Home / Browse projects / Mumbai Suburban, Maharashtra / NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9

Registration lapsed No litigation declared Residential / Group Housing project

NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9

By MUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD

RG-MH-61109 · RERA P51800008871 · Last updated on MahaRERA portal: 16 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 45 months past the filed date
  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2023Possession promised45 months past this date
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 90%
0Complaints at MahaRERAon this registration
Jump to the 44 documents Report an error

NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9 is a Residential / Group Housing project by MUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008871 on 19 Aug 2017. Possession was promised by 30 Jan 2023 and is now 45 months past that date. The completion date has moved by 42 months from the original filing.

At a glance

Project

  • NameNEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9
  • TypeResidential / Group Housing
  • Location
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008871
  • ReraGenie IDRG-MH-61109

Builder

  • NameMUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD
  • Entity typeCompany
  • Managing DirectorGITIKA GANESH SANE
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

45 months past promisethis monthRegisteredAug 2017First promiseJul 2019Revised toJan 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 Jan 2023
  • Revised completionRevised to 30 Jan 2023 (originally 31 Jul 2019)
  • Buildings2 building records
  • Documents filed44 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA170000
B WINGNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 16 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 90%.

A WING50%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor90%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING50%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor90%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered58
Open Space2
BuildingClosed/CoveredOpen SpaceTotal
A WING26228
B WING32032

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,656 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6049.79
Proposed, not sanctioned6,050 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOREGAON WEST MUMBAI

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectELLORA PROJECT CONSULTANS PVT LTD
EngineerELLORA CONSULTANCY SERVICES AS A RCC CONSULTANT
PartnerRole in project
MUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008985Jul 2019 → Jul 2022

Reason as filed by the promoterDate : 19/01/2021 To, Maharashtra Real Estate Regulatory Authority Maharashtra. Respected Sir, Sub : Renewal of date specified in our RERA application for project Nehru Nagar Mangal Prabhat CHS. Ltd. Building No. 9, Nehru Nagar , Kurla (E), Mumbai. Ref : RERA Regn. No. P51800008871 This has reference to our RARA registration No. P51800008871 for the project - Nehru Nagar Mangal Prabhat CHS. Ltd. , Building No. 9, at on plot bearing CTS No.12(pt), Village Kurla , Nehru Nagar , Kurla (E), Mumbai -400024 . In this regard we have to inform you that the construction work of the aforesaid proposed r

EXT51800002085Jul 2019 → Jul 2020

Reason as filed by the promoter1. The compound wall of our building No. 9 on the west side is lying within the 30 mtrs of adjacent railway line. Hence, we have to obtain NOC from Railway Authority. The Railway Authority in their NOC has restricted our FSI consumption on the 11th, 12th,13th, 14th & 15th Floor for which we have already paid premium on this FSI to the MHADA & BMC. Since, we could not utilise this FSI on upper floor, we are compelled to use this unutilised FSI on the ground floor of the building . We have to submit our file to MHADA for their approval for utilising this FSI on ground floor. We have already appl

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Oct 2022

Documents filed44

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf16 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MANGAL PRABHAT OC COPY.pdf6 Oct 2022
Layout approvalFile: 1.pdf16 Jun 2022
Layout approvalFile: 2.pdf16 Jun 2022
Building plan approvalFile: 3.pdf16 Jun 2022
Building plan approvalFile: 4.pdf16 Jun 2022
Building plan approvalFile: 1.pdf16 Jun 2022
Building plan approvalFile: 2.pdf16 Jun 2022
Building plan approvalFile: 5.pdf16 Jun 2022
Building plan approvalFile: 6.pdf16 Jun 2022
Copy of Layout Approval (in case of layout)File: 1.pdf16 Jun 2022
Copy of Layout Approval (in case of layout)File: 2.pdf16 Jun 2022
Building Plan Approval (IOD)File: 3.pdf16 Jun 2022
Building Plan Approval (IOD)File: 4.pdf16 Jun 2022
Building Plan Approval (IOD)File: 1.pdf16 Jun 2022
Building Plan Approval (IOD)File: 2.pdf16 Jun 2022
Building Plan Approval (IOD)File: 5.pdf16 Jun 2022
Building Plan Approval (IOD)File: 6.pdf16 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf16 Jun 2022
Certificates of CA (Form 5)File: RERA - FORM 5 MANGAL PRABHAT.pdf29 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2_MANGAL PRABHAT_April 2018.pdf16 Apr 2018
Layout approvalFile: 1.pdf30 Jul 2017
Building plan approvalFile: 1.pdf30 Jul 2017
Building plan approvalFile: 2.pdf30 Jul 2017
Building plan approvalFile: 3.pdf30 Jul 2017
Building plan approvalFile: 5.pdf30 Jul 2017
Building plan approvalFile: 4.pdf30 Jul 2017
Building plan approvalFile: 6.pdf30 Jul 2017
PAN CardFile: COMPANY PAN CARD.pdf30 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf30 Jul 2017
Details of encumbrancesFile: ECUMBRANCES.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: 1.pdf30 Jul 2017
Building Plan Approval (IOD)File: 1.pdf30 Jul 2017
Building Plan Approval (IOD)File: 2.pdf30 Jul 2017
Building Plan Approval (IOD)File: 3.pdf30 Jul 2017
Building Plan Approval (IOD)File: 4.pdf30 Jul 2017
Building Plan Approval (IOD)File: 5.pdf30 Jul 2017
Building Plan Approval (IOD)File: 6.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf30 Jul 2017
Declaration in FORM BFile: FORM B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ELLORA ARCH.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE.pdf30 Jul 2017
Proforma of Allotment letterFile: 2) Sale Agreement for Mangal Prabhat.pdf30 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmNEHRU NAGAR MANGAL PRABHCompleted 106Lapsed / revoked 83Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 318 registered projects within 2 km.

Builder: MUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD

MUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD has 2 registrations on MahaRERA, including NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9 and SIDDHARTH NAGAR ABHIMAN CHS LTD BUILDING NO-25. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9 is delayed beyond 30 Jan 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9?

The registered promoter entity is MUMBAI SHELTER HOUSING DEVELOPMENT PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9?

The professionals named in the filing: Architect: ELLORA PROJECT CONSULTANS PVT LTD; Engineer: ELLORA CONSULTANCY SERVICES AS A RCC CONSULTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING NO-9. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEHRU NAGAR MANGAL PRABHAT CHS LTD BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.