Neuleaf Techd
By Neuleaf Lifespace Developers LLP
RG-MH-01574 · RERA P52100000181 · Last updated on MahaRERA portal: 3 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 6 complaints at MahaRERA
- Completion date moved by 144 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Neuleaf Techd is a Residential / Group Housing project by Neuleaf Lifespace Developers LLP in Pune, Maharashtra, registered with MahaRERA as P52100000181 on 10 Jul 2017. Possession is promised by 30 Jun 2033. The completion date has moved by 144 months from the original filing. 120 of the 207 units on this registration are recorded sold or booked, and 16 of 44 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameNeuleaf Techd
- TypeResidential / Group Housing
- Location
- Taluka- Mulshi
- Bhugaon
- Kothrud
- Haveli
- Pune
- 412115
- Pincode412115
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100000181
- ReraGenie IDRG-MH-01574
Builder
- NameNeuleaf Lifespace Developers LLP
- Entity typeLimited Liability Partnership
- LLPINAAY-4152
- PartnersMahendra Arun Kulkarni, Atul Ram Jethmalani, Vasim Mahamad Shaikh, BHUSHAN PRADEEP NALAWADE
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Jul 2017
- Promised completion30 Jun 2033
- Revised completionRevised to 30 Jun 2033 (originally 30 Jun 2021)
- Buildings4 building records
- Documents filed157 files
Current status
Figures as on 3 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C | NA | 17 | 14 | 112 | 0 | 112 |
| B | NA | 18 | 13 | 50 | 0 | 50 |
| A | NA | 6 | 2 | 0 | 14 | 14 |
| D | NA | 6 | 4 | 0 | 31 | 31 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 95%.
C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B55%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A5%
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 10% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 25% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed245
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| C | 148 | 0 | 148 |
| B | 67 | 0 | 67 |
| A | 11 | 0 | 11 |
| D | 9 | 10 | 19 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mohol Construction Pvt Ltd | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C | NA | Rs 27.50 cr | Rs 27.50 cr |
| B | NA | Rs 18.01 cr | Rs 14.00 cr |
| A | NA | Rs 9.68 cr | Rs 50.00 lakh |
| - | NA | Rs 9.50 cr | Rs 6.64 cr |
| D | NA | Rs 4.39 cr | Rs 1.44 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JAY AERAM & ASSOCIATES |
| Engineer | SK Consultants & Engineers |
| Engineer | Vishal Bhosale |
| Chartered Accountant | S.B. Shingte & Co. |
| Chartered Accountant | NB Sayed & Associates |
| Chartered Accountant | Amol Shamrao Deshmukh |
| Chartered Accountant | NIKHIL NANAWARE AND COMPANY |
| Partner | Role in project |
|---|---|
| Neuleaf Lifespace Developers LLP | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe reasons for extension in date of completion are as follows:- 1. The promoter was suffering through huge financial losses as there was no abundant booking done by customers. Due to such financial constrained there was slow progress as work site. 2. Further, It is a fact that there was nationwide lockdown due to Covid-19 pandemic situation. Due to such pandemic situation, promoter could not progress the work at site. 3. Due to such situation there were further financial constraints on the Promoter. There have been bookings in the said project. However, Promoter seeks extension of date of com
Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 68% allottees for purpose of extension of RERA registration period of the said project.
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000064842 | DIGAMBAR S. MORE | VIJAY JAYWANT MOHOL & MANISHA JAYWANT MOHOL | 19/11/2020 |
| CC005000000167407 | SATEJ RAGHUNATH KOTHAWADE | vijay mohol | 29/07/2022 |
| CC12400781 | Abhishek Kelkar | Mohol Construction Private Limited | 15/11/2024 |
| CC12500033 | Abhishek Kelkar | Mohol Construction Private Limited | 03/01/2025 |
| CC12503157 | ABHIJIT VISHNU SHETE | Mohol Construction Private Limited | 07/09/2025 |
| CC12503815 | Nand Kishore Baheti | Neuleaf Lifespace Developers LLP | 31/10/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Sep 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2033
Documents filed157
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 157 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 3 Aug 2026 |
| Withdrawal Update Form 1File: mcpl FORM 1 JULY.pdf | 3 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 (1).pdf | 3 Aug 2026 |
| Withdrawal Update Form 2File: mcpl JULY FORM 2.pdf | 3 Aug 2026 |
| Withdrawal Update Form 3File: form 3 (2).pdf | 3 Aug 2026 |
| Withdrawal Update Form 3File: mcpl FORM 3 JULY.pdf | 3 Aug 2026 |
| Withdrawal Update Form 1File: rera form 1_0001.pdf | 25 Feb 2026 |
| Withdrawal Update Form 1File: rera form 1_0001.pdf | 25 Feb 2026 |
| Withdrawal Update Form 2File: form 2 Dec 2025.pdf | 25 Feb 2026 |
| Withdrawal Update Form 2File: form 2 Dec 2025.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: form 3 Dec 2025.pdf | 25 Feb 2026 |
| Withdrawal Update Form 3File: form 3 Dec 2025.pdf | 25 Feb 2026 |
| Form 1File: FORM 1 ARCHITECT CERTIFICATE .pdf | 2 Feb 2026 |
| Form 2File: FORM-2_0001.pdf | 2 Feb 2026 |
| Form 3File: FORM-3_0001.pdf | 2 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Circular- 29.pdf | 2 Feb 2026 |
| OthersFile: doc04856920260202211830.pdf | 2 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5 -Neuleaf Techd FY 2024-2025.pdf | 11 Nov 2025 |
| Form 1File: Form 1 - Neuleaf Techd as on Sep 2025.pdf | 8 Nov 2025 |
| Form 2File: Form 2 - Neuleaf Techd as on Sep 2025.pdf | 8 Nov 2025 |
| Form 3File: Form 3 - Neuleaf Techd as on Sep 2025.pdf | 8 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Circular- 29 - Neuleaf Techd as on Sep 2025.pdf | 8 Nov 2025 |
| Certificates of CA (Form 3)File: Form 3 - Sept 2024.pdf | 22 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 - Dec 2024.pdf | 22 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29 Dec 2024.pdf | 22 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MCPL RERA FORM2 Q2 2024-25.pdf | 13 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MCPL RERA FORM 2 Q3 2024-25.pdf | 13 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 of Grace Land as on 30-09-2024.pdf | 11 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 of Grace Land as on 31-12-2024.pdf | 11 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 2023-24.pdf | 5 Dec 2024 |
| Certificates of CA (Form 3)File: RERA FORM 3 - CA CERTIFICATE_11zon.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - June 2024_11zon.pdf | 2 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - FY 2023-24.pdf | 2 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 11 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE (1).pdf | 11 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 6 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 6 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold and unsold inventory list 20240704164837.pdf | 6 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 6 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23.pdf | 28 May 2024 |
| Declaration about Commencement CertificateFile: DECLARATION - COMMENCEMENT.pdf | 12 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD - GRACELAND_11zon.pdf | 12 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sept 2023_11zon.pdf | 8 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2023_11zon.pdf | 8 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 2023.pdf | 8 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 2023.pdf | 8 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 Dec2023_11zon.pdf | 8 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form No 2A.pdf | 23 Jan 2024 |
| Layout approvalFile: PAGE 1_11zon.pdf | 23 Sep 2023 |
| Layout approvalFile: PAGE 2_11zon.pdf | 23 Sep 2023 |
| Layout approvalFile: PAGE 3_11zon (1).pdf | 23 Sep 2023 |
| Layout approvalFile: PAGE 3A_11zon.pdf | 23 Sep 2023 |
| Building plan approvalFile: PAGE 4_11zon.pdf | 23 Sep 2023 |
| Building plan approvalFile: PAGE 5_11zon.pdf | 23 Sep 2023 |
| Building plan approvalFile: PAGE 7_11zon.pdf | 23 Sep 2023 |
| Building plan approvalFile: PAGE 8_11zon.pdf | 23 Sep 2023 |
| Building plan approvalFile: PAGE 9_11zon.pdf | 23 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: PAGE 1_11zon.pdf | 23 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: PAGE 2_11zon.pdf | 23 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: PAGE 3_11zon (1).pdf | 23 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: PAGE 3A_11zon.pdf | 23 Sep 2023 |
| Building Plan Approval (IOD)File: PAGE 4_11zon.pdf | 23 Sep 2023 |
| Building Plan Approval (IOD)File: PAGE 5_11zon.pdf | 23 Sep 2023 |
| Building Plan Approval (IOD)File: PAGE 7_11zon.pdf | 23 Sep 2023 |
| Building Plan Approval (IOD)File: PAGE 8_11zon.pdf | 23 Sep 2023 |
| Building Plan Approval (IOD)File: PAGE 9_11zon.pdf | 23 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed_compressed.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 _ Architect's Certificate Quarter-4_2022-2023_0001.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 _ Architect's Certificate Quarter-1_2023-2024_0001.pdf | 23 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2.pdf | 23 Sep 2023 |
| Certificates of CA (Form 3)File: form 3 _ Chartedred Accountants Certificate_0001_compressed_compressed.pdf | 23 Sep 2023 |
| Declaration in FORM BFile: Affidavit _ Bhushan Nalawade RERA_0001.pdf | 5 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate 2021-2022_0001.pdf | 5 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Scan CIRCULAR 29 Grace Land_0001.pdf | 5 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2_ 31-03-2022.pdf | 2 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2_Qurter 1 _ 30-06-2022_0001.pdf | 2 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2_Qurter 2_ 30-09-2022_0001.pdf | 2 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2_Qurter 3_ 31-12-2022_0001.pdf | 2 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form No 2_Qurter 4_ 31-03-2023_0001_0001.pdf | 2 Jun 2023 |
| Certificates of CA (Form 3)File: FORM 3 - March 2022.pdf | 2 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 157 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Neuleaf Techd on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhugaon13,700+ in Pune
Filed coordinates, straight-line distance. 119 registered projects within 2 km.
Avian Valley - Solaire
KAKADE ESTATE DEVELOPERS PVT. LTD.
Park Pebbles Phase I
M/s Rainbow Purple Construction LLP
Mahindra Rivenza Phase 2
Mahindra Lifespace Developers limited
Mahindra Rivenza Phase 1
Mahindra Lifespace Developers limited
FOREST TRAILS ATHASHRI B3
LAVIM DEVELOPERS PVT LTD
KOHINOOR WOODSHIRE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: Neuleaf Lifespace Developers LLP
Neuleaf Lifespace Developers LLP has 1 registration on MahaRERA, including Neuleaf Techd. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Neuleaf Techd is delayed beyond 30 Jun 2033?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Neuleaf Techd?
The registered promoter entity is Neuleaf Lifespace Developers LLP, a limited liability partnership as per the filing. Its LLPIN AAY-4152 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Neuleaf Techd?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Neuleaf Techd?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Neuleaf Techd?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Neuleaf Techd?
The professionals named in the filing: Architect: JAY AERAM & ASSOCIATES; Engineer: SK Consultants & Engineers; Engineer: Vishal Bhosale; Chartered Accountant: S.B. Shingte & Co.; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Amol Shamrao Deshmukh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Neuleaf Techd?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback