Home / Browse projects / Nashik, Maharashtra / Natures Pride Phase 2
Natures Pride Phase 2
RG-MH-54128 · RERA P51600022281 · Last updated on MahaRERA portal: 15 Jul 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 17 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Natures Pride Phase 2 is a Commercial project by BAGAD PROPERTIES in Nashik, Maharashtra, registered with MahaRERA as P51600022281 on 9 Sep 2019. The registration is recorded completed; possession was promised by 20 May 2025. The completion date has moved by 17 months from the original filing.
At a glance
Project
- NameNatures Pride Phase 2
- TypeCommercial
- Location
- Makhmalabad Road
- Makhmalabad
- Nashik (M Corp.)
- Nashik
- 422003
- Pincode422003
- RERA no.P51600022281
- ReraGenie IDRG-MH-54128
Builder
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on9 Sep 2019
- Promised completion20 May 2025
- Revised completionRevised to 20 May 2025 (originally 10 Dec 2023)
- Buildings3 building records
- Documents filed104 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D Wing | NA | 3 | 0 | 0 | 0 | 0 |
| E Wing | NA | 7 | 0 | 0 | 0 | 0 |
| F Wing | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 15 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
23 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 80%.
D Wing100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E Wing79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
F Wing79%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Progress on shared amenities15
As on 15 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 30% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Avinash Kothawade & Company |
| Engineer | Prashant Patil |
| Chartered Accountant | CA Rahul Chhallani |
| Chartered Accountant | PRAVIN R RATHI & ASSOCIATES |
| Partner | Role in project |
|---|---|
| BAGAD PROPERTIES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRequest for Extension due to the following reasons: 1) Acute shortage of Labour during covid period 2)Disruption caused by rains during excavation work 3)Substantial part of Project is completed as on date Detailed letter and submission attached
Reason as filed by the promoterDear Sir, This is in relation to our Project Registered with Maharera vide Registration Number P51600022281 under the name of “Natures Pride Phase 2”. We are hereby applying for extension under section 7(3) of RERA Act. We further are attaching the following documents alongwith the Extension application: 1) Consent of Allottees as required under Circular No 28/2021 2) Screenshot of all QPR duly completed till 30.09.2024 i.e: a. Form 1, Form 2, Form 3, Form 2A till 30.09.2024 b. Form 5 FY 23-24 c. Details of Sold/Unsold Inventory till 30.09.2024 d. Updation of project details till 30.09.2024 Fu
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jul 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 May 2025
Documents filed104
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Architect Certificate 24-25 Q1.pdf | 15 Jul 2025 |
| Form 2File: Engineer Certificate.pdf | 15 Jul 2025 |
| Form 3File: Form 3 Signed_2.pdf | 15 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Summary Q1 2024-25.pdf | 15 Jul 2025 |
| Form 1File: Architect Certificate 24-25 Q2.pdf | 15 Jul 2025 |
| Form 2File: Enginner cert.pdf | 15 Jul 2025 |
| Form 3File: Form 3 Signed_1.pdf | 15 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Summary Q2 2024-25.pdf | 15 Jul 2025 |
| Form 1File: NP-II Architech Certificate Q3 2024-2025.pdf | 15 Jul 2025 |
| Form 2File: Natures Pride - II F2 Q3 2024-25.pdf | 15 Jul 2025 |
| Form 3File: Natures Pride F3 31-12-2024 Compressed.pdf | 15 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Natures Pride - II Sold & Unsold Q3 2024-25.pdf | 15 Jul 2025 |
| Occupational CertificateFile: Merged Completion.pdf | 6 Jun 2025 |
| Occupational CertificateFile: Form 4 Natures Pride II Architects Certificate -2024-25.pdf | 6 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP-II Architech Certificate Q3 2024-2025.pdf | 17 May 2025 |
| Certificates of CA (Form 3)File: Natures Pride F3 31-12-2024 Compressed.pdf | 17 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Natures Pride - II F2 Q3 2024-25.pdf | 17 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Nature Pride phase II - D Wing.pdf | 17 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP-II Architech Certificate Q3 2024-2025.pdf | 14 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP-II Architec Certificate 2024-25 Q4.pdf | 14 Apr 2025 |
| Declaration in FORM BFile: Form B - 11-02-2025.pdf | 12 Feb 2025 |
| CERSAI detailsFile: CERSAI_Search_Report_200335389028_For_Asset_Based_Search_15_01_2025_11_17_26_397.pdf | 15 Jan 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 15 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Organisation_DDB.pdf | 15 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Organisation_DRB.pdf | 15 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in Other Organisation_RDB.pdf | 15 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Natures Pride II Quality Engineer.pdf | 3 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-03-2023.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 23-24 Q1.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 23-24 Q2.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 23-24 Q3.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 23-24 Q4.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 24-25 Q1.pdf | 29 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 24-25 Q2.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed_2.pdf | 29 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3 Signed_1.pdf | 29 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q2 2024-25.pdf | 29 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Q1 2024-25.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Summary Q1 2024-25.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Summary Q2 2024-25.pdf | 29 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nature Pride II F5 2023-24-.pdf | 23 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Dt 31-03-2024.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Dt 31-12-2023.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Dt 30-09-2023.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 31-12-23.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 31-03-24.pdf | 9 Nov 2024 |
| Certificates of CA (Form 3)File: Nature Pride -II F-3 30-9-23_.pdf | 8 Nov 2024 |
| Certificates of CA (Form 3)File: Nature Pride -II F3 31-12-23_.pdf | 8 Nov 2024 |
| Certificates of CA (Form 3)File: Nature Pride- II F3 31-3-2024_.pdf | 8 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Natures Pride Phase II 30-09-2023.pdf | 8 Nov 2024 |
| Declaration in FORM BFile: NP-Comm Rera Affidavit.pdf | 1 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30-06-2022.pdf | 1 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30-09-2022.pdf | 1 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31-12-2022.pdf | 1 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31-03-2023.pdf | 1 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30-06-2023.pdf | 1 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Natures Pride - II form 2A 31-03-2022.pdf | 1 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Natures Pride - II Form - 2A 31-03-2023.pdf | 1 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Natures Pride Phase II Sold - Unsold 31-12-2022.pdf | 1 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Natures Pride Phase II Sold - Unsold 31-03-2023.pdf | 1 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Natures Pride Phase II Sold - Unsold 30-06-2023.pdf | 1 Jan 2024 |
| Certificates of CA (Form 3)File: Natures Pride Phase- II F3 30-06-2023.pdf | 8 Dec 2023 |
| Certificates of CA (Form 3)File: Signed Form 3.pdf | 6 Dec 2023 |
| Certificates of CA (Form 3)File: Natures Pride Phase II F3 30-6-22.pdf | 6 Dec 2023 |
| Certificates of CA (Form 3)File: Natures Pride Phase II F3 30-9-22.pdf | 6 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nature Pride -II F5 31-3-23_.pdf | 4 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 30-09-2019.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMMArchitect 31-12-2019.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-03-2020.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 30-06-2020.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 30-09-2020.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-12-2020.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-03-2021.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 30-06-2021.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMMArchitect 30-09-2021.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-12-2021.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-03-2022.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 30-06-2022.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 30-09-2022.pdf | 18 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: NP COMM Architect 31-12-2022.pdf | 18 Feb 2023 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NATURES PRIDE - PHASE I | Westwind Meadows. Riverfront Cruiseway Off Makhmalabad Road Nashik Maharashtra | 192 | Completed | Jun 2018 | Apr 2018 |
| BLUE BELLS APARTMENT | KARMAYOGI NAGAR NASHIK | 63 | Completed | Dec 2016 | Late, Apr 2017 |
| SURYADARSHAN APARTMENT | NEW PANDIT COLONY NASHIK | 16 | Completed | Jan 2012 | Late, Jun 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations, which the RERA portal never shows together
- All 104 filed documents as one ZIP, foldered, with a manifest
Keep Natures Pride Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Makhmalabad4,100+ in Nashik
THE PLATINUM MALL BY PARKSYDE
JAIKUMAR CONSTRUCTIONS LTD
AVADH UTOPIA
DHATRAK CONSTRUWELL
ROONGTA ELEGANTE APARTMENT
ROONGTA LANDMARKS LLP
Siddhivinayak Trade Center
Dhatrak Constructions
G SQUARE
GIRI ASSOCIATE CONSTRUCTION
SADGURU HOMES
SHREE SADGURU HOMES
See every Nashik project, with the district possession charts
Builder: BAGAD PROPERTIES
BAGAD PROPERTIES has 5 registrations on MahaRERA, including NATURES PRIDE - PHASE I and NATURES BLISS, PHASE- I. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Natures Pride Phase 2 is delayed beyond 20 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Natures Pride Phase 2?
The registered promoter entity is BAGAD PROPERTIES, a partnership as per the filing. Its GSTIN 27AAJFB2257P1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Natures Pride Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Natures Pride Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Natures Pride Phase 2?
The professionals named in the filing: Architect: Avinash Kothawade & Company; Engineer: Prashant Patil; Chartered Accountant: CA Rahul Chhallani; Chartered Accountant: PRAVIN R RATHI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Natures Pride Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback