Home / Browse projects / Pune, Maharashtra / Nexus Kinaara D
Nexus Kinaara D
RG-MH-27530 · RERA P52100033605 · Last updated on MahaRERA portal: 2 Feb 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Nexus Kinaara D is a Residential / Group Housing project by Nexus Enterprises in Pune, Maharashtra, registered with MahaRERA as P52100033605 on 2 Mar 2022. The registration is recorded completed; possession was promised by 30 Dec 2025. The completion date has moved by 12 months from the original filing. 99 of the 120 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameNexus Kinaara D
- TypeResidential / Group Housing
- Location
- Behind River residency
- Chikhali
- Haveli
- Pune
- 412114
- Pincode412114
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100033605
- ReraGenie IDRG-MH-27530
Builder
- NameNexus Enterprises
- Entity typePartnership
- PartnerSatishkumar Ravjibhai Patel
- Other registrations2 more →
- Completed2 of 3
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on2 Mar 2022
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed164 files
Current status
Figures as on 2 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D Building | NA | 18 | 15 | 120 | 0 | 120 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
D Building: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 2 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed75
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Dhanvir Madhukar Jadhav | Chikhali | Pune |
| Daulat Madhukar Jadhav | Chikhali | Pune |
| Madhukar Rangnath Jadhav | Chikhali | Pune |
| Hanumant Nivrutti Jadhav | Chikhali | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mahendra Thakur and Associates |
| Architect | Dream Space Architect |
| Engineer | Ajinkya A Lahigude |
| Chartered Accountant | Shubham S Bora |
| Chartered Accountant | Mohamadyasir A Bagwan |
| Chartered Accountant | DHIRAJ MANOJ BALDOTA |
| Chartered Accountant | Vinit D Achha and Associates Chartered Accountant |
| Partner | Role in project |
|---|---|
| Nexus Enterprises | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe shortage of raw material like Cement, Crushed Sand, Steel and more which constitute major portion for Construction Industry, however we are not in position to ascertain the exact the delay for such activity for the project We wish to inform you that the construction of our project has been 90% completed. Given these circumstances, we kindly request MahaRERA to grant us an extension of Twelve months for the archiving completion certificate of our project. This extension will allow us to complete all necessary formalities and obtain the Completion Certificate without further complications.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 23 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 10 Jan 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed164
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 164 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 1) ARCHITECT CERTIFICATE WING D DATE 31-03-22.pdf | 2 Feb 2026 |
| Withdrawal Update Form 1File: 1) ARCHITECT CERTIFICATE WING D DATE 31-03-22.pdf | 2 Feb 2026 |
| Withdrawal Update Form 2File: 1) ENG CERTIFICATE 17-05-2022 (31-03-22).pdf | 2 Feb 2026 |
| Withdrawal Update Form 2File: 1) ENG CERTIFICATE 17-05-2022 (31-03-22).pdf | 2 Feb 2026 |
| Withdrawal Update Form 3File: 2) CA CERTIFICATE DATE 16-05-2024 (31-03-24)_comp.pdf | 2 Feb 2026 |
| Withdrawal Update Form 3File: 2) CA CERTIFICATE DATE 16-05-2024 (31-03-24)_comp.pdf | 2 Feb 2026 |
| Occupational CertificateFile: Occupancy Certificate.pdf | 2 Feb 2026 |
| Occupational CertificateFile: Occupancy Certificate.pdf | 18 Sep 2025 |
| Form 5 (FY 2021-2022)File: 1 Form 5 (02-03-2022 to 31-03-2022) Date 22-09-2022.pdf | 25 Aug 2025 |
| Form 5 (FY 2022-2023)File: 2 Form 5 (01-04-2022 to 31-03-2023).pdf | 25 Aug 2025 |
| Form 5 (FY 2023-2024)File: 3 Form 5 (01-04-2023 to 31-03-2024) Date 09-07-2024.pdf | 25 Aug 2025 |
| Form 5 (FY 2024-2025)File: 4)Form - 5 ( 01-04-2024 - 31-03-2025) Date - 06-08-2025.pdf | 25 Aug 2025 |
| Form 1File: 16) ARCHITECT CERTIFICATE WING D DATE 30-06-2025.pdf | 25 Jul 2025 |
| Form 2File: 16) ENGINEER CRTIFICATE DATE-30-06-2025.pdf | 25 Jul 2025 |
| Form 3File: 15 CA CERTIFICATE DATE 30-06-2025 compressed.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 14) DISCLOUSURE OF SOLD & UNSOLD ( 01-04-2025 TO 30-06-2025 ) Q1_compressed.pdf | 25 Jul 2025 |
| Form 1File: 11) ARCHITECT CERTIFICATE WING D DATE 31-03-2024.pdf | 24 Jul 2025 |
| Form 2File: 10) ENGINEET CRTIFICATE DATE - 31-03-2024.pdf | 24 Jul 2025 |
| Form 3File: 10 CA CERTIFICATE DATE 16-05-2024 (March-24)_compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 9) DISCLOUSURE OF SOLD & UNSOLD ( 01-01-2024 TO 31-03-2024 ) Q4_compressed.pdf | 24 Jul 2025 |
| Form 1File: 12) ARCHITECT CERTIFICATE WINGD DATE 30-06-2024.pdf | 24 Jul 2025 |
| Form 2File: 11) ENGINEET CRTIFICATE DATE - 30-06-2024.pdf | 24 Jul 2025 |
| Form 3File: 11 CA CERTIFICATE DATE 13-07-2024 (June-24)_compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 10) DISCLOUSURE OF SOLD & UNSOLD ( 01-04-2024 TO 30-06-2024 ) Q1_compressed.pdf | 24 Jul 2025 |
| Form 1File: 13) ARCHITECT CERTIFICATE WINGD DATE 30-09-2024.pdf | 24 Jul 2025 |
| Form 2File: 12) ENGINEET CRTIFICATE DATE - 30-09-2024.pdf | 24 Jul 2025 |
| Form 3File: 12 CA CERTIFICATE DATE 22-11-2024 (Sep-24)_compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 11) DISCLOUSURE OF SOLD & UNSOLD ( 01-07-2024 TO 30-09-2024 ) Q2_compressed.pdf | 24 Jul 2025 |
| Form 1File: 14) ARCHITECT CERTIFICATE WINGD DATE 31-12-2024.pdf | 24 Jul 2025 |
| Form 2File: 14) ENGINEER CRTIFICATE DATE 0512025 Date31122024.pdf | 24 Jul 2025 |
| Form 3File: 13 CA CERTIFICATE DATE 25022025 Dec24compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 12) DISCLOUSURE OF SOLD & UNSOLD ( 01-10-2024 TO 31-12-2024 ) Q3_compressed.pdf | 24 Jul 2025 |
| Form 1File: 15) ARCHITECT CERTIFICATE WING D DATE 31-03-2025.pdf | 24 Jul 2025 |
| Form 2File: 15) ENGINEER CRTIFICATE DATE 31032025.pdf | 24 Jul 2025 |
| Form 3File: 14 CA CERTIFICATE DATE (31 03 2025compressed.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 13) DISCLOUSURE OF SOLD & UNSOLD ( 01-01-2025 TO 31-03-2025 ) Q4_compressed.pdf | 24 Jul 2025 |
| Form 1File: 1) ARCHITECT CERTIFICATE WING D DATE 31-03-22.pdf | 23 Jul 2025 |
| Form 2File: 1) ENG CERTIFICATE 17-05-2022 (31-03-22).pdf | 23 Jul 2025 |
| Form 3File: 1 CA CERTIFICATE DATE 23-02-2022_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 1) DISCLOUSURE OF SOLD & UNSOLD ( 01-01-2022 TO 31-03-2022 ) Q4_compressed.pdf | 23 Jul 2025 |
| Form 1File: 2) ARCHITECT CERTIFICATE WING D DATE 30-06-22.pdf | 23 Jul 2025 |
| Form 2File: 2) ENGINEET CRTIFICATE DATE 30-06-2022.pdf | 23 Jul 2025 |
| Form 3File: 3 CA CERTIFICATE DATE 30-06-2022_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 2) DISCLOUSURE OF SOLD & UNSOLD ( 01-04-2022 TO 30-06-2022 ) Q1_compressed.pdf | 23 Jul 2025 |
| Form 1File: 3) ARCHITECT CERTIFICATE WING D DATE 30-09-22.pdf | 23 Jul 2025 |
| Form 2File: 4)ENGINEET CRTIFICATE DATE - 30-09-2022.pdf | 23 Jul 2025 |
| Form 3File: 4 CA CERTIFICATE DATE 30-09-2022_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 3) DISCLOUSURE OF SOLD & UNSOLD ( 01-07-2022 TO 30-09-2022 ) Q2_compressed.pdf | 23 Jul 2025 |
| Form 1File: 4) ARCHITECT CERTIFICATE WING D DATE 01-12-2022.pdf | 23 Jul 2025 |
| Form 2File: 5) ENGINEET CRTIFICATE DATE 05-12-2022 (31-12-22).pdf | 23 Jul 2025 |
| Form 3File: 5 CA CERTIFICATE DATE 31-12-2022_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 4) DISCLOUSURE OF SOLD & UNSOLD ( 01-10-2022 TO 31-12-2022 ) Q3_compressed.pdf | 23 Jul 2025 |
| Form 1File: 5) ARCHITECT CERTIFICATE WING D DATE 20-01-2023.pdf | 23 Jul 2025 |
| Form 2File: 5) ENGINEET CRTIFICATE DATE 24-01-2023.pdf | 23 Jul 2025 |
| Form 3File: 6 CA CERTIFICATE DATE 31-03-2023_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 5) DISCLOUSURE OF SOLD & UNSOLD ( 01-01-2023 TO 31-03-2023 ) Q4_compressed.pdf | 23 Jul 2025 |
| Form 1File: 7) ARCHITECT CERTIFICATE WING D DATE 01-06-2023.pdf | 23 Jul 2025 |
| Form 2File: 7) ENGINEET CRTIFICATE DATE 29-07-2023 (30-06-23).pdf | 23 Jul 2025 |
| Form 3File: 7 CA CERTIFICATE DATE 31-06-2023_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 6) DISCLOUSURE OF SOLD & UNSOLD ( 01-04-2023 TO 30-06-2023 ) Q1_compressed.pdf | 23 Jul 2025 |
| Form 1File: 9) ARCHITECT CERTIFICATE WING D DATE 26-09-2023.pdf | 23 Jul 2025 |
| Form 2File: 8) ENGINEET CRTIFICATE DATE (30-09-23).pdf | 23 Jul 2025 |
| Form 3File: 8 CA CERTIFICATE DATE 30-09-2023_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 7) DISCLOUSURE OF SOLD & UNSOLD ( 01-07-2023 TO 30-09-2023 ) Q2_compressed.pdf | 23 Jul 2025 |
| Form 1File: 10) ARCHITECT CERTIFICATE WING D DATE 31-12-2023.pdf | 23 Jul 2025 |
| Form 2File: 9) ENGINEET CRTIFICATE DATE - 31-12-2023.pdf | 23 Jul 2025 |
| Form 3File: 9 CA CERTIFICATE DATE 31-12-2023_compressed.pdf | 23 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: 8) DISCLOUSURE OF SOLD & UNSOLD ( 01-10-2023 TO 31-12-2023 ) Q3_compressed.pdf | 23 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15) ARCHITECT CERTIFICATE WING D DATE 31-03-2025.pdf | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 15) ENGINEET CRTIFICATE-31032025.pdf | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F-3 1.pdf | 22 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14) ARCHITECT CERTIFICATE WINGD DATE 31-12-2024.pdf | 16 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F-1.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F-3.pdf | 13 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F-2.pdf | 13 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 31.pdf | 13 Jan 2025 |
| Layout approvalFile: 1_compressed.pdf | 10 Jan 2025 |
| Copy of Layout Approval (in case of layout)File: 1_compressed.pdf | 10 Jan 2025 |
| Declaration in FORM BFile: Form B 09-01-2025.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD -Discolsure 30-09-2024.pdf | 10 Jan 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 164 filed documents as one ZIP, foldered, with a manifest
Keep Nexus Kinaara D on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chikhali13,700+ in Pune
Filed coordinates, straight-line distance. 154 registered projects within 2 km.
Aishwaryam Anand
Sai Essen Developers
AISHWARYAM HAMARA ABHIMAAN
SAI ESSEN DEVELOPERS
AISHWARYAM HAMARA GAURAV
SAI ESSEN DEVELOPERS
VAASTU DREAMS III
SAI ESSEN 7 AND 8 LLP
AISHWARYAM COURTYARD GOLD
SAI ESSEN PROPERTIES
GANESH PARADISE PHASE 2
EKDANTA NEST LLP
Builder: Nexus Enterprises
Nexus Enterprises has 3 registrations on MahaRERA, including Nexus Kinaara B C and Nexus Kinaara D. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Nexus Kinaara D is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Nexus Kinaara D?
The registered promoter entity is Nexus Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Nexus Kinaara D?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Nexus Kinaara D?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Nexus Kinaara D?
The professionals named in the filing: Architect: Mahendra Thakur and Associates; Architect: Dream Space Architect; Engineer: Ajinkya A Lahigude; Chartered Accountant: Shubham S Bora; Chartered Accountant: Mohamadyasir A Bagwan; Chartered Accountant: DHIRAJ MANOJ BALDOTA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nexus Kinaara D?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.