NANDAN CARNIVAL B BUILDING
RG-MH-07923 · RERA P51600012244 · Last updated on MahaRERA portal: 30 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 108 months
- 3 extensions taken
- Rs 80.00 crore secured on the land, in favour of SBICAP TRUSTEE COMPANY LTD
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
NANDAN CARNIVAL B BUILDING is a Residential / Group Housing project by NANDAN BUILDCON PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600012244 on 1 Sep 2017. Possession is promised by 31 Mar 2028. The completion date has moved by 108 months from the original filing. 20 of the 104 units on this registration are recorded sold or booked, and 3 of 10 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameNANDAN CARNIVAL B BUILDING
- TypeResidential / Group Housing
- Location
- MUMBAI AGRA HIGHWAY
- ADGAON
- Nashik (M Corp.)
- Nashik
- 422003
- Pincode422003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600012244
- ReraGenie IDRG-MH-07923
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Sep 2017
- Promised completion31 Mar 2028
- Revised completionRevised to 31 Mar 2028 (originally 31 Mar 2019)
- Buildings1 building record
- Documents filed174 files
Current status
Figures as on 30 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NANDAN CARNIVAL B BUILDING | NA | 14 | 13 | 104 | 0 | 104 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 10 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
NANDAN CARNIVAL B BUILDING: 54% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | 40% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
Progress on shared amenities15
As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 35% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | 20% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 95% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 70% |
| Open Parking | No | Not applicable |
Parking filed166
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| NANDAN CARNIVAL B BUILDING | NA | Rs 38.93 cr | Rs 20.91 cr |
| - | NA | Rs 5.91 cr | Rs 3.70 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RAVI AMRUTKAR AND ASSOCIATES |
| Engineer | LAXMAN AFRANDE |
| Engineer | NILESH CHAUDHARY |
| Chartered Accountant | P B D & CO. CHARTERED ACCOUNTANTS |
| Chartered Accountant | JAGDISHKUMAR AMRUTLAL PATEL |
| Partner | Role in project |
|---|---|
| NANDAN BUILDCON PVT LTD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCONSTRUCTION ACTIVITY NOT COMPLETED DUE TO POOR SALE. HOWEVER 30% CONSTRUCTION IS COMPLETED BY OUR OWN FUND AND PART SALE OF FLAT.
Reason as filed by the promoterDue to no response from customers which resulted into insufficient, cash flow and there fore we had to stop the project construction. Now with the help of SWAMIH fund (A fund by Govt to revive the stopped projects), We are restarting the project.
Reason as filed by the promoterWe have restarted the work at the project site in the month of August 2025 after completing due diligence, obtaining necessary approvals, and receiving disbursement from the SWAMIH Fund. The SWAMIH Fund has sanctioned and disbursed the required funds to enable us to complete the entire construction of the project within the next 24 months. The progress of construction is reflected in our quarterly progress reports submitted from time to time. Further, sales in the project have commenced from the month of December 2025. However, we are pleased to inform you that with the assistance of the SWAMI
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC001000000010154 | DR VISHAL THAKUR | MR SHAMKANT KOTKAR NANDAN BUILD CON | 26/09/2020 |
| CC001000000020193 | prakash bhaurao borse | Shyamkant keshav kotkar | 17/08/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Aug 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Jun 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Apr 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2028
Documents filed174
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 174 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 27 NC B Architect Certificate 30062026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: 36 NC BLDG B ENGG CERTIFICATE FORM 2 30062026.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: Q1 B Building 300626.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: 26 NC B Architect Certificate 31032026.pdf | 8 May 2026 |
