Home / Browse projects / Mumbai Suburban, Maharashtra / NAV CHETNA
NAV CHETNA
RG-MH-87297 · RERA P51800048061 · Last updated on MahaRERA portal: 29 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 6 months past the filed date
- Rs 0.25 crore secured on the land, in favour of Aditya Birla Housing Finance Ltd
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NAV CHETNA is a Others project by Forishna Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800048061 on 8 Dec 2022. Possession was promised by 30 Apr 2026 and is now 6 months past that date.
At a glance
Project
- NameNAV CHETNA
- TypeOthers
- Location
- JUHU ROAD
- SANTACRUZ WEST NEAR SANTACRUZ POLICE STATION
- Bandra
- Andheri
- Mumbai Suburban
- 400054
- Pincode400054
- RERA no.P51800048061
- ReraGenie IDRG-MH-87297
Builder
- NameForishna Developers LLP
- Entity typePartnership
- PartnersManish Bhadrasen Thakker, Jayesh Chandrakant Shah, Priyank Jayesh Shah
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Dec 2022
- Promised completion30 Apr 2026
- Revised completionNone
- Buildings1 building record
- Documents filed105 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NAV CHETNA | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.
NAV CHETNA: 43% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| NAV CHETNA CHSL | Bandra | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANISH SHAH |
| Engineer | Mehul K shah |
| Chartered Accountant | N S SHETTY AND CO |
| Chartered Accountant | M R SHARMA AND CO |
| Partner | Role in project |
|---|---|
| Forishna Developers LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed105
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 signed.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 Final signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 29 Apr 2026 |
| Form 1File: Form 1 signed.pdf | 29 Apr 2026 |
| Form 2File: Form 2 signed.pdf | 29 Apr 2026 |
| Form 3File: Form 3 signed.pdf | 29 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory.pdf | 29 Apr 2026 |
| Form 1File: Form 1 signed.pdf | 3 Nov 2025 |
| Form 2File: Form 2.pdf | 3 Nov 2025 |
| Form 3File: Form 3.pdf | 3 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 3 Nov 2025 |
| Self-declaration of Quarterly ProgressFile: Quaterly progress Self declaration.pdf | 3 Nov 2025 |
| Form 1File: Form 1.pdf | 31 Jul 2025 |
| Form 2File: Form 2 signed.pdf | 31 Jul 2025 |
| Form 3File: Form 3 signed.pdf | 31 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SoldUnsold Inventory signed.pdf | 31 Jul 2025 |
| Self-declaration of Quarterly ProgressFile: Self declaration signed.pdf | 31 Jul 2025 |
| Form 1File: Form 1.pdf | 9 Jun 2025 |
| Form 2File: Form 2 signed.pdf | 9 Jun 2025 |
| Form 3File: Form 3 signed.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventories signed.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Signed Quaterly progress.pdf | 9 Jun 2025 |
| Building plan approvalFile: Amended Drawing.pdf | 16 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended Drawing.pdf | 16 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC Upto 8th FLoor.pdf | 16 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 16 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 16 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 16 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 19 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 19 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY2223.pdf | 5 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 25 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.pdf | 16 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: Sale Agreement.pdf | 21 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA Certificate.pdf | 8 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Self Declaration.pdf | 6 Sep 2023 |
| Details of encumbrances concerned to LegalFile: Encumbrance Self Declaration.pdf | 6 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 6 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate.pdf | 6 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Forishna Developers LLP Hdfc Bank Ac Rera.pdf | 6 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Plinth CC.pdf | 28 Aug 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Chart - Agreement For Sale.pdf | 2 Dec 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 105 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NAV CHETNA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SANTACRUZ WEST NEAR SANTACRUZ POLICE STATION6,700+ in Mumbai Suburban
AVIARA
BALUWALA BUILDERS
Ruparel Panache
Ruparel Infra & Realty Pvt Ltd
Vascon Orchids
Vascon Engineers Ltd
COMMERZ 54
SHREE VINAYAK REALITY PRIVATE LIMITED
Vascon Onyx Residences
Vascon Engineers Ltd
REDEVELOPMENT OF SHINING STAR CHSL
PRANAV CONSTRUCTIONS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: Forishna Developers LLP
Forishna Developers LLP has 1 registration on MahaRERA, including NAV CHETNA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that NAV CHETNA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if NAV CHETNA is delayed beyond 30 Apr 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NAV CHETNA?
The registered promoter entity is Forishna Developers LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NAV CHETNA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NAV CHETNA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NAV CHETNA?
The professionals named in the filing: Architect: MANISH SHAH; Engineer: Mehul K shah; Chartered Accountant: N S SHETTY AND CO; Chartered Accountant: M R SHARMA AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NAV CHETNA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback