Home / Browse projects / Nashik, Maharashtra / NANDAN CARNIVAL A BUILDING

Registered No litigation declared Residential / Group Housing project

NANDAN CARNIVAL A BUILDING

By NANDAN BUILDCON PVT LTD

RG-MH-07866 · RERA P51600012372 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 99 months
  • 3 extensions taken
  • Rs 80.00 crore secured on the land, in favour of SBICAP TRUSTEE COMPANY LTD

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 99 months from the original
4 of 10Construction stages donefurthest along: Internal walls, 60%
95 of 104Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 169 documents Report an error

NANDAN CARNIVAL A BUILDING is a Residential / Group Housing project by NANDAN BUILDCON PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600012372 on 1 Sep 2017. Possession is promised by 31 Mar 2028. The completion date has moved by 99 months from the original filing. 9 of the 104 units on this registration are recorded sold or booked, and 4 of 10 construction stages are filed complete.

At a glance

Project

  • NameNANDAN CARNIVAL A BUILDING
  • TypeResidential / Group Housing
  • Location
    • MUMBAI AGRA HIGHWAY
    • ADGAON
    • Nashik (M Corp.)
    • Nashik
    • 422003
  • Pincode422003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600012372
  • ReraGenie IDRG-MH-07866

Builder

  • NameNANDAN BUILDCON PVT LTD
  • Entity typeCompany
  • Managing DirectorSHAMKANT KESHAV KOTKAR
  • Other registrations2 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2017First promiseDec 2019Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Sep 2017
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed169 files

Current status

9%9 of 104 units booked
61.7%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NANDAN CARNIVAL A BUILDINGNA15131040104

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 10 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

NANDAN CARNIVAL A BUILDING: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)40%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.48%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes40%
Street LightingYes0%
Community BuildingsNo20%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes0%
Energy managemcntNo0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceYes70%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,371 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofSBICAP TRUSTEE COMPANY LTD
Secured amountRs 80.00 crore
CERSAI search filedYes
Declared on19 Jul 2025

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI9642.18
Proposed, not sanctioned9,642 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT 265/2 BANER ROAD OPP BHARAT GAS PETROL PUMP, BANER
Estimated costRs 30.80 cr
Cost incurredRs 19.00 cr
Work done61.7%
BuildingWingEstimatedIncurred
NANDAN CARNIVAL A BUILDINGNARs 26.09 crRs 16.06 cr
-NARs 4.70 crRs 2.95 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDISIGN SQUARE ASSOCIATES
ArchitectRAVI AMRUTKAR AND ASSOCIATES
EngineerLAXMAN AFRANDE
EngineerNILESH CHAUDHARY
Chartered AccountantP B D & CO. CHARTERED ACCOUNTANTS
Chartered AccountantJAGDISHKUMAR AMRUTLAL PATEL
PartnerRole in project
NANDAN BUILDCON PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600005656Dec 2019 → Dec 2020

Reason as filed by the promoterDUE TO POOR SALES AND MARKET CONDITION IN NASHIK WE COULD NOT EXECUTE WORK ON SITE FOR LAST THREE YEARS. WE HAVE HAD BANKING FINANCIAL ISSUES WHICH ARE NOW SOLVED THROUGH PART SALE OF LAND TO A MNC. WE WILL NOW COMMENCE WITH THE WORK FOR WHICH WE WILL NEED 2 YEARS OF EXTENSION.

EXT51600025558Dec 2019 → Mar 2026

Reason as filed by the promoterDue to no response from customers which resulted into insufficient, Cash flow and there for we had to stop the project construction. Now with the help of SWAMIH fund (A fund by Govt to revive the stopped projects). We are restarting the project.

EA04032620076Dec 2019 → Mar 2028

Reason as filed by the promoterWe have restarted the work at the project site in the month of August 2025 after completing due diligence, obtaining necessary approvals, and receiving disbursement from the SWAMIH Fund. The SWAMIH Fund has sanctioned and disbursed the required funds to enable us to complete the entire construction of the project within the next 24 months. The progress of construction is reflected in our quarterly progress reports submitted from time to time. Further, sales in the project have commenced from the month of December 2025. However, we are pleased to inform you that with the assistance of the SWAMI

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jun 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jun 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed169

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 169 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 27 NC A Architect Certificate 30062026.pdf30 Jul 2026
Withdrawal Update Form 2File: 36 NC BLDG A ENGG CERTIFICATE FORM 2 30062026.pdf30 Jul 2026
Withdrawal Update Form 3File: Q1 A Building 300626.pdf30 Jul 2026
Withdrawal Update Form 1File: 25 NC A Architect Certificate 31122025.pdf8 May 2026
Withdrawal Update Form 1File: 26 NC A Architect Certificate 31032026.pdf8 May 2026
Withdrawal Update Form 2File: 33 NC BLDG A ENGG CERTIFICATE FORM 2 30092025.pdf8 May 2026
Withdrawal Update Form 2File: 35 NC BLDG A ENGG CERTIFICATE FORM 2 31032026.pdf8 May 2026
Withdrawal Update Form 3File: From 3 A.pdf8 May 2026
Withdrawal Update Form 3File: From 3 A-31032026.pdf8 May 2026
Form 2A (FY 2024-2025)File: From 2A Bild A.pdf16 Mar 2026
Form 5 (FY 2017-2018)File: NCAR_A BLD Form 5_17-18.pdf11 Mar 2026
Form 5 (FY 2018-2019)File: NCAR_A BLD Form 5_18-19.pdf11 Mar 2026
Form 5 (FY 2019-2020)File: NCAR_A BLD Form 5_19-20.pdf11 Mar 2026
Form 5 (FY 2020-2021)File: NCAR_A BLD Form 5_20-21.pdf11 Mar 2026
Form 5 (FY 2021-2022)File: NCAR_A BLD Form 5_21-22.pdf11 Mar 2026
Form 5 (FY 2022-2023)File: NCAR_A BLD Form 5_22-23.pdf11 Mar 2026
Form 5 (FY 2023-2024)File: NCAR_A BLD Form 5_23-24.pdf11 Mar 2026
Form 5 (FY 2024-2025)File: NCAR_A BLD Form 5_24-25.pdf11 Mar 2026
Withdrawal Update Form 1File: 25 NC A Architect Certificate 31122025.pdf16 Feb 2026
Withdrawal Update Form 1File: 25 NC A Architect Certificate 31122025.pdf16 Feb 2026
Withdrawal Update Form 2File: 33 NC BLDG A ENGG CERTIFICATE FORM 2 30092025.pdf16 Feb 2026
Withdrawal Update Form 2File: 33 NC BLDG A ENGG CERTIFICATE FORM 2 30092025.pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3 - Q 2 - 30-09-2025 A Building.pdf16 Feb 2026
Withdrawal Update Form 3File: Q 3 - 31-12-2025 A Building.pdf16 Feb 2026
Withdrawal Update Form 1File: 24 NC A Architect Certificate 30092025.pdf7 Nov 2025
Withdrawal Update Form 1File: 24 NC A Architect Certificate 30092025.pdf7 Nov 2025
Withdrawal Update Form 2File: 33 NC BLDG A ENGG CERTIFICATE FORM 2 30092025.pdf7 Nov 2025
Withdrawal Update Form 2File: 33 NC BLDG A ENGG CERTIFICATE FORM 2 30092025.pdf7 Nov 2025
Withdrawal Update Form 3File: Form 3 - Q 2 - 30-09-2025 A Building.pdf7 Nov 2025
Withdrawal Update Form 3File: Form 3 - Q 2 - 30-09-2025 A Building.pdf7 Nov 2025
Withdrawal Update Form 1File: From 1 A Building.pdf28 Aug 2025
Withdrawal Update Form 2File: 32 NC BLDGA ENGG CERTIFICATE FORM 2 30062025 1.pdf28 Aug 2025
Withdrawal Update Form 3File: 19 Nandan Carnival A Building.pdf28 Aug 2025
Certificates of CA (Form 3)File: 3 a Building A - 31-03-2025.pdf26 Jun 2025
Disclosure of sold/ booked inventoryFile: 3 A - 31-03-2025.pdf26 Jun 2025
Disclosure for secured/unsecured finance availed for the projectFile: A - 31-03-2025.pdf23 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NC A Architect Certificate 31032025.pdf11 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 31 NC BLDG A ENGG CERTIFICATE FORM 2 31032025.pdf11 Jun 2025
Layout approvalFile: Layout PLAN A.pdf4 Jun 2025
Building plan approvalFile: BUILDING A FSI.pdf4 Jun 2025
Copy of Layout Approval (in case of layout)File: Layout PLAN A.pdf4 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: NCAR Revised NMC CC 18082023.pdf4 Jun 2025
Building Plan Approval (IOD)File: BUILDING A FSI.pdf4 Jun 2025
Declaration about Commencement CertificateFile: Declaration about CC Bld A.pdf4 Jun 2025
Other - TechnicalFile: Building A.pdf4 Jun 2025
Layout approvalFile: Sanction Highlighted a Build.pdf28 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction Highlighted a Build.pdf28 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 21 NC A Architect Certificate 31 12 2024.pdf28 Mar 2025
Certificates of CA (Form 3)File: nandan Carnival Building A Form-3 dec 24_Final.pdf24 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BLDG-A ENGG CERTIFICATE FORM 2 Dec 24.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: Building A Dec 24.pdf24 Mar 2025
Declaration in FORM BFile: 01 Format B Building A.pdf26 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A A.pdf25 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20 NC A Architect Certificate 30-09-2024.pdf23 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 19 NC A Architect Certificate 30-06-2024.pdf23 Dec 2024
Certificates of CA (Form 3)File: 4 From 3 Bld A_31-03-22.pdf23 Dec 2024
Certificates of CA (Form 3)File: 14 From 3 Bld A_30-09-24.pdf23 Dec 2024
Certificates of CA (Form 3)File: 13 From 3 Bld A-30-06-24.pdf23 Dec 2024
Certificates of CA (Form 3)File: 12 From 3 Bld A_31-03-24.pdf23 Dec 2024
Certificates of CA (Form 3)File: 11 From 3 Bld A_31-12-23.pdf23 Dec 2024
Certificates of CA (Form 3)File: 10 From 3 Bld A_30-09-23.pdf23 Dec 2024
Certificates of CA (Form 3)File: 9 From 3 Bld A_30-06-23.pdf23 Dec 2024
Certificates of CA (Form 3)File: 7 From 3 Bld A_31-12-22.pdf23 Dec 2024
Certificates of CA (Form 3)File: 6 From 3 Bld A_30-09-22.pdf23 Dec 2024
Certificates of CA (Form 3)File: 5 From 3 Bld A_30-06-22.pdf23 Dec 2024
Certificates of CA (Form 3)File: 8 From 3 Bld A_31-03-23.pdf23 Dec 2024
Certificates of CA (Form 3)File: 3 From 3 Bld A_31-12-21.pdf23 Dec 2024
Certificates of CA (Form 3)File: 2 From 3 Bld A_30-09-21.pdf23 Dec 2024
Certificates of CA (Form 3)File: 1 From 3 Bld A_30-06-21 (1).pdf23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 25 NC BLDG-A ENGG CERTIFICATE FORM 2 30 09 2023.pdf23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 26 NC BLDG-A ENGG CERTIFICATE FORM 2 31 12 2023.pdf23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 27 NC BLDG-A ENGG CERTIFICATE FORM 2 31 03 2024.pdf23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 28 NC BLDG-A ENGG CERTIFICATE FORM 2 30 06 2024.pdf23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 29 NC BLDG-A ENGG CERTIFICATE FORM 2 30 09 2024.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5 _ Build_A_19-12-24.pdf21 Dec 2024
Disclosure of sold/ booked inventoryFile: A-Q2_30-09-24.pdf17 Dec 2024
Disclosure of sold/ booked inventoryFile: A-Q1_30-06-24.pdf17 Dec 2024
Disclosure of sold/ booked inventoryFile: A-Q4_31-03-24.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A-Q2_30-09-24.pdf16 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: A-Q1_30-06-24.pdf16 Dec 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NANDAN EUPHORASR NO 47 HISSA 1A HAWALDARA MALA DHANORI PUNE 411015130CompletedFeb 2015Feb 2015

How this compares with Nashik

9%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 99 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NANDAN CARNIVAL A BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ADGAON4,100+ in Nashik

2 kmNANDAN CARNIVAL A BUILDICompleted 4Lapsed / revoked 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: NANDAN BUILDCON PVT LTD

NANDAN BUILDCON PVT LTD has 3 registrations on MahaRERA, including NANDAN CARNIVAL A BUILDING and NANDAN CARNIVAL B BUILDING. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if NANDAN CARNIVAL A BUILDING is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NANDAN CARNIVAL A BUILDING?

The registered promoter entity is NANDAN BUILDCON PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NANDAN CARNIVAL A BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NANDAN CARNIVAL A BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NANDAN CARNIVAL A BUILDING?

The professionals named in the filing: Architect: DISIGN SQUARE ASSOCIATES; Architect: RAVI AMRUTKAR AND ASSOCIATES; Engineer: LAXMAN AFRANDE; Engineer: NILESH CHAUDHARY; Chartered Accountant: P B D & CO. CHARTERED ACCOUNTANTS; Chartered Accountant: JAGDISHKUMAR AMRUTLAL PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NANDAN CARNIVAL A BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NANDAN CARNIVAL A BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NANDAN CARNIVAL A BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.