| Withdrawal Update Form 2File: 35 NC BLDG B ENGG CERTIFICATE FORM 2 31032026.pdf | 8 May 2026 |
| Withdrawal Update Form 3File: From 3 B.pdf | 8 May 2026 |
| Form 2A (FY 2024-2025)File: From 2A Bild B.pdf | 13 Mar 2026 |
| Form 5 (FY 2017-2018)File: NCAR_B BLD Form 5_17-18.pdf | 11 Mar 2026 |
| Form 5 (FY 2018-2019)File: NCAR_B BLD Form 5_18-19.pdf | 11 Mar 2026 |
| Form 5 (FY 2019-2020)File: NCAR_B BLD Form 5_19-20.pdf | 11 Mar 2026 |
| Form 5 (FY 2020-2021)File: NCAR_B BLD Form 5_20-21.pdf | 11 Mar 2026 |
| Form 5 (FY 2021-2022)File: NCAR_B BLD Form 5_21-22.pdf | 11 Mar 2026 |
| Form 5 (FY 2022-2023)File: NCAR_B BLD Form 5_22-23.pdf | 11 Mar 2026 |
| Form 5 (FY 2023-2024)File: NCAR_B BLD Form 5_23-24.pdf | 11 Mar 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - 2024-25.pdf | 11 Mar 2026 |
| Withdrawal Update Form 1File: 25 NC B Architect Certificate 31122025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: 34 NC BLDG B ENGG CERTIFICATE FORM 2 31122025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: Q 3 - 31-12-2025 B Building.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: 24 NC B Architect Certificate 30092025.pdf | 7 Nov 2025 |
| Withdrawal Update Form 1File: 24 NC B Architect Certificate 30092025.pdf | 7 Nov 2025 |
| Withdrawal Update Form 2File: 33 NC BLDG-B ENGG CERTIFICATE FORM 2 30092025.pdf | 7 Nov 2025 |
| Withdrawal Update Form 2File: 33 NC BLDG-B ENGG CERTIFICATE FORM 2 30092025.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: 20 Nandan Carnival B Building.pdf | 7 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 - Q 2 - 30-09-2025 B Building.pdf | 7 Nov 2025 |
| Withdrawal Update Form 1File: From 1 B Building.pdf | 28 Aug 2025 |
| Withdrawal Update Form 1File: From 1 B Building.pdf | 28 Aug 2025 |
| Withdrawal Update Form 2File: 32NC BLDGB ENGG CERTIFICATE FORM 2 30062025.pdf | 28 Aug 2025 |
| Withdrawal Update Form 2File: 32NC BLDGB ENGG CERTIFICATE FORM 2 30062025.pdf | 28 Aug 2025 |
| Withdrawal Update Form 3File: CA Certificate- B Building .pdf | 28 Aug 2025 |
| Withdrawal Update Form 3File: 20 Nandan Carnival B Building.pdf | 28 Aug 2025 |
| Certificates of CA (Form 3)File: 3 Building B - 31-03-2025.pdf | 26 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: B - 31-03-2025.pdf | 23 Jun 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 22 NC B Architect Certificate 31032025.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 22 NC BLDG B ENGG CERTIFICATE FORM 2 31122022.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 23 NC BLDG B ENGG CERTIFICATE FORM 2 31032023.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 24 NC BLDG B ENGG CERTIFICATE FORM 2 30062023.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 25 NC BLDG B ENGG CERTIFICATE FORM 2 30092023.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 26 NC BLDG B ENGG CERTIFICATE FORM 2 31122023.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 27 NC BLDG B ENGG CERTIFICATE FORM 2 31032024.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 28 NC BLDG B ENGG CERTIFICATE FORM 2 30062024.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 29 NC BLDG B ENGG CERTIFICATE FORM 2 30092024.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30 NC BLDG B ENGG CERTIFICATE FORM 2 31122024.pdf | 11 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 NC BLDG B ENGG CERTIFICATE FORM 2 31032025.pdf | 11 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: B.pdf | 11 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: NC BLDG B QUALITY CERTIFICATE FORM 2A 2023.pdf | 11 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: NC BLDG B QUALITY CERTIFICATE FORM 2A 2024.pdf | 11 Jun 2025 |
| Layout approvalFile: Layout PLAN B.pdf | 4 Jun 2025 |
| Copy of Layout Approval (in case of layout)File: Layout PLAN B.pdf | 4 Jun 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: NCAR Revised NMC CC 18082023.pdf | 4 Jun 2025 |
| Declaration about Commencement CertificateFile: Declaration about CC Bld B.pdf | 4 Jun 2025 |
| Other - TechnicalFile: Building B.pdf | 4 Jun 2025 |
