Home / Browse projects / Chandrapur, Maharashtra / NIKHIL PLANET

Registration lapsed No litigation declared Others project

NIKHIL PLANET

By J K BUILDERS AND DEVELOPERS

RG-MH-94208 · RERA P50900022124 · Last updated on MahaRERA portal: 26 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 23 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
3 of 11Construction stages donefurthest along: Stilt Floor, 95%
28 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

NIKHIL PLANET is a Others project by J K BUILDERS AND DEVELOPERS in Chandrapur, Maharashtra, registered with MahaRERA as P50900022124 on 28 Aug 2019. Possession was promised by 14 Mar 2026 and is now 7 months past that date. The completion date has moved by 23 months from the original filing. 28 of the 56 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameNIKHIL PLANET
  • TypeOthers
  • Location
    • NEAR EKDANT LAWN
    • BALLARPUR
    • Ballarpur (M Cl)
    • Chandrapur
    • 442701
  • Pincode442701
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50900022124
  • ReraGenie IDRG-MH-94208

Builder

  • NameJ K BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersRAJKUMAR DHOLANDAS MULCHANDANI, SUNIL KEWALRAM MULCHANDANI, ARTI JAIKUMAR MULCHANDANI, KAJAL SUNIL MULCHANDANI, PREMPRAKASH PUNDLIKRAO MAKODE, MAHENDRA ASHOK KHATRI
  • Other registrations2 more →
  • Completed2 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredAug 2019First promiseApr 2024Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Aug 2019
  • Promised completion14 Mar 2026
  • Revised completionRevised to 14 Mar 2026 (originally 30 Apr 2024)
  • Buildings1 building record
  • Documents filed73 files

Current status

50%28 of 56 units booked

Figures as on 26 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIKHIL PLANETNA65243256

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

NIKHIL PLANET: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered42
Open Space28

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,980 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Mar 2026

Approvals and building plan

Sanctioning authorityBALLARPUR MUNICIPAL COUNCIL
Permissible FSI3679.4
Proposed, not sanctioned3,679 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOPP BUS STAND, BALLARPUR

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajesh Sawarkar
EngineerVaishnavi Karnewar
EngineerMANOJ KHATRI
Chartered AccountantManish Mulchandani
Chartered AccountantA M Dabke & Associates
PartnerRole in project
J K BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50900026071Apr 2024 → Mar 2026

Reason as filed by the promoterDear Respected Sir / Madam, Due to Corona Pandemic our work was hitted and also Labour Supply was Slow; henceforth our Construction Activity was unable to complete on time. Therefore, we requests you to kindly provide us Extension for our Project. Thanking You & Regards !

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jul 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jul 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B affidative.pdf26 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q3 2024-25.pdf26 Feb 2025
Certificates of CA (Form 3)File: Form 3 Q3 2024-25_compressed.pdf26 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 2024-25_compressed.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: unsold inventory.pdf26 Feb 2025
Declaration about Commencement CertificateFile: commencement declaration.pdf26 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 d.pdf3 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q1 d.pdf3 Jan 2025
Certificates of CA (Form 3)File: 2024-25 Q2 signed.pdf3 Jan 2025
Certificates of CA (Form 3)File: 2024-25 Q1 signed.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 signed 2024-25 Q2.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 signed 2024-25 Q1.pdf3 Jan 2025
Certificates of CA (Form 3)File: 2023-24_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2023-24 Q3_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2023-24 Q2_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2023-24 Q1_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2022-23_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2022-23 Q3_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2022-23 Q2_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2021-22_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: DEC 2021_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2020-21_compressed.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2019-20.pdf18 Oct 2024
Certificates of CA (Form 3)File: 2022-23 Q1_compressed.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2019-20.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020-21.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021-22.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-23.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2023-24.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf18 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023-24.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3 2023.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2 2023.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q1 2023.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2022-23.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3 2022.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2 2022.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q1 2022.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2021-22.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: DEC 2021.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2020-21.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2019-20.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2022-23 Q3.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-24 Q4.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-24 Q3.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-24 Q2.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-24 Q2.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2023-24 Q1.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2022-23 Q4.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2022-23 Q2.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2021-22.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: DEC 2021.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2021-22.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2020-21.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2019-20.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2022-23 Q1.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf26 Aug 2019
Building plan approvalFile: Building_Plan_Approval.pdf16 Jul 2019
Layout approvalFile: Layout_Approval.pdf16 Jul 2019
PAN CardFile: Pan_Firm.pdf16 Jul 2019
Copy of the legal title reportFile: Legal_Title_compressed.pdf16 Jul 2019
Details of encumbrancesFile: Not_Applicable.pdf16 Jul 2019
Copy of Layout Approval (in case of layout)File: Layout_Approval.pdf16 Jul 2019
Building Plan Approval (IOD)File: Building_Plan_Approval.pdf16 Jul 2019
Commencement Certificates / NA Order for plotted developmentFile: Commencement_Certi.pdf16 Jul 2019
Declaration in FORM BFile: FORM_B.pdf16 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Form_1.pdf16 Jul 2019
Certificates of CA (Form 3)File: CA_Form_3_compressed.pdf16 Jul 2019
Proforma of Allotment letterFile: Allotment_Sale_Agreement.pdf16 Jul 2019

How this compares with Chandrapur

50%of this project is bookeddistrict median 18%
10%of Chandrapur projects moved their completion datethis one moved by 23 months
39%of Chandrapur registrations have lapsed or been cancelledthis one is among them

Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.

Keep NIKHIL PLANET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BALLARPUR220+ in Chandrapur

Builder: J K BUILDERS AND DEVELOPERS

J K BUILDERS AND DEVELOPERS has 3 registrations on MahaRERA, including KALYANI SAI SWAROOP and KALYANI SAI ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Chandrapur district page.

Frequently asked questions

What does it mean that NIKHIL PLANET shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NIKHIL PLANET is delayed beyond 14 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIKHIL PLANET?

The registered promoter entity is J K BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIKHIL PLANET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NIKHIL PLANET?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIKHIL PLANET?

The professionals named in the filing: Architect: Rajesh Sawarkar; Engineer: Vaishnavi Karnewar; Engineer: MANOJ KHATRI; Chartered Accountant: Manish Mulchandani; Chartered Accountant: A M Dabke & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIKHIL PLANET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIKHIL PLANET. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIKHIL PLANET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.