Completed No litigation declared Others project

Nexus Carnation

By Nexus Infrawell

RG-MH-83985 · RERA P52100048682 · Last updated on MahaRERA portal: 29 Dec 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 20 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2026Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
39 of 49Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

Nexus Carnation is a Others project by Nexus Infrawell in Pune, Maharashtra, registered with MahaRERA as P52100048682 on 12 Jan 2023. The registration is recorded completed; possession was promised by 28 Feb 2026. The completion date has moved by 20 months from the original filing. 10 of the 49 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameNexus Carnation
  • TypeOthers
  • Location
    • Opp Athavan Hotel Kalewadi Main Road
    • Kalewadi
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • RERA no.P52100048682
  • ReraGenie IDRG-MH-83985

Builder

  • NameNexus Infrawell
  • Entity typePartnership
  • PartnersSatishkumar Ravjibhai Patel, Ravi Sunder Khemani, Jaiminkumar Arvindbhai Patel, Jayraj Dudharam Choudhary, Jigneshkumar Jethalal Makani

Key dates

this monthRegisteredJan 2023First promiseJun 2024Revised toFeb 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on12 Jan 2023
  • Promised completion28 Feb 2026
  • Revised completionRevised to 28 Feb 2026 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed131 files

Current status

20%10 of 49 units booked
86.4%Work done, per cost certificate

Figures as on 29 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WingNA8722426
A WingNA8702323

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

B Wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A Wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed104

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots104
Closed/Covered104
BuildingClosed/CoveredTotal
B Wing5252
A Wing5252

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,250 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Oct 2025
LandownerVillageDistrict
Mohit Developers and ConstructionPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI3394.0
Proposed, not sanctioned3,353 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchIndryani Nagar Bhosari Pune
Estimated costRs 9.23 cr
Cost incurredRs 7.98 cr
Work done86.41%
BuildingWingEstimatedIncurred
B WingNARs 4.30 crRs 3.99 cr
A WingNARs 4.30 crRs 3.99 cr
-NARs 62.29 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKalprachana Associates
EngineerAjinkya A Lahigude
EngineerBipin Parshotambhai Parasiya
Chartered AccountantGANESH SUNIL MANDLECHA
Chartered AccountantDHIRAJ BALDOTA
Chartered AccountantSHUBHAM S BORA
PartnerRole in project
Nexus Infrawell-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018819Jun 2024 → Jun 2025

Reason as filed by the promoterdue to technical and financial issues there is a delay in completing the project and obtaining completion certificate in the given time.

EA15102518121Jun 2024 → Feb 2026

Reason as filed by the promoterWe are applying for a project extension as we have already applied for the Occupancy Certificate (OC) with the Corporation, and the process is expected to take some time. Therefore, we request that the project be extended up to 28/02/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Nov 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Completion Certificate Date - 29-09-2025.pdf29 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf8 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf8 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf8 Dec 2025
Layout approvalFile: 1.pdf5 Nov 2025
Building plan approvalFile: 1.pdf5 Nov 2025
Building plan approvalFile: 2.pdf5 Nov 2025
Building plan approvalFile: 3.pdf5 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf5 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf5 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf5 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A - Nexus Carnation.pdf15 Oct 2025
Form 2A (FY 2022-2023)File: Form 2A - Nexus Carnation.pdf15 Oct 2025
Form 2A (FY 2023-2024)File: Form 2A - Nexus Carnation.pdf15 Oct 2025
Form 5 (FY 2023-2024)File: Form 5 - FY 2023-24.pdf15 Oct 2025
Form 5 (FY 2022-2023)File: FORM-5 Nexus Infrawell Date 23-12-2023.pdf23 Aug 2025
Form 1File: 2 ARCH CERTI DATE 31032023.pdf20 Aug 2025
Form 2File: 2) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-31-03-2023.pdf20 Aug 2025
Form 3File: 2) NEXUS INFRAWELL CA CERTIFICATE DATE 31-03-2023.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 1 SOLD UNSOLD NEXUS INFRAWELL (1-1-2023 to 31-03-2023) QTR-4_compressed.pdf20 Aug 2025
Form 1File: 3 ARCH CERTI DATE 31-06-2023.pdf20 Aug 2025
Form 2File: 3) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-02-06-2023.pdf20 Aug 2025
Form 3File: 3) NEXUS INFRAWELL CA CERTIFICATE DATE - 30-06-2023.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 2 SOLD UNSOLD NEXUS INFRAWELL (1-4-2023 to 30-06-2023) QTR-1.pdf20 Aug 2025
Form 1File: 4 ARCH CERTI DATE 25-9-2023.pdf20 Aug 2025
Form 2File: 4) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 25-09-2023.pdf20 Aug 2025
Form 3File: 4) NEXUS INFRAWELL CA CERTIFICATE DATE - 30-09-2023.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 3 SOLD UNSOLD NEXUS INFRAWELL (1-7-2023 to 30-09-2023) QTR-2.pdf20 Aug 2025
Form 1File: 5 ARCH CERTI DATE 31-12-2023 New.pdf20 Aug 2025
Form 2File: 5) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-12-2023.pdf20 Aug 2025
Form 3File: 5) NEXUS INFRAWELL CA CERTIFICATE DATE - 31-12-2023.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 SOLD UNSOLD NEXUS INFRAWELL (1-10-2023 to 31-12-2023) QTR-3.pdf20 Aug 2025
Form 1File: 6 ARCH CERTI DATE 31-03-2024.pdf20 Aug 2025
Form 2File: 6) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-03-2024.pdf20 Aug 2025
Form 3File: 6) NEXUS INFRAWELL CA CERTIFICATE DATE -31-03-2024.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 5 SOLD UNSOLD NEXUS INFRAWELL (1-1-2024 to 31-3-2024) QTR-4.pdf20 Aug 2025
Form 1File: 7 ARCH CERTI DATE 30-06-2024.pdf20 Aug 2025
Form 2File: 7) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2024.pdf20 Aug 2025
Form 3File: 7) NEXUS INFRAWELL CA CERTIFICATE DATE -31-06-2024.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 6 SOLD UNSOLD NEXUS INFRAWELL (1-4-2024 to 30-6-2024) QTR-1.pdf20 Aug 2025
Form 1File: 8 ARCH CERTI DATE 30-09-2024.pdf20 Aug 2025
Form 2File: 8) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-09-2024.pdf20 Aug 2025
Form 3File: 8) NEXUS INFRAWELL CA CERTIFICATE DATE -30-09-2024.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 7 SOLD UNSOLD NEXUS INFRAWELL (1-7-2024 to 30-9-2024) QTR-2.pdf20 Aug 2025
Form 1File: 9 ARCH CERTI DATE 31-12-2024.pdf20 Aug 2025
Form 2File: 9) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-12-2024.pdf20 Aug 2025
Form 3File: 9) NEXUS INFRAWELL CA CERTIFICATE DATE -31-12-2024.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 8 SOLD UNSOLD NEXUS INFRAWELL (1-10-2024 to 31-12-2024) QTR-3.pdf20 Aug 2025
Form 1File: 10 ARCH CERTI DATE 31-03-2025.pdf20 Aug 2025
Form 2File: 10) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-03-2025.pdf20 Aug 2025
Form 3File: 10) NEXUS INFRAWELL CA CERTIFICATE DATE - 04-04-2025 (MARCH -25)_compressed.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 9 SOLD UNSOLD NEXUS INFRAWELL (1-1-2025 to 31-3-2025) QTR-4.pdf20 Aug 2025
Form 1File: 11 ARCH CERTI DATE 30-06-2025.pdf20 Aug 2025
Form 2File: 11) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2025.pdf20 Aug 2025
Form 3File: 11) NEXUS INFRAWELL CA CERTIFICATE DATE - 11-07-2025 (JUNE -25)_compressed.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 10 SOLD UNSOLD NEXUS INFRAWELL (1-4-2025 to 30-6-2025) QTR-1.pdf20 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 ARCH CERTI DATE 31-03-2025.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 ARCH CERTI DATE 31-03-2025.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9) NEXUS INFRAWELL CA CERTIFICATE DATE -31-12-2024_compressed.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7) NEXUS INFRAWELL CA CERTIFICATE DATE -31-06-2024_compressed.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8) NEXUS INFRAWELL CA CERTIFICATE DATE -30-09-2024_compressed.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-12-2024.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 ARCH CERTI DATE 31-12-2024.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6) NEXUS INFRAWELL CA CERTIFICATE DATE -31-03-2024.pdf1 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-09-2024.pdf1 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 ARCH CERTI DATE 30-09-2024.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2024.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-31-03-2023.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 25-09-2023.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 ARCH CERTI DATE 30-09-2024.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-31-03-2023.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 25-09-2023.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2024.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 ARCH CERTI DATE 31-03-2024.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 ARCH CERTI DATE 30-06-2024.pdf12 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nexus Infrawell Form - 5 Date - 09-07-2024.pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-03-2024.pdf27 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A.pdf10 Apr 2024
Disclosure of sold/ booked inventoryFile: Inventory.pdf10 Apr 2024
Declaration in FORM BFile: FORM B_0001.pdf18 Mar 2024

How this compares with Pune

20%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 20 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nexus Carnation on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kalewadi13,700+ in Pune

Builder: Nexus Infrawell

Nexus Infrawell has 1 registration on MahaRERA, including Nexus Carnation. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Nexus Carnation is delayed beyond 28 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nexus Carnation?

The registered promoter entity is Nexus Infrawell, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nexus Carnation?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nexus Carnation?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nexus Carnation?

The professionals named in the filing: Architect: Kalprachana Associates; Engineer: Ajinkya A Lahigude; Engineer: Bipin Parshotambhai Parasiya; Chartered Accountant: GANESH SUNIL MANDLECHA; Chartered Accountant: DHIRAJ BALDOTA; Chartered Accountant: SHUBHAM S BORA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nexus Carnation?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nexus Carnation. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nexus Carnation to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.