Home / Browse projects / Mumbai Suburban, Maharashtra / Navnath Jayas
Navnath Jayas
By Navnath Infrastructures Private Limited
RG-MH-05845 · RERA P51800051536 · Last updated on MahaRERA portal: 18 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Navnath Jayas is a Residential / Group Housing project by Navnath Infrastructures Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800051536 on 23 Jun 2023. Possession is promised by 31 Dec 2027. 61 of the 129 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.
At a glance
Project
- NameNavnath Jayas
- TypeResidential / Group Housing
- Location
- Jayprakash Nagar Road No. 5
- Goregaon East
- Pahadi-Goregaon
- Borivali
- Mumbai Suburban
- 400063
- Pincode400063
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800051536
- ReraGenie IDRG-MH-05845
Builder
- NameNavnath Infrastructures Private Limited
- Entity typeCompany
- DirectorsNeelam Vaibhav Joshi, Shardool Vaibhav Joshi
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Jun 2023
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings2 building records
- Documents filed87 files
Current status
Figures as on 18 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Navnath Jayas - A Wing | NA | 18 | 17 | 63 | 0 | 63 |
| Navnath Jayas - B Wing | NA | 18 | 17 | 66 | 0 | 66 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.
Navnath Jayas - A Wing59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Navnath Jayas - B Wing59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 20% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed142
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Navnath Jayas - A Wing | 71 | 71 |
| Navnath Jayas - B Wing | 71 | 71 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Navnath Jayas - A Wing | NA | Rs 13.50 cr | Rs 11.54 cr |
| Navnath Jayas - B Wing | NA | Rs 13.50 cr | Rs 11.54 cr |
| - | NA | Rs 3.00 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tangent Architects and Interior Designers |
| Engineer | R C Tipnis |
| Chartered Accountant | Ms Gaurav S Rajpal and CO |
| Chartered Accountant | ANKS & CO Chartered Accountants |
| Chartered Accountant | A N K S & Co. |
| Partner | Role in project |
|---|---|
| Navnath Infrastructures Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Jan 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Mar 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 May 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Jayas Form 1.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Jayas Form 2.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Navnath Jayas Form 3 Q4 of FY 25-26 Signed.pdf | 18 Apr 2026 |
| Building plan approvalFile: Building plan Page 1-4_V2.pdf | 30 Mar 2026 |
| Building plan approvalFile: page 1-4.pdf | 12 Feb 2026 |
| Building plan approvalFile: Page 5-8.pdf | 12 Feb 2026 |
| Building plan approvalFile: Page 9-13.pdf | 12 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Q3 FY 25-26.pdf | 20 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Q3 FY 25-26.pdf | 20 Jan 2026 |
| Withdrawal Update Form 3File: Navnath Jayas Form 3 Q3 of FY 25-26 _signed.pdf | 20 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 Jayas.pdf | 20 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 Jayas.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Jayas.pdf | 20 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Jayas.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: Jayas Form 3 Signed.pdf | 20 Oct 2025 |
| Withdrawal Update Form 3File: Jayas Form 3 final Signed.pdf | 20 Oct 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 - JAYAS Signed.pdf | 29 Sep 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Jul 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Jul 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Jayas Form 3 -Signed.pdf | 18 Jul 2025 |
| Withdrawal Update Form 3File: Jayas Form 3 -Signed.pdf | 18 Jul 2025 |
| Form 2A (FY 2024-2025)File: NAVNATH INFRASTRUCTURES PVT.LTD. JAYAS 2024-25.pdf | 26 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Navnath Jayas.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed_Form-3_Navnath Jayas.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Navnath Jayas.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Navnath Jayas_Signed.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1_17_10_2024.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Signed.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 20 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 9 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A NIPL 23-24.pdf | 25 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Jayas_Signed.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1_06_07_2024.pdf | 19 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 19 Jul 2024 |
| Details of encumbrances concerned to FinanceFile: 20240322143605.pdf | 5 Jul 2024 |
| Details of encumbrances concerned to LegalFile: 20240322143605.pdf | 5 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_Jayas_Q4 FY 23-24.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Jayas Form 3_Q4_Signed.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 NIPL Jayas tipnis FY 23-24 Q4.pdf | 18 Apr 2024 |
| Other - FinanceFile: Project Finance Certificate.pdf | 28 Mar 2024 |
| Layout approvalFile: Updated Layout Approval.pdf | 20 Jan 2024 |
| Building plan approvalFile: Jayas 1_11zon.pdf | 20 Jan 2024 |
| Building plan approvalFile: Jayas 1 1-8 FLOORS.pdf | 20 Jan 2024 |
| Building plan approvalFile: Jayas 3 14-17 FLOORS.pdf | 20 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: Updated Layout Approval.pdf | 20 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Jayas 1_11zon.pdf | 20 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Jayas 1 1-8 FLOORS.pdf | 20 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Jayas 3 14-17 FLOORS.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 19 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Signed.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 signed.pdf | 3 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 30 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate for Jayas.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer CErtificate jayas.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Format Form 3 of Navnath Jayas as on 30th June 2023.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed First Form 3 of Navnath Jayas.pdf | 9 Jun 2023 |
| Other - TechnicalFile: 3 Building Plan Approval _ NA Order for plotted development (6)-2.pdf | 9 Jun 2023 |
| Proforma of Agreement for saleFile: AFS_Navnath Jayas_Navnath Infrastructures_09052023 (1).pdf | 18 May 2023 |
| Proforma of Allotment letterFile: Allotment Letter_Navnath Jayas_Navnath Infrastructures_09052023 (1).pdf | 18 May 2023 |
| CERSAI detailsFile: Cersai declaration Jayas.pdf | 17 May 2023 |
| Declaration about Commencement CertificateFile: FORMAT D - 2 Wings (Rev).pdf | 16 May 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Report of Allotment Letter_Navnath Jayas(Rev).pdf | 16 May 2023 |
| Layout approvalFile: Plan Navnath Jayas_1-1_11zon.pdf | 11 May 2023 |
| Building plan approvalFile: Plan Navnath Jayas_8-end_11zon (1).pdf | 11 May 2023 |
| Building plan approvalFile: Plan Navnath Jayas_2-4_11zon (1).pdf | 11 May 2023 |
| Building plan approvalFile: Plan Navnath Jayas_5-7_11zon.pdf | 11 May 2023 |
| PAN CardFile: Pan Card NIPL.pdf | 11 May 2023 |
| Copy of the legal title reportFile: Title-Navnath Jayas.pdf | 11 May 2023 |
| Details of encumbrances concerned to FinanceFile: No ENCUMBRANCE LETTER -Dues.pdf | 11 May 2023 |
| Details of encumbrances concerned to FinanceFile: No ENCUMBRANCE LETTER Litigations.pdf | 11 May 2023 |
| Details of encumbrances concerned to LegalFile: No ENCUMBRANCE LETTER -Dues.pdf | 11 May 2023 |
| Details of encumbrances concerned to LegalFile: No ENCUMBRANCE LETTER Litigations.pdf | 11 May 2023 |
| Copy of Layout Approval (in case of layout)File: Plan Navnath Jayas_1-1_11zon.pdf | 11 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan Navnath Jayas_2-4_11zon (1).pdf | 11 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Navnath Jayas on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Goregaon East6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
Elysian Tower C, D, E
Oberoi Realty Limited
Elysian Tower B
Oberoi Realty Limited
Elysian Tower A
Oberoi Realty Limited
Sheetal Sangam
DGS Township Pvt Ltd
SEJAL SQUARE
ALCHEMI DEVELOPERS PRIVATE LIMITED
Mehta Marquina 1978
Shreeram Builders
See every Mumbai Suburban project, with the district possession charts
Builder: Navnath Infrastructures Private Limited
Navnath Infrastructures Private Limited has 2 registrations on MahaRERA, including Navnath Jayas and Navnath Nandikesh. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Navnath Jayas is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Navnath Jayas?
The registered promoter entity is Navnath Infrastructures Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Navnath Jayas?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Navnath Jayas?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Navnath Jayas?
The professionals named in the filing: Architect: Tangent Architects and Interior Designers; Engineer: R C Tipnis; Chartered Accountant: Ms Gaurav S Rajpal and CO; Chartered Accountant: ANKS & CO Chartered Accountants; Chartered Accountant: A N K S & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Navnath Jayas?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback