Home / Browse projects / Palghar, Maharashtra / NARANG URBANE HOUSING FORUM-PHASE I
NARANG URBANE HOUSING FORUM-PHASE I
By YAMUNA REALTY PRIVATE LIMITED
RG-MH-24929 · RERA P99000004745 · Last updated on MahaRERA portal: 21 Aug 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 58 months past the filed date
- 6 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NARANG URBANE HOUSING FORUM-PHASE I is a Residential / Group Housing project by YAMUNA REALTY PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000004745 on 9 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. 6 complaints are on record with the regulator.
At a glance
Project
- NameNARANG URBANE HOUSING FORUM-PHASE I
- TypeResidential / Group Housing
- Location
- Walve
- Palghar
- 401501
- Pincode401501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000004745
- ReraGenie IDRG-MH-24929
Builder
- NameYAMUNA REALTY PRIVATE LIMITED
- Entity typeCompany
- Managing DirectorAMIT AMARCHAND NARANG
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Aug 2017
- Promised completion30 Dec 2021
- Revised completionNone
- Buildings16 building records
- Documents filed70 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TWIN BLOCK 1 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 2 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 3 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 4 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 5 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 6 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 7 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 8 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 9 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 10 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 11 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 12 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 13 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 14 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 15 | NA | 2 | 0 | 0 | 0 | 0 |
| TWIN BLOCK 16 | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building16
As on 21 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 176 construction stages are filed complete across 16 buildings. The stage furthest along is Excavation, at 85%.
TWIN BLOCK 139%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 239%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 339%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 439%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 539%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 639%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 739%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 839%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 939%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1039%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1139%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1239%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1339%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1439%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1539%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BLOCK 1639%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 15% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 21 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 60% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 10% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY WADE |
| Engineer | C & G BUILDING CONSULTANCY PRIVATE LIMITED |
| Partner | Role in project |
|---|---|
| YAMUNA REALTY PRIVATE LIMITED | - |
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000058005 | Nagindas Properties Private Limited | Yamuna Realty Private Limited | 22/02/2019 |
| CC006000000078199 | Mohit Shankla | Yamuna Realty Private Limited | 22/02/2019 |
| CC006000000078200 | Tapan Shah | Yamuna Reatly Private Limited | 22/02/2019 |
| CC006000000078202 | Nilesh M Shah | Yamuna Realty Private Limited | 22/02/2019 |
| CC006000000078207 | Murtuza Munim | Yamuna Realty Private Limited | 22/02/2019 |
| CC006000000078206 | Vidya Sagar V. | Yamuna Realty Private Limited | 22/02/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jan 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed70
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_Phase - I.pdf | 21 Aug 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate Twin block june'23.pdf | 21 Aug 2023 |
| Declaration about Commencement CertificateFile: Phase-I_ CC declaration Letter.pdf | 22 Jul 2023 |
| CERSAI detailsFile: Phase-I_CERSAI Declaration.pdf | 22 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Phase-I_Inventory Disclosure.pdf | 22 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: apr to june 22.pdf | 8 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: july to sept 22.pdf | 8 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: oct to dec 22.pdf | 8 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: jan to march 23.pdf | 8 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 Q1(FY 2022-2023) Phase I.pdf | 7 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 Q2 (FY 2022-2023) Phase I.pdf | 7 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 Q3 (FY 2022-2023) Phase I.pdf | 7 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 Q4 (FY 2022-2023) Phase I.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Form_2 03 2018_Phase I.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Form_2 03 2019_Phase I.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Form_2 03 2020_Phase I.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Form_2 03 2021_Phase I.pdf | 7 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Form_2 03 2022_Phase I.pdf | 7 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Mar 23 Phase I YRPL.pdf | 7 Jul 2023 |
| Certificates of CA (Form 3)File: signed CA Certificate June'22 Twin block.pdf | 7 Jul 2023 |
| Certificates of CA (Form 3)File: SIgned CA Certificate sept'22 Twin block.pdf | 7 Jul 2023 |
| Certificates of CA (Form 3)File: signed CA Certificate dec'22 Twin block.pdf | 7 Jul 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate Twin block March'23.pdf | 7 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Phase I.pdf | 7 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 31-03-2018 Phase I.PDF | 27 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 31-03-2019 Phase I.PDF | 27 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 31-03-2020 Phase I.PDF | 27 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 31-03-2021 Phase I.PDF | 27 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1 31-03-2022 Phase I.PDF | 27 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Mar 20 Phase I YRPL.PDF | 27 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Mar 21 Phase I YRPL.PDF | 27 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Mar 22 Phase I YRPL.PDF | 27 Jun 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate- March 18 Twin block.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate- March 19 Twin block.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate- March 20 Twin block.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate- March 21 Twin block old.pdf | 27 Jun 2023 |
| Certificates of CA (Form 3)File: Signed CA Certificate March'22 Twin block (2).pdf | 27 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Mar 19 Phase I.PDF | 26 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Mar 20 Phase I.PDF | 26 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Mar 21 Phase I.PDF | 26 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Mar 22 Phase I.PDF | 26 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate NUHF PHASE-1 5th Quarter.pdf | 13 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase I (Architect Certificate) - FORM -1.pdf | 3 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 01022018 (Engineers Certificate) Phase I.pdf | 1 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 01082018 (Engineers Certificate) Phase I new.pdf | 1 Oct 2018 |
| Certificates of CA (Form 5)File: yamuna phase I RERA_r.pdf | 30 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 04022018 (Architects Certificate) Phase I.pdf | 28 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Boisar Phase 1 4th Quarter-ilovepdf-compressed.pdf | 28 Sep 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 01022018 (Engineers Certificate) Phase I.pdf | 28 Sep 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Boisar Phase 1 4th Quarter-ilovepdf-compressed.pdf | 28 Sep 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-ilovepdf-compressed.pdf | 30 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_NUHF, Phase - I-FORM 1 (2).pdf | 16 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: (Town Planning Order).pdf | 9 Jan 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form -1, NUHF-Phase I At the time of updation.pdf | 8 Jan 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NUHF Architect Certificate Phase I Form 1.pdf | 23 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: NUHF Engineer's Certificate Phase 1.pdf | 23 Nov 2017 |
| Layout approvalFile: Phase -I Layout Plan.pdf | 31 Jul 2017 |
| Building plan approvalFile: TP Order.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate Part 1.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate Part 2.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate Part 3.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Details of Encumbrances.pdf | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Phase -I Layout Plan.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: TP Order.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Form B (Twin Block).pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Phase I.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL TWIN ENGG CERTIFICATE.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate Twin Block.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT ROW HOUSE.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter Row House.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 70 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep NARANG URBANE HOUSING FORUM-PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Walve3,200+ in Palghar
Birla Mrida
Birla Estates Private Limited
Roop Rajat Park Phase 3
MAHAVIR ASSOCIATES
AGAMI INFINITY PARK
MAYURESH REALTY PRIVATE LIMITED
Luxury Empire Township Phase I
VEENAA DEVELOPERS PRIVATE LIMITED
MAHAVIR ARCADE
MAHAVIR DEVELOPERS AND REALTORS
SHANTI VISTA - II
SHAH REALTY CORPORATION
See every Palghar project, with the district possession charts
Builder: YAMUNA REALTY PRIVATE LIMITED
YAMUNA REALTY PRIVATE LIMITED has 2 registrations on MahaRERA, including NARANG URBANE HOUSING FORUM-PHASE I and NARANG URBANE HOUSING FORUM - PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that NARANG URBANE HOUSING FORUM-PHASE I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if NARANG URBANE HOUSING FORUM-PHASE I is delayed beyond 30 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NARANG URBANE HOUSING FORUM-PHASE I?
The registered promoter entity is YAMUNA REALTY PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NARANG URBANE HOUSING FORUM-PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against NARANG URBANE HOUSING FORUM-PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for NARANG URBANE HOUSING FORUM-PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NARANG URBANE HOUSING FORUM-PHASE I?
The professionals named in the filing: Architect: AJAY WADE; Engineer: C & G BUILDING CONSULTANCY PRIVATE LIMITED. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NARANG URBANE HOUSING FORUM-PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.