
Details of encumbrances concerned to LegalFile: Concern to Finance.pdf15 Dec 2022
Details of encumbrances concerned to LegalFile: Concern to legal.pdf15 Dec 2022
Declaration about Commencement CertificateFile: Format D.pdf15 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf15 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf15 Dec 2022
Proforma of Allotment letterFile: Allottment Letter - New.pdf15 Dec 2022
Proforma of Agreement for saleFile: Building Agreement to Sell as per RERA Act 1 (1).pdf15 Dec 2022
Deviation Report with respect to Allotment letterFile: No Deviation in allotement letter.pdf15 Dec 2022
Deviation Report with respect to model copy of AgreementFile: No Deviation in agreement to sell.pdf15 Dec 2022
Building plan approvalFile: NA Order1.pdf20 Oct 2022
Building plan approvalFile: Sanction Plan.pdf20 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: NA Order1.pdf20 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan.pdf20 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf20 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: NILAY RESIDENCY - Bank Declaration.pdf19 Oct 2022
Details of encumbrances concerned to FinanceFile: Nilay - Finance.pdf27 Sep 2022
Details of encumbrances concerned to LegalFile: Nilay - Legal.pdf27 Sep 2022
Building plan approvalFile: NA Order.pdf9 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf9 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: NA Order1.pdf9 Jul 2022
Declaration in FORM BFile: Affidavit pdf.pdf9 Jul 2022
Layout approvalFile: Layout.pdf8 Jul 2022
PAN CardFile: PAN.pdf8 Jul 2022
Copy of Layout Approval (in case of layout)File: Layout.pdf8 Jul 2022

How this compares with Kolhapur

82%of this project is bookeddistrict median 19%
17%of Kolhapur projects moved their completion datethis one has not
25%of Kolhapur registrations have lapsed or been cancelledthis one is completed

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep NILAY RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near A ward NALE COLONY880+ in Kolhapur

2 kmNILAY RESIDENCYCompleted 23Lapsed / revoked 9Other 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 77 registered projects within 2 km.

Builder: MANDAR UMESH KOKANE

MANDAR UMESH KOKANE has 1 registration on MahaRERA, including NILAY RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if NILAY RESIDENCY is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NILAY RESIDENCY?

The registered promoter entity is MANDAR UMESH KOKANE, an individual as per the filing. Its GSTIN 27HSFPK1154M1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NILAY RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NILAY RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NILAY RESIDENCY?

The professionals named in the filing: Architect: Parshwa Consultants; Engineer: SACHIN MEHTA Mehta; Chartered Accountant: CA Nitish VandurePatil and Associates; Chartered Accountant: Swapnil Narayan Vaidya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NILAY RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NILAY RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NILAY RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.