Home / Browse projects / Palghar, Maharashtra / NIDAN EMPIRE

Registered No litigation declared Residential / Group Housing project

NIDAN EMPIRE

By NITIN VITTHALRAO THORAVE

RG-MH-96691 · RERA P99000019859 · Last updated on MahaRERA portal: 21 Aug 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 81 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 81 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 90%
26 of 70Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

NIDAN EMPIRE is a Residential / Group Housing project by NITIN VITTHALRAO THORAVE in Palghar, Maharashtra, registered with MahaRERA as P99000019859 on 7 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 81 months from the original filing. 44 of the 70 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameNIDAN EMPIRE
  • TypeResidential / Group Housing
  • Location
    • SAMEL PADA ROAD
    • NEAR DATTA MANDIR
    • NALASOPARA WEST
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000019859
  • ReraGenie IDRG-MH-96691

Builder

  • NameNITIN VITTHALRAO THORAVE
  • Entity typeIndividual

Key dates

this monthRegisteredMar 2019First promiseMar 2020Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Mar 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 1 Mar 2020)
  • Buildings1 building record
  • Documents filed59 files

Current status

63%44 of 70 units booked
75.4%Work done, per cost certificate

Figures as on 21 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AAKANSHA DEVELOPERSNA9770070

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

AAKANSHA DEVELOPERS: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 21 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered30
Open Space54

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,443 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Aug 2025

Approvals and building plan

Sanctioning authorityVASAI VIRAR CITY MUNCIPAL CORPORATION
Permissible FSI5532.0
Proposed, not sanctioned2,732 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNALASOPARA WEST-401203
Estimated costRs 8.57 cr
Cost incurredRs 6.46 cr
Work done75.38%
BuildingWingEstimatedIncurred
AAKANSHA DEVELOPERSNARs 8.09 crRs 6.46 cr
-NARs 48.53 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHIMANSHU GUPTA & ASSOCIATES
ArchitectSANJAY MALOO
EngineerAPTE ASSOCIATES
Chartered AccountantMISHRA MAYEKAR & CO
Chartered AccountantDOLLY harish ASHAR
PartnerRole in project
NITIN VITTHALRAO THORAVE-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019647Mar 2020 → Dec 2026

Reason as filed by the promoterDELAY DUE TO PARKING WORK AND CHANGE IN CONTRACTORS.

EXT99000006375Mar 2020 → Aug 2021

Reason as filed by the promoterDUE TO COVID & SHORTAGE OF LABOUR PROJECT IS STILL STUCK

EXT99000010871Mar 2020 → Sep 2023

Reason as filed by the promoterDUE TO COVID PANDEMIC AND FINANCIAL CRISES

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000089851JavedAkanksha Group Of Construction Co.25/06/2019
CC006000000195371Shobha UmraoNitin Vithalrao Thorave24/12/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jan 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Forn 1 Architects certificate (1).pdf21 Aug 2025
Withdrawal Update Form 2File: Apte - 30-06-25 (1) signed_11zon.pdf21 Aug 2025
Withdrawal Update Form 3File: Akansha form 3 signed 30 6 25.pdf21 Aug 2025
Disclosure of sold/ booked inventoryFile: Disclouser of sold unsold new.pdf23 Apr 2024
Proforma of Allotment letterFile: allotment letter.pdf23 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Forn 1 Architects certificate (1).pdf21 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (1).pdf21 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_200304407728_For_Asset_Based_Search_21_04_2024_12_55_13_159.pdf21 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclouser of sold unsold (1).pdf21 Apr 2024
Certificates of CA (Form 3)File: Form 3.pdf21 Apr 2024
Proforma of Agreement for saleFile: Nidan Empire Blank Format AGREEMENT.pdf21 Apr 2024
Details of encumbrances concerned to FinanceFile: Encumbrances concerned to legal.pdf20 Apr 2024
Details of encumbrances concerned to LegalFile: Encumbrances concerned to legal.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers certificate 2022.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers certificate 2023.pdf20 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclouser of intrest in other real estate project.pdf20 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2022.pdf20 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2023.pdf20 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of bank account.pdf20 Apr 2024
Deviation Report with respect to Allotment letterFile: Deviation report for allotment letter.pdf20 Apr 2024
Deviation Report with respect to model copy of AgreementFile: Deviation report for agreement sale.pdf20 Apr 2024
Other - TechnicalFile: Declaration cum undertaking (1).pdf20 Apr 2024
Declaration about Commencement CertificateFile: declaration abt CC.pdf8 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers certificate compressed.pdf8 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers certificate 2021compressed.pdf8 Sep 2021
Disclosure of sold/ booked inventoryFile: disclosure of sold and booked inventory nidan.pdf8 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 2017-2018.pdf8 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-2019.pdf8 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-2020.pdf8 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-2021.pdf8 Sep 2021
Certificates of CA (Form 3)File: CA Certificate.pdf11 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: krupesh0001-min.pdf5 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: VIRAR0001-min.pdf22 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: PLINTH CERTIFICATE.pdf22 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: combinepdf (1).pdf15 Feb 2019
Certificates of CA (Form 3)File: UNSOLD CA Certificate.pdf11 Feb 2019
Building plan approvalFile: BPLAN.pdf18 Jan 2019
Layout approvalFile: LAYOUT.pdf18 Jan 2019
Copy of the legal title reportFile: 1.pdf18 Jan 2019
Copy of the legal title reportFile: 2.pdf18 Jan 2019
Copy of the legal title reportFile: 3.pdf18 Jan 2019
Copy of the legal title reportFile: 4.pdf18 Jan 2019
Copy of the legal title reportFile: 5.pdf18 Jan 2019
Copy of the legal title reportFile: 6.pdf18 Jan 2019
Copy of the legal title reportFile: 7.pdf18 Jan 2019
Copy of the legal title reportFile: 8.pdf18 Jan 2019
Copy of the legal title reportFile: 9.pdf18 Jan 2019
Copy of the legal title reportFile: 10.pdf18 Jan 2019
Copy of the legal title reportFile: 11.pdf18 Jan 2019
Details of encumbrancesFile: EMBURANCE.pdf18 Jan 2019
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf18 Jan 2019
Building Plan Approval (IOD)File: BPLAN.pdf18 Jan 2019
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf18 Jan 2019
Declaration in FORM BFile: FORM B.pdf18 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS.pdf18 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTIFICATE.pdf18 Jan 2019
Proforma of Allotment letterFile: declaration.pdf18 Jan 2019
PAN CardFile: PAN.pdf8 Jan 2019
OtherFile: AADHAR.pdf8 Jan 2019

How this compares with Palghar

63%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 81 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NIDAN EMPIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NALASOPARA WEST3,200+ in Palghar

2 kmNIDAN EMPIRECompleted 44Lapsed / revoked 36Other 86Dot size: filed unitsN

Filed coordinates, straight-line distance. 166 registered projects within 2 km.

Builder: NITIN VITTHALRAO THORAVE

NITIN VITTHALRAO THORAVE has 1 registration on MahaRERA, including NIDAN EMPIRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if NIDAN EMPIRE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIDAN EMPIRE?

The registered promoter entity is NITIN VITTHALRAO THORAVE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIDAN EMPIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NIDAN EMPIRE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NIDAN EMPIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIDAN EMPIRE?

The professionals named in the filing: Architect: HIMANSHU GUPTA & ASSOCIATES; Architect: SANJAY MALOO; Engineer: APTE ASSOCIATES; Chartered Accountant: MISHRA MAYEKAR & CO; Chartered Accountant: DOLLY harish ASHAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIDAN EMPIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIDAN EMPIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIDAN EMPIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.