| Layout approvalFile: 4 BUILDING B ODD FLOOR_Highlighted B Building FSI.pdf | 7 Apr 2025 |
| Layout approvalFile: 8 Layout Plan ROW HOUSE Highlighted.pdf | 7 Apr 2025 |
| Building plan approvalFile: 3 BUILDING B_rotated.pdf | 7 Apr 2025 |
| Building plan approvalFile: 7 Layout PLAN.pdf | 7 Apr 2025 |
| Building plan approvalFile: 8 Layout Plan ROW HOUSE.pdf | 7 Apr 2025 |
| Building plan approvalFile: 8 Layout Plan ROW HOUSE Highlighted.pdf | 7 Apr 2025 |
| Building plan approvalFile: 9 PARKING LAYOUT_rotated.pdf | 7 Apr 2025 |
| Building plan approvalFile: 4 BUILDING B ODD FLOOR_Highlighted B Building FSI.pdf | 7 Apr 2025 |
| Copy of Layout Approval (in case of layout)File: 4 BUILDING B ODD FLOOR_Highlighted B Building FSI.pdf | 7 Apr 2025 |
| Copy of Layout Approval (in case of layout)File: 8 Layout Plan ROW HOUSE Highlighted.pdf | 7 Apr 2025 |
| Building Plan Approval (IOD)File: 3 BUILDING B_rotated.pdf | 7 Apr 2025 |
| Building Plan Approval (IOD)File: 7 Layout PLAN.pdf | 7 Apr 2025 |
| Building Plan Approval (IOD)File: 8 Layout Plan ROW HOUSE.pdf | 7 Apr 2025 |
| Building Plan Approval (IOD)File: 8 Layout Plan ROW HOUSE Highlighted.pdf | 7 Apr 2025 |
| Building Plan Approval (IOD)File: 9 PARKING LAYOUT_rotated.pdf | 7 Apr 2025 |
| Building Plan Approval (IOD)File: 4 BUILDING B ODD FLOOR_Highlighted B Building FSI.pdf | 7 Apr 2025 |
| Layout approvalFile: Sanction Highlighted B Build.pdf | 28 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: Sanction Highlighted B Build.pdf | 28 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 21 NC B Architect Certificate 31 12 2024.pdf | 28 Mar 2025 |
| Certificates of CA (Form 3)File: 15 From 3 Bid B_ 31-12-24.pdf | 24 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BLDG-B ENGG CERTIFICATE FORM 2 Dec24.pdf | 24 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Building B.PDF | 24 Mar 2025 |
| Declaration in FORM BFile: 01 Format B Building B.pdf | 26 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A B.pdf | 25 Dec 2024 |
| Certificates of CA (Form 3)File: 7 From 3 Bid B_31-12-22.pdf | 23 Dec 2024 |
| Certificates of CA (Form 3)File: 14 From 3 Bid B_ 30-09-24.pdf | 23 Dec 2024 |
| Certificates of CA (Form 3)File: 13 From 3 Bid B_30-06-24.pdf | 23 Dec 2024 |
| Certificates of CA (Form 3)File: 12 From 3 Bid B_31-3-24.pdf | 23 Dec 2024 |
| Certificates of CA (Form 3)File: 11 From 3 Bid B_31-12-23.pdf | 23 Dec 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NANDAN EUPHORA | SR NO 47 HISSA 1A HAWALDARA MALA DHANORI PUNE 411015 | 130 | Completed | Feb 2015 | Feb 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 174 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep NANDAN CARNIVAL B BUILDING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ADGAON4,100+ in Nashik
THE PLATINUM MALL BY PARKSYDE
JAIKUMAR CONSTRUCTIONS LTD
AVADH UTOPIA
DHATRAK CONSTRUWELL
ROONGTA ELEGANTE APARTMENT
ROONGTA LANDMARKS LLP
Siddhivinayak Trade Center
Dhatrak Constructions
G SQUARE
GIRI ASSOCIATE CONSTRUCTION
SADGURU HOMES
SHREE SADGURU HOMES
See every Nashik project, with the district possession charts
Builder: NANDAN BUILDCON PVT LTD
NANDAN BUILDCON PVT LTD has 3 registrations on MahaRERA, including NANDAN CARNIVAL A BUILDING and NANDAN CARNIVAL B BUILDING. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if NANDAN CARNIVAL B BUILDING is delayed beyond 31 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of NANDAN CARNIVAL B BUILDING?
The registered promoter entity is NANDAN BUILDCON PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in NANDAN CARNIVAL B BUILDING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against NANDAN CARNIVAL B BUILDING?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for NANDAN CARNIVAL B BUILDING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at NANDAN CARNIVAL B BUILDING?
The professionals named in the filing: Architect: RAVI AMRUTKAR AND ASSOCIATES; Engineer: LAXMAN AFRANDE; Engineer: NILESH CHAUDHARY; Chartered Accountant: P B D & CO. CHARTERED ACCOUNTANTS; Chartered Accountant: JAGDISHKUMAR AMRUTLAL PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NANDAN CARNIVAL B BUILDING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback