Registered No litigation declared Residential / Group Housing project

NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.

By KEDAR BUILDCON PRIVATE LIMITED

RG-MH-05523 · RERA P52000051169 · Last updated on MahaRERA portal: 18 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 9 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 85%
11 of 22Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD. is a Residential / Group Housing project by KEDAR BUILDCON PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000051169 on 1 Jun 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 9 months from the original filing. 11 of the 22 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameNAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.
  • TypeResidential / Group Housing
  • Location
    • NAVI MUMBAI
    • OLD PANVEL
    • Navi Mumbai Panvel Rigardh (CT)
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000051169
  • ReraGenie IDRG-MH-05523

Builder

  • NameKEDAR BUILDCON PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsPIYUSH DHIRAJLAL DOSHI, VISHAL PIYUSH DOSHI, MITESH PIYUSH DOSHI
  • Other registrations1 more →
  • Past their filed date1

Key dates

this monthRegisteredJun 2023First promiseMar 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Jun 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed77 files

Current status

50%11 of 22 units booked
90.0%Work done, per cost certificate

Figures as on 18 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTDNA7722022

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 18 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 85%.

NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 18 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area628 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.Navi Mumbai Panvel Rigardh (CT)Raigarh

Approvals and building plan

Sanctioning authorityPANVEL MUNICIPAL CORPORATION
Permissible FSI1893.91
Proposed, not sanctioned1,894 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANVEL
Estimated costRs 5.30 cr
Cost incurredRs 4.77 cr
Work done90.0%
BuildingWingEstimatedIncurred
NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTDNARs 4.77 crRs 4.77 cr
-NARs 53.00 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEVISE DESIGN
EngineerDESTECH STRUCTURAL CONSULTANTS
EngineerVINAYAK PATIL
Chartered AccountantMSNK AND ASSOCIATES LLP
Chartered AccountantPAWAN & ASSOCIATES
Chartered AccountantKMR & ASSOCIATES LLP
PartnerRole in project
KEDAR BUILDCON PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31032620484Mar 2026 → Dec 2026

Reason as filed by the promoter1. While registering the project with MahaRERA,we had underestimated the project completion time which proved to be less for such a project. 2. But rest assured,now the works are in full swing & will be completed with in the stipulated time lines of this extended date and OC will be obtained. 3. Also,we are uploading the PERTChart/work completion schedule of the project. 4. Hence,we request you to consider our request & justification & grant extension to our said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 May 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 June 2026 (2).pdf18 Aug 2026
Withdrawal Update Form 2File: Form-2 June 2026 (2).pdf18 Aug 2026
Withdrawal Update Form 3File: Form-3 June 2026 (2).pdf18 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A(Fy 2025-26).pdf10 Aug 2026
Withdrawal Update Form 1File: Form-1 March 2026 (1).pdf11 Jun 2026
Withdrawal Update Form 2File: Form-2 March 2026 (1).pdf11 Jun 2026
Withdrawal Update Form 3File: Form-3 March 2026 (1).pdf11 Jun 2026
Form 2A (FY 2024-2025)File: Form-2A(Fy 2024-25).pdf31 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 (Fy 2024-25).pdf31 Mar 2026
Withdrawal Update Form 1File: F1 Q3 Navankur.pdf23 Mar 2026
Withdrawal Update Form 2File: Form-2 Navankur.pdf23 Mar 2026
Withdrawal Update Form 3File: F-3 Q3 CA Certificate - Navankur_compressed.pdf23 Mar 2026
Withdrawal Update Form 1File: Form-1 Navankur.pdf26 Oct 2025
Withdrawal Update Form 2File: Form-2 Navankur.pdf26 Oct 2025
Withdrawal Update Form 3File: Form-3 Navankur.pdf26 Oct 2025
F-1 Navankur Q4 2024-2529 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F-3 Navankur Q4 24-25_compressed.pdf29 Apr 2025
F-2 Navankur Q4 24-2529 Apr 2025
Disclosure of sold/ booked inventoryFile: Navanur Q4 sold unsole sign copy.pdf29 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no1 Navankur.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: navnakur sold unsold Q3.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Navankur CHS.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Navankur_compressed.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Navankur CHS.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Navankur-Sold booked Inventory.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1-Architect Certificate Navankur Q2.pdf17 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3-Navankur CA Certificate - Q2.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2- Engineers Certificate Navankur-Q2.pdf17 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Navankur Form no2 Q1 (24-25).pdf23 Jul 2024
Disclosure of sold/ booked inventoryFile: Navankur Disclosure of sold,unsold june 24.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3Q1 Navankur(24-25)_compressed.pdf20 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form-05 navankur 23-24.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1Architect Certificate.pdf18 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form No-2 Structural Engineer Certificate.pdf18 May 2024
Disclosure of sold/ booked inventoryFile: NAVANKUR SOCIETY Sold Unsold.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Navankur Society CA Certificate.pdf18 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Navankur (30-09-23).pdf23 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: navankur form 3 sep 2023.pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: navankur form 3 dec 2023.pdf16 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2NAVANKUR Q-2 NEW.pdf12 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: NAVANKUR Q-3-Form-2 new.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: NAVANKUR Q-2 SOLD UNSOLD new.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: NAVANKUR Q-3-sold unsold new.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 (Navankur CHS)Form1- 1.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 (Navankur CHS)form 1-2.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 (Navankur CHS)Form-1-3.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 (Navankur CHS)Form 1-4.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 (Navankur CHS)Form 1-5.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q3 (Navankur CHS)Form 1-6.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: Q2-Navankur Sold Unsold Inventory sep 2023.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: Q3-Navankur Sold Unsold Inventory dec 2023.pdf9 Feb 2024
Layout approvalFile: Scan_3853-02 copy (1)_compressed.pdf15 May 2023
Building plan approvalFile: Scan_3853-01 copy (1).PDF15 May 2023
Copy of Layout Approval (in case of layout)File: Scan_3853-02 copy (1)_compressed.pdf15 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Scan_3853-01 copy (1).PDF15 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Navankur CHS (1)_compressed.pdf12 May 2023
Copy of the legal title reportFile: TITLE SRACH_compressed.pdf3 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Ac declaration (2).pdf3 May 2023
PAN CardFile: PAN Card Firm-Kedar Buildcon Pvt Ltd.pdf24 Apr 2023
Details of encumbrances concerned to FinanceFile: Declaration Finance encumbrances (2).pdf24 Apr 2023
Details of encumbrances concerned to FinanceFile: Declaration legal encumbrances (2).pdf24 Apr 2023
Details of encumbrances concerned to LegalFile: Declaration Finance encumbrances (2).pdf24 Apr 2023
Details of encumbrances concerned to LegalFile: Declaration legal encumbrances (2).pdf24 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE_compressed.pdf24 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Development Permission.pdf24 Apr 2023
Declaration about Commencement CertificateFile: Declaration CC.pdf24 Apr 2023
Declaration in FORM BFile: Developer Declaration (on stamp paper).pdf24 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Registration form.pdf24 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 final.pdf24 Apr 2023
CERSAI detailsFile: Declaration Cersai (3).pdf24 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest in other rera estate organizations - MD SIR.pdf24 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest in other rera estate organizations - PD SIR.pdf24 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest in other rera estate organizations - VD SIr.pdf24 Apr 2023
Proforma of Agreement for saleFile: AFS_RERA_Navankur CHS.pdf24 Apr 2023
Proforma of Allotment letterFile: MODEL Draft Allotment letter as per rera (3)_compressed.pdf24 Apr 2023
Deviation Report with respect to Allotment letterFile: Declaration allotment deviation report (2).pdf24 Apr 2023
Deviation Report with respect to model copy of AgreementFile: Declaration agreement deviation report (2).pdf24 Apr 2023

How this compares with Raigarh

50%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 9 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OLD PANVEL5,900+ in Raigarh

2 kmNAVANKUR CO-OPERATIVE HOCompleted 212Lapsed / revoked 57Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 402 registered projects within 2 km.

Builder: KEDAR BUILDCON PRIVATE LIMITED

KEDAR BUILDCON PRIVATE LIMITED has 2 registrations on MahaRERA, including NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD. and YASHO NANDANVAN CO-OPERATIVE HOUSING SOCIETY LTD.. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD. is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.?

The registered promoter entity is KEDAR BUILDCON PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.?

The professionals named in the filing: Architect: DEVISE DESIGN; Engineer: DESTECH STRUCTURAL CONSULTANTS; Engineer: VINAYAK PATIL; Chartered Accountant: MSNK AND ASSOCIATES LLP; Chartered Accountant: PAWAN & ASSOCIATES; Chartered Accountant: KMR & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAVANKUR CO-OPERATIVE HOUSING SOCIETY LTD. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.