Home / Browse projects / Pune, Maharashtra / Nexus Carnation
Nexus Carnation
RG-MH-83985 · RERA P52100048682 · Last updated on MahaRERA portal: 29 Dec 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 20 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Nexus Carnation is a Others project by Nexus Infrawell in Pune, Maharashtra, registered with MahaRERA as P52100048682 on 12 Jan 2023. The registration is recorded completed; possession was promised by 28 Feb 2026. The completion date has moved by 20 months from the original filing. 10 of the 49 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.
At a glance
Project
- NameNexus Carnation
- TypeOthers
- Location
- Opp Athavan Hotel Kalewadi Main Road
- Kalewadi
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411017
- Pincode411017
- RERA no.P52100048682
- ReraGenie IDRG-MH-83985
Builder
- NameNexus Infrawell
- Entity typePartnership
- PartnersSatishkumar Ravjibhai Patel, Ravi Sunder Khemani, Jaiminkumar Arvindbhai Patel, Jayraj Dudharam Choudhary, Jigneshkumar Jethalal Makani
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on12 Jan 2023
- Promised completion28 Feb 2026
- Revised completionRevised to 28 Feb 2026 (originally 30 Jun 2024)
- Buildings2 building records
- Documents filed131 files
Current status
Figures as on 29 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B Wing | NA | 8 | 7 | 22 | 4 | 26 |
| A Wing | NA | 8 | 7 | 0 | 23 | 23 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 29 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
B Wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A Wing82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 29 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed104
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| B Wing | 52 | 52 |
| A Wing | 52 | 52 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Mohit Developers and Construction | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| B Wing | NA | Rs 4.30 cr | Rs 3.99 cr |
| A Wing | NA | Rs 4.30 cr | Rs 3.99 cr |
| - | NA | Rs 62.29 lakh | - |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kalprachana Associates |
| Engineer | Ajinkya A Lahigude |
| Engineer | Bipin Parshotambhai Parasiya |
| Chartered Accountant | GANESH SUNIL MANDLECHA |
| Chartered Accountant | DHIRAJ BALDOTA |
| Chartered Accountant | SHUBHAM S BORA |
| Partner | Role in project |
|---|---|
| Nexus Infrawell | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterdue to technical and financial issues there is a delay in completing the project and obtaining completion certificate in the given time.
Reason as filed by the promoterWe are applying for a project extension as we have already applied for the Occupancy Certificate (OC) with the Corporation, and the process is expected to take some time. Therefore, we request that the project be extended up to 28/02/2026.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Nov 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Nov 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed131
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Completion Certificate Date - 29-09-2025.pdf | 29 Dec 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 8 Dec 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 8 Dec 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 8 Dec 2025 |
| Layout approvalFile: 1.pdf | 5 Nov 2025 |
| Building plan approvalFile: 1.pdf | 5 Nov 2025 |
| Building plan approvalFile: 2.pdf | 5 Nov 2025 |
| Building plan approvalFile: 3.pdf | 5 Nov 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 5 Nov 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 5 Nov 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 5 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Nexus Carnation.pdf | 15 Oct 2025 |
| Form 2A (FY 2022-2023)File: Form 2A - Nexus Carnation.pdf | 15 Oct 2025 |
| Form 2A (FY 2023-2024)File: Form 2A - Nexus Carnation.pdf | 15 Oct 2025 |
| Form 5 (FY 2023-2024)File: Form 5 - FY 2023-24.pdf | 15 Oct 2025 |
| Form 5 (FY 2022-2023)File: FORM-5 Nexus Infrawell Date 23-12-2023.pdf | 23 Aug 2025 |
| Form 1File: 2 ARCH CERTI DATE 31032023.pdf | 20 Aug 2025 |
| Form 2File: 2) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-31-03-2023.pdf | 20 Aug 2025 |
| Form 3File: 2) NEXUS INFRAWELL CA CERTIFICATE DATE 31-03-2023.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 SOLD UNSOLD NEXUS INFRAWELL (1-1-2023 to 31-03-2023) QTR-4_compressed.pdf | 20 Aug 2025 |
| Form 1File: 3 ARCH CERTI DATE 31-06-2023.pdf | 20 Aug 2025 |
| Form 2File: 3) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-02-06-2023.pdf | 20 Aug 2025 |
| Form 3File: 3) NEXUS INFRAWELL CA CERTIFICATE DATE - 30-06-2023.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 2 SOLD UNSOLD NEXUS INFRAWELL (1-4-2023 to 30-06-2023) QTR-1.pdf | 20 Aug 2025 |
| Form 1File: 4 ARCH CERTI DATE 25-9-2023.pdf | 20 Aug 2025 |
| Form 2File: 4) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 25-09-2023.pdf | 20 Aug 2025 |
| Form 3File: 4) NEXUS INFRAWELL CA CERTIFICATE DATE - 30-09-2023.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 SOLD UNSOLD NEXUS INFRAWELL (1-7-2023 to 30-09-2023) QTR-2.pdf | 20 Aug 2025 |
| Form 1File: 5 ARCH CERTI DATE 31-12-2023 New.pdf | 20 Aug 2025 |
| Form 2File: 5) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-12-2023.pdf | 20 Aug 2025 |
| Form 3File: 5) NEXUS INFRAWELL CA CERTIFICATE DATE - 31-12-2023.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 4 SOLD UNSOLD NEXUS INFRAWELL (1-10-2023 to 31-12-2023) QTR-3.pdf | 20 Aug 2025 |
| Form 1File: 6 ARCH CERTI DATE 31-03-2024.pdf | 20 Aug 2025 |
| Form 2File: 6) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-03-2024.pdf | 20 Aug 2025 |
| Form 3File: 6) NEXUS INFRAWELL CA CERTIFICATE DATE -31-03-2024.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 5 SOLD UNSOLD NEXUS INFRAWELL (1-1-2024 to 31-3-2024) QTR-4.pdf | 20 Aug 2025 |
| Form 1File: 7 ARCH CERTI DATE 30-06-2024.pdf | 20 Aug 2025 |
| Form 2File: 7) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2024.pdf | 20 Aug 2025 |
| Form 3File: 7) NEXUS INFRAWELL CA CERTIFICATE DATE -31-06-2024.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 SOLD UNSOLD NEXUS INFRAWELL (1-4-2024 to 30-6-2024) QTR-1.pdf | 20 Aug 2025 |
| Form 1File: 8 ARCH CERTI DATE 30-09-2024.pdf | 20 Aug 2025 |
| Form 2File: 8) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-09-2024.pdf | 20 Aug 2025 |
| Form 3File: 8) NEXUS INFRAWELL CA CERTIFICATE DATE -30-09-2024.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 SOLD UNSOLD NEXUS INFRAWELL (1-7-2024 to 30-9-2024) QTR-2.pdf | 20 Aug 2025 |
| Form 1File: 9 ARCH CERTI DATE 31-12-2024.pdf | 20 Aug 2025 |
| Form 2File: 9) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-12-2024.pdf | 20 Aug 2025 |
| Form 3File: 9) NEXUS INFRAWELL CA CERTIFICATE DATE -31-12-2024.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 SOLD UNSOLD NEXUS INFRAWELL (1-10-2024 to 31-12-2024) QTR-3.pdf | 20 Aug 2025 |
| Form 1File: 10 ARCH CERTI DATE 31-03-2025.pdf | 20 Aug 2025 |
| Form 2File: 10) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-03-2025.pdf | 20 Aug 2025 |
| Form 3File: 10) NEXUS INFRAWELL CA CERTIFICATE DATE - 04-04-2025 (MARCH -25)_compressed.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 SOLD UNSOLD NEXUS INFRAWELL (1-1-2025 to 31-3-2025) QTR-4.pdf | 20 Aug 2025 |
| Form 1File: 11 ARCH CERTI DATE 30-06-2025.pdf | 20 Aug 2025 |
| Form 2File: 11) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2025.pdf | 20 Aug 2025 |
| Form 3File: 11) NEXUS INFRAWELL CA CERTIFICATE DATE - 11-07-2025 (JUNE -25)_compressed.pdf | 20 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 SOLD UNSOLD NEXUS INFRAWELL (1-4-2025 to 30-6-2025) QTR-1.pdf | 20 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 ARCH CERTI DATE 31-03-2025.pdf | 28 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 ARCH CERTI DATE 31-03-2025.pdf | 28 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9) NEXUS INFRAWELL CA CERTIFICATE DATE -31-12-2024_compressed.pdf | 16 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7) NEXUS INFRAWELL CA CERTIFICATE DATE -31-06-2024_compressed.pdf | 13 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8) NEXUS INFRAWELL CA CERTIFICATE DATE -30-09-2024_compressed.pdf | 13 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-12-2024.pdf | 13 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 ARCH CERTI DATE 31-12-2024.pdf | 9 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6) NEXUS INFRAWELL CA CERTIFICATE DATE -31-03-2024.pdf | 1 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-09-2024.pdf | 1 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 ARCH CERTI DATE 30-09-2024.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2024.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-31-03-2023.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 25-09-2023.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 ARCH CERTI DATE 30-09-2024.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2) NEXUS INFRAWELL- ENG CERTIFICATE - DATE-31-03-2023.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 25-09-2023.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 7) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 30-06-2024.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 ARCH CERTI DATE 31-03-2024.pdf | 12 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 7 ARCH CERTI DATE 30-06-2024.pdf | 12 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nexus Infrawell Form - 5 Date - 09-07-2024.pdf | 5 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6) NEXUS INFRAWELL- ENG CERTIFICATE - DATE- 31-03-2024.pdf | 27 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A.pdf | 10 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory.pdf | 10 Apr 2024 |
| Declaration in FORM BFile: FORM B_0001.pdf | 18 Mar 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 131 filed documents as one ZIP, foldered, with a manifest
Keep Nexus Carnation on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalewadi13,700+ in Pune
VARDHAMAN SKYTOWN
VARDHAMAN ASSOCIATES
Tamara
Goldfinger Kataria Urban Developments
Sindhu Skies
G K Wonders
Legacy Kairos A and B Building
Legacy Lifespaces LLP
Amberwood Phase 1
SMP NAMRATA ASSOCIATES
121 Paradise Phase I
Wamanbhau & Daga Realtors LLP
Builder: Nexus Infrawell
Nexus Infrawell has 1 registration on MahaRERA, including Nexus Carnation. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Nexus Carnation is delayed beyond 28 Feb 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Nexus Carnation?
The registered promoter entity is Nexus Infrawell, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Nexus Carnation?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Nexus Carnation?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Nexus Carnation?
The professionals named in the filing: Architect: Kalprachana Associates; Engineer: Ajinkya A Lahigude; Engineer: Bipin Parshotambhai Parasiya; Chartered Accountant: GANESH SUNIL MANDLECHA; Chartered Accountant: DHIRAJ BALDOTA; Chartered Accountant: SHUBHAM S BORA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nexus Carnation?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback