ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Nandanvan

Registered Litigation declared Residential / Group Housing project

Nandanvan

By H B Realty

RG-MH-89630 · RERA P52000045672 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
4 of 201Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Nandanvan is a Residential / Group Housing project by H B Realty in Raigarh, Maharashtra, registered with MahaRERA as P52000045672 on 6 Jun 2022. Possession is promised by 31 Dec 2026. 197 of the 201 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameNandanvan
  • TypeResidential / Group Housing
  • Location
    • Ghot Road
    • Taloja Phase 2
    • Taloje Majkur
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000045672
  • ReraGenie IDRG-MH-89630

Builder

  • NameH B Realty
  • Entity typePartnership
  • GSTIN27AALFH1749N1ZT
  • PartnersBhanupratap harilal Chaurasia, URESHA SANDEEP SHETH
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Jun 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed75 files

Current status

98%197 of 201 units booked
100.0%Work done, per cost certificate

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Nandanvan Building 1NA111110810118
Nandanvan Building 2NA111179483

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

Nandanvan Building 1100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Nandanvan Building 2100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed125

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots125
Closed/Covered125
BuildingClosed/CoveredTotal
Nandanvan Building 18181
Nandanvan Building 24444

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,060 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on14 Nov 2025

Approvals and building plan

Permissible FSI9726.2
Proposed, not sanctioned9,726 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMADHURAAJ BHIMASHANKAR SHOP NO 1 PLOT NO 13 SECTO 19 TALOJA PANCHANAND PHASE 1 MUMBAI MH 410208
Estimated costRs 31.58 cr
Cost incurredRs 31.58 cr
Work done100.0%
BuildingWingEstimatedIncurred
Nandanvan Building 1NARs 17.90 crRs 17.90 cr
Nandanvan Building 2NARs 10.68 crRs 10.68 cr
-NARs 3.00 crRs 3.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNeha Jain
EngineerSamarth Agarwal
EngineerNikhil Gharat
Chartered AccountantHimanshu Kalavadia
Chartered AccountantSiddharth Shah
PartnerRole in project
H B Realty-

Litigation declared1

CaseCourtStatus
Spl.C.S./0000247/2022/2022Panvel, Civil and Criminal courtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM NO 1 OF PH1.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 phase1.pdf4 May 2026
Withdrawal Update Form 3File: Form 3_0001.pdf4 May 2026
Withdrawal Update Form 1File: Form 1_0002.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3_0001.pdf5 Feb 2026
Withdrawal Update Form 1File: Architect Certificate.pdf25 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf25 Nov 2025
Withdrawal Update Form 3File: Form 3.pdf25 Nov 2025
Form 2A (FY 2024-2025)File: Form 2A-Phase 1 _ FY 24-25.pdf20 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 5672- nandanvan ph 2.pdf18 Nov 2025
Withdrawal Update Form 1File: Form 1 ARCHITECT CERTIFICATE...pdf10 Nov 2025
Withdrawal Update Form 2File: Nandanvan EC Phase - I 28-07-25 for 30-06-25 with DSC.pdf10 Nov 2025
Withdrawal Update Form 3File: CA Certificate HB Realty PH 1_compressed.pdf10 Nov 2025
Withdrawal Update Form 1File: Form 1 ARCHITECT CERTIFICATE...pdf2 Aug 2025
Withdrawal Update Form 2File: Nandanvan EC Phase - I 28-07-25 for 30-06-25 with DSC.pdf2 Aug 2025
Withdrawal Update Form 3File: CA Certificate HB Realty PH 1_compressed.pdf2 Aug 2025
Form 1File: Form 1 ARCHITECT CERTIFICATE ( PHASE-1).pdf30 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aechitect Certificate Phase 1.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate HB Realty PH 1.pdf12 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandanvan EC Phase - I 03-02-25 for 31-12-24.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan_Certificate_PH 1_compressed.pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect June 2022.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect Sept 2024_compressed.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandanvan --- EC Phase - I 21-10-24 for 30-09-24.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandanvan EC 30-06-22.pdf24 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Quality Assurance Certificate FY 2022-23 signed.pdf18 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality Assurance Certificate FY 2023-24 signed.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062023.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122023.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062024_compressed.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 311223.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 300624.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ANNUAL REPORT - H B REALITIES FY 23-24.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate HB Realty.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Siddharth Certificate form 3_compressed.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate HB Realty.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE 31-03-2024_compressed (1).pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandanvan EC 31-03-24.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Copy of CA Certificate HB Realty.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Adobe Scan 14 Feb 2024_compressed.pdf15 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE 30-09-2023_compressed.pdf19 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandanvan --- EC 30-09-23.pdf19 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ca Certificate.pdf19 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - H B REALITIES.pdf3 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandanvan EC 30-06-23 with DSC.pdf26 Sep 2023
Copy of the legal title reportFile: TITLE REPORT.pdf20 Jun 2023
Details of encumbrances concerned to FinanceFile: Rera Letter for dismissal of suit.pdf20 Jun 2023
Details of encumbrances concerned to LegalFile: Rera Letter for dismissal of suit.pdf20 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect- An arch_compressed.pdf20 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Structure Engg-Samarth Agarwal_compressed.pdf20 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 ARCHITECT CERTIFICATE_compressed.pdf4 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf4 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_compressed.pdf4 Feb 2023
Details of encumbrances concerned to LegalFile: legal Case Declaration.pdf14 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate_compressed.pdf17 Sep 2022
Layout approvalFile: Sheet_No_compressed_11zon.pdf28 May 2022
Copy of Layout Approval (in case of layout)File: Sheet_No_compressed_11zon.pdf28 May 2022
Building plan approvalFile: Approval plan.pdf27 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Approval plan.pdf27 May 2022
Declaration about Commencement CertificateFile: declaration - H B Realty.pdf27 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf27 May 2022
OtherFile: Credai MCHI certificate.pdf27 May 2022
Layout approvalFile: Development permission.pdf21 May 2022
PAN CardFile: Pan card.pdf21 May 2022
Copy of the legal title reportFile: Legal Title Report.pdf21 May 2022
Details of encumbrancesFile: NO ENCUMBRANCE DECLARATION.pdf21 May 2022
Copy of Layout Approval (in case of layout)File: Development permission.pdf21 May 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf21 May 2022
Declaration about Commencement CertificateFile: CC.pdf21 May 2022
Declaration in FORM BFile: notarised affidavit.pdf21 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf21 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf21 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200237845100_For_Asset_Based_Search_21_05_2022_16_29_24_950.pdf21 May 2022
Proforma of Allotment letterFile: Proforma Allotment letter and agrrement of sale.pdf21 May 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NEEM VATIKASURVEY NO 130-0 TALOJE MAJKUR PANVEL48CompletedJun 2020Jan 2020

How this compares with Raigarh

98%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nandanvan on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Taloja Phase 25,900+ in Raigarh

2 kmNandanvanCompleted 10Lapsed / revoked 10Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: H B Realty

H B Realty has 3 registrations on MahaRERA, including NEEM VATIKA and Nandanvan. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Nandanvan is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nandanvan?

The registered promoter entity is H B Realty, a partnership as per the filing. Its GSTIN 27AALFH1749N1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nandanvan?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nandanvan?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nandanvan?

The professionals named in the filing: Architect: Neha Jain; Engineer: Samarth Agarwal; Engineer: Nikhil Gharat; Chartered Accountant: Himanshu Kalavadia; Chartered Accountant: Siddharth Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nandanvan?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nandanvan. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nandanvan to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.