NANDANVAN PARK
By SWAGAT PROMOTERS AND BUILDERS
RG-MH-09933 · RERA P52100000846 · Last updated on MahaRERA portal: 16 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 82 months
- 6 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NANDANVAN PARK is a Residential / Group Housing project by SWAGAT PROMOTERS AND BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100000846 on 23 Jul 2017. Possession is promised by 23 Mar 2028. The completion date has moved by 82 months from the original filing.
At a glance
Project
- NameNANDANVAN PARK
- TypeResidential / Group Housing
- Location
- PUNE MULSHI ROAD
- BHUGAON
- Mulshi
- Pune
- 412115
- Pincode412115
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100000846
- ReraGenie IDRG-MH-09933
Builder
- NameSWAGAT PROMOTERS AND BUILDERS
- Entity typePartnership
- GSTIN27ACQFS1606N1ZL
- PartnersBALU DAGADU CHONDHE, Rohidas Dattatray Chondhe
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Jul 2017
- Promised completion23 Mar 2028
- Revised completionRevised to 23 Mar 2028 (originally 28 May 2021)
- Buildings1 building record
- Documents filed300 files
Current status
Figures as on 16 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NANDANVAN PARK | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
NANDANVAN PARK: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed32
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| VASANT RAMBHAU POKHARKAR | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| NANDANVAN PARK | NA | Rs 7.86 cr | Rs 7.86 cr |
| - | NA | Rs 1.61 cr | Rs 1.11 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DIXIT AND ASSOCIATES Associates |
| Engineer | VILAS PURANDARE |
| Engineer | Pavan Vikas Joshi |
| Chartered Accountant | Sandip S. Jagtap |
| Chartered Accountant | S M Pathare & Associates |
| Chartered Accountant | SHRIKANT MARUTI PATHARE |
| Partner | Role in project |
|---|---|
| SWAGAT PROMOTERS AND BUILDERS | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe Swagat Developers and Builder had registered out Real Estate project viz. ‘Nandanvan Park’ with you under Project Registration No. P5210000084. The Project Completion Date is 28.05.2021. Though the structural and site development is completed in full , due to labor and material shortage owing to ‘ Global Pandemic’ and ‘Recent Lockdown’ few actions like OC and Handover is still pending. We require some more time to finish the project and complete paper work for Handover to Association of Allottee In Light of above fact we request you to grant us 1 year extension for project completion and is
Reason as filed by the promoterAs on 21.11.2022 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) Delay in receipt of NOC from Ministry of Civil Aviation about building height permission 2) Fire NOC not yet received in respect of completion of the project from Fire Officer There is time required for getting documents compliance to get completion certificate for remaining 6 flats at 6th Floor, you are requested
Reason as filed by the promoterAs on 27.11.2023 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA. There is time required for getting documents compliance to get completion certificate for remaining 6 flats at
Reason as filed by the promoterAs on 19.12.2024 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA.
Reason as filed by the promoterAs on 10.08.2026 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA. The above mentioned technical issue not resolved from PMRDA department till date.
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Oct 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Nov 2022
Documents filed300
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 300 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form - I.pdf | 16 Sep 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 16 Sep 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 16 Sep 2026 |
| Form 2A (FY 2026-2027)File: Form 2A.pdf | 16 Sep 2026 |
| Withdrawal Update Form 1File: Form - 1.pdf | 15 Sep 2026 |
| Withdrawal Update Form 1File: Form - 1.pdf | 15 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 (March 26).pdf | 15 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 (March 26).pdf | 15 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 (March 26).pdf | 15 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 (March 26).pdf | 15 Sep 2026 |
| Form 5 (FY 2017-2018)File: Form -5 (2017-2018).pdf | 31 Jul 2026 |
| Form 5 (FY 2018-2019)File: Form 5 (2018-2019).pdf | 31 Jul 2026 |
| Form 5 (FY 2019-2020)File: Form -5 (2019-2020).pdf | 31 Jul 2026 |
| Form 5 (FY 2020-2021)File: Form -5 (2020-2021).pdf | 31 Jul 2026 |
| Form 5 (FY 2021-2022)File: Form - 5 (2021-2022).pdf | 31 Jul 2026 |
| Form 5 (FY 2022-2023)File: Form 5 (2022-2023.pdf | 31 Jul 2026 |
| Form 5 (FY 2023-2024)File: Form -5 (2023-2024).pdf | 31 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5 (2024-2025).pdf | 31 Jul 2026 |
| Form 2A (FY 2017-2018)File: 18-10-19.pdf | 29 Jul 2026 |
| Form 2A (FY 2018-2019)File: 18-10-19.pdf | 29 Jul 2026 |
| Form 2A (FY 2019-2020)File: 18-10-19.pdf | 29 Jul 2026 |
| Form 2A (FY 2020-2021)File: 12-6-21.pdf | 29 Jul 2026 |
| Form 2A (FY 2021-2022)File: Form-2A.pdf | 29 Jul 2026 |
| Form 2A (FY 2022-2023)File: Form 2A.pdf | 29 Jul 2026 |
| Form 2A (FY 2023-2024)File: Form 2A.pdf | 29 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A (March 25).pdf | 29 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A (March 26).pdf | 29 Jul 2026 |
| Form 1File: Form - 1.pdf | 28 Jul 2026 |
| Form 2File: Form 2 (Dec 24).pdf | 28 Jul 2026 |
| Form 3File: Form 3 (Dec 24).pdf | 28 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold(Dec 24).pdf | 28 Jul 2026 |
| OthersFile: Format A (Dec 24).pdf | 28 Jul 2026 |
| Form 2File: Form 2 (March 25).pdf | 28 Jul 2026 |
| Form 3File: Form 3 (March 25).pdf | 28 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold (March 25).pdf | 28 Jul 2026 |
| OthersFile: Format A (March 25).pdf | 28 Jul 2026 |
| Form 1File: Form - 1.pdf | 28 Jul 2026 |
| Form 1File: Form - 1.pdf | 28 Jul 2026 |
| Form 2File: Form 2 (June 25).pdf | 28 Jul 2026 |
| Form 3File: Form 3 (June 25).pdf | 28 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold (June 25).pdf | 28 Jul 2026 |
| OthersFile: Format A (June 25).pdf | 28 Jul 2026 |
| Form 1File: Form - 1.pdf | 28 Jul 2026 |
| Form 2File: Form 2 (Sep 25).pdf | 28 Jul 2026 |
| Form 3File: Form 3 (Sep 25).pdf | 28 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold (Sep 25).pdf | 28 Jul 2026 |
| OthersFile: Format A (Sep 25).pdf | 28 Jul 2026 |
| Form 1File: Form - 1.pdf | 28 Jul 2026 |
| Form 2File: Form 2 (Dec 25).pdf | 28 Jul 2026 |
| Form 3File: Form 3 (Dec 25).pdf | 28 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold (Dec 25).pdf | 28 Jul 2026 |
| OthersFile: Format A (Dec 25).pdf | 28 Jul 2026 |
| Form 1File: Form - 1.pdf | 27 Jul 2026 |
| Form 2File: Form - 2.pdf | 27 Jul 2026 |
| Form 3File: form 3 (1st).pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
| Form 1File: Form-I.pdf | 27 Jul 2026 |
| Form 2File: Form-2.pdf | 27 Jul 2026 |
| Form 3File: Form-3.pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
| Form 1File: Form-I.pdf | 27 Jul 2026 |
| Form 2File: Form-2.pdf | 27 Jul 2026 |
| Form 3File: Form-3.pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
| Form 1File: Form-I.pdf | 27 Jul 2026 |
| Form 2File: Form-2.pdf | 27 Jul 2026 |
| Form 3File: Form-3.pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
| Form 1File: Form-I.pdf | 27 Jul 2026 |
| Form 2File: Form-2.pdf | 27 Jul 2026 |
| Form 3File: Form-3.pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
| Form 1File: Form-I.pdf | 27 Jul 2026 |
| Form 2File: Form-2.pdf | 27 Jul 2026 |
| Form 3File: Form-3.pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
| Form 1File: Form-I.pdf | 27 Jul 2026 |
| Form 2File: Form-2.pdf | 27 Jul 2026 |
| Form 3File: Form-3.pdf | 27 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 27 Jul 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 300 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NANDANVAN PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHUGAON13,700+ in Pune
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
Avian Valley - Solaire
KAKADE ESTATE DEVELOPERS PVT. LTD.
Park Pebbles Phase I
M/s Rainbow Purple Construction LLP
Mahindra Rivenza Phase 2
Mahindra Lifespace Developers limited
Mahindra Rivenza Phase 1
Mahindra Lifespace Developers limited
FOREST TRAILS ATHASHRI B3
LAVIM DEVELOPERS PVT LTD
KOHINOOR WOODSHIRE
INTOFINITY PROMOTERS PRIVATE LIMITED
Builder: SWAGAT PROMOTERS AND BUILDERS
SWAGAT PROMOTERS AND BUILDERS has 1 registration on MahaRERA, including NANDANVAN PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if NANDANVAN PARK is delayed beyond 23 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NANDANVAN PARK?
The registered promoter entity is SWAGAT PROMOTERS AND BUILDERS, a partnership as per the filing. Its GSTIN 27ACQFS1606N1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NANDANVAN PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for NANDANVAN PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NANDANVAN PARK?
The professionals named in the filing: Architect: DIXIT AND ASSOCIATES Associates; Engineer: VILAS PURANDARE; Engineer: Pavan Vikas Joshi; Chartered Accountant: Sandip S. Jagtap; Chartered Accountant: S M Pathare & Associates; Chartered Accountant: SHRIKANT MARUTI PATHARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NANDANVAN PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback