Home / Browse projects / Mumbai Suburban, Maharashtra / NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED
NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED
By DERAIYA REALTORS PRIVATE LIMITED
RG-MH-15796 · RERA P51800023015 · Last updated on MahaRERA portal: 17 Feb 2025
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED is a Others project by DERAIYA REALTORS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800023015 on 14 Nov 2019. The registration is recorded completed; possession was promised by 30 Dec 2025. 1 complaint is on record with the regulator.
At a glance
Project
- NameNEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED
- TypeOthers
- Location
- S. G. BARVE MARG
- NEHRU NAGAR
- Kurla
- Mumbai Suburban
- 400024
- Pincode400024
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800023015
- ReraGenie IDRG-MH-15796
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on14 Nov 2019
- Promised completion30 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed54 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DERAIYA ICONICO A AND B WING | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
DERAIYA ICONICO A AND B WING: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed84
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SPACE MOULDERS |
| Engineer | SIHAVAT CONSULTANCY SERVICES |
| Chartered Accountant | Afzal N Patel & Co |
| Chartered Accountant | R A N K & Associates |
| Partner | Role in project |
|---|---|
| DERAIYA REALTORS PRIVATE LIMITED | - |
Litigation declared9
| Case | Court | Status |
|---|---|---|
| 2714/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2715/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2726/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2727/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2728/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2932/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2933/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 2934/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
| 3143/2019 | In The Bombay City Civil Court at Mumbai | Suit has been disposed |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12501196 | DERAIYA REALTORS PRIVATE LIMITED | MR ABHIJIT RAMESH KEKANE | 10/04/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Apr 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Jan 2025
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Guruprasad Sold and Unsold 31-10-24.pdf | 17 Feb 2025 |
| Other - TechnicalFile: Form 4 Guruprasad Nehru Nagar.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Guruprasad_Form 3.pdf | 13 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2- ENG CERT-Guruprasad-RERA-June 2024_V3.pdf | 13 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_Guruprasad_FY 19-20.pdf | 13 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_Guruprasad_FY 20-21.pdf | 13 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Guruprasad_FY 21-22.pdf | 13 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Guruprasad_FY 22-23.pdf | 13 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Guruprasad_FY 23-24.pdf | 13 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 19-07-2024.pdf | 10 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A_2019-20.pdf | 10 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_2021-22.pdf | 10 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A_2022-23.pdf | 10 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_2023-24.pdf | 10 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Guruprasad Nehru Nagar.pdf | 18 Jan 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf | 18 Jan 2025 |
| Status of ConveyanceFile: Conveyance Deed - Neharu Nagar Guruprasad CHS LTD.pdf | 18 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full Occupation Certificate Guruprasad CHSL.pdf | 18 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Approved FCC.pdf | 8 Mar 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: F2 FCC 18th floor.pdf | 8 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate Dec 22.pdf | 24 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Form 1 Architect Certificate.pdf | 7 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate (2).pdf | 23 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 18 Jul 2022 |
| Proforma of Allotment letterFile: 40 - Draft Agreement.pdf | 28 Apr 2022 |
| Details of encumbrancesFile: Encumbrance On Project.pdf | 14 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: FURTHER CC.pdf | 3 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Jul-Sep 2021.pdf | 3 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Oct-Dec 2021.pdf | 3 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 15 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf | 14 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Apr-Jun 2021.pdf | 14 Aug 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Jun 2021.pdf | 14 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certifcate Apr Jun 2021.pdf | 14 Aug 2021 |
| Building plan approvalFile: Amended IOA.pdf | 30 Apr 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended IOA.pdf | 30 Apr 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC 11-02-2021.pdf | 12 Mar 2021 |
| Building plan approvalFile: IOA.pdf | 5 Nov 2019 |
| Layout approvalFile: Ground Floor.pdf | 5 Nov 2019 |
| Layout approvalFile: First Floor.pdf | 5 Nov 2019 |
| Layout approvalFile: Typical Floor.pdf | 5 Nov 2019 |
| Layout approvalFile: 10th Floor.pdf | 5 Nov 2019 |
| PAN CardFile: 40 DRPL Pan.pdf | 5 Nov 2019 |
| Copy of the legal title reportFile: Legal Title Certificate.pdf | 5 Nov 2019 |
| Details of encumbrancesFile: NON- ENCUMBRANCE CERTIFICATE.pdf | 5 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: Ground Floor.pdf | 5 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: First Floor.pdf | 5 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: Typical Floor.pdf | 5 Nov 2019 |
| Copy of Layout Approval (in case of layout)File: 10th Floor.pdf | 5 Nov 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf | 5 Nov 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: 40 PLINTH CC.pdf | 5 Nov 2019 |
| Declaration in FORM BFile: FORM B AFFIDAVIT CUM DECLARATION.pdf | 5 Nov 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 5 Nov 2019 |
| Proforma of Allotment letterFile: Allotment Letter and Agreement for Sale.pdf | 5 Nov 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
Keep NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEHRU NAGAR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 357 registered projects within 2 km.
Ruparel Urbana
R R Builders
SKYVIEW CHS
HIRANIMANTHAN BUILDERS AND DEVELOPERS
Ruparel Crest
BHARAT MAHAN DEVELOPERS & BUILDERS
Kurla Vijay Rahivashi Sangh Co-op. Hsg.Soc.Ltd
VIKAS NARAYAN RAIKAR
Pearl Grace
Pearl Concept Habitat LLP
SAYBA CRYSTAL
AMOOL ENTERPRISES
See every Mumbai Suburban project, with the district possession charts
Builder: DERAIYA REALTORS PRIVATE LIMITED
DERAIYA REALTORS PRIVATE LIMITED has 2 registrations on MahaRERA, including NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED and Nehru Nagar Nirmal C.H.S. Ltd.. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED?
The registered promoter entity is DERAIYA REALTORS PRIVATE LIMITED, a company as per the filing. Its CIN U70102MH2011PTC213094 and GSTIN 27AADCD7365D1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED?
The professionals named in the filing: Architect: SPACE MOULDERS; Engineer: SIHAVAT CONSULTANCY SERVICES; Chartered Accountant: Afzal N Patel & Co; Chartered Accountant: R A N K & